5/3/2023 1:57:33 PM
|
Submission request sent to Applicant
|
|
4/11/2023 8:31:00 AM
|
Submission request sent to Applicant
|
|
9/22/2022 10:39:14 AM
|
Project Closed
|
|
9/22/2022 10:39:14 AM
|
Project Approved: 9/22/2022
|
|
9/13/2022 12:56:16 PM
|
Request for Review Comments returned by PCD Project Manager
|
|
9/13/2022 11:47:06 AM
|
Request for Review Comments returned by PCD Engineering Division
|
|
8/30/2022 2:46:35 PM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Kari Parsons on behalf of PCD Project Manager
|
|
8/30/2022 2:46:32 PM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
|
8/30/2022 9:33:29 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Kari Parsons on behalf of PCD Project Manager
|
|
8/30/2022 9:33:27 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
|
8/30/2022 9:22:01 AM
|
Submission Triaged
|
|
8/30/2022 9:18:50 AM
|
Submission received from Applicant
|
|
8/16/2022 10:56:54 AM
|
Submission request sent to Applicant
|
|
8/16/2022 10:50:43 AM
|
Request for Review Comments returned by PCD Project Manager
|
|
8/15/2022 7:33:36 AM
|
Request for Review Comments returned by PCD Engineering Division
|
|
8/3/2022 1:56:54 PM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Kari Parsons on behalf of PCD Project Manager
|
|
8/3/2022 1:56:51 PM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
|
8/3/2022 1:55:31 PM
|
Submission Triaged
|
|
8/3/2022 1:17:32 PM
|
Submission received from Applicant
|
|
8/3/2022 7:07:55 AM
|
Submission request sent to Applicant
|
|
8/2/2022 2:10:41 PM
|
Submission request sent to Applicant
|
|
8/2/2022 10:42:06 AM
|
Request for Review Comments returned by County Attorney - Development Review
|
|
7/25/2022 7:14:50 AM
|
Request for Review Comments returned by PCD Project Manager
|
|
7/20/2022 5:44:37 PM
|
Request for Review Comments returned by PCD Engineering Division
|
|
7/20/2022 10:27:31 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Lori Seago on behalf of County Attorney - Development Review
|
|
7/20/2022 10:26:19 AM
|
Submission Triaged
|
|
7/20/2022 10:12:00 AM
|
Submission received from Applicant
|
|
7/20/2022 10:09:39 AM
|
Submission request sent to Applicant
|
|
7/20/2022 10:08:16 AM
|
Submission Triaged
|
|
7/20/2022 9:52:55 AM
|
Submission received from Applicant
|
|
7/20/2022 7:15:50 AM
|
Submission request sent to Applicant
|
|
7/20/2022 7:15:06 AM
|
Submission Triaged
|
|
7/20/2022 6:29:40 AM
|
Submission received from Applicant
|
|
7/19/2022 10:51:35 AM
|
Submission request sent to Applicant
|
|
7/19/2022 9:31:13 AM
|
Request for Review Comments returned by County Attorney - Development Review
|
|
7/13/2022 10:22:53 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
|
6/29/2022 8:41:17 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
|
6/29/2022 8:41:15 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Lori Seago on behalf of County Attorney - Development Review
|
|
6/29/2022 8:41:12 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Kari Parsons on behalf of PCD Project Manager
|
|
6/29/2022 8:41:09 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
|
6/29/2022 8:39:39 AM
|
Submission Triaged
|
|
6/28/2022 12:43:14 PM
|
Submission received from Applicant
|
|
5/5/2022 3:56:07 PM
|
Submission request sent to Applicant
|
|
5/5/2022 3:55:02 PM
|
Request for Review Comments returned by PCD Project Manager
|
|
5/5/2022 2:40:20 PM
|
Request for Review Comments returned by PCD Engineering Division
|
|
4/20/2022 9:39:12 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
|
4/19/2022 2:26:58 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
|
4/1/2022 12:15:33 PM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
|
4/1/2022 12:15:30 PM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Lori Seago on behalf of County Attorney - Development Review
|
|
4/1/2022 12:15:27 PM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Kari Parsons on behalf of PCD Project Manager
|
|
4/1/2022 12:15:24 PM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
|
4/1/2022 12:12:30 PM
|
Submission Triaged
|
|
4/1/2022 11:00:56 AM
|
Submission received from Applicant
|
|
3/19/2022 9:17:00 PM
|
Request for Review Comments returned by EPC Health Department
|
|
3/9/2022 4:26:51 PM
|
Request for Review Comments returned by Parks Advisory Board
|
|
3/1/2022 7:35:26 AM
|
Submission request sent to Applicant
|
|
3/1/2022 7:32:13 AM
|
Request for Review Comments returned by PCD Project Manager
|
|
3/1/2022 7:24:38 AM
|
Request for Review Comments returned by PCD Engineering Division
|
|
2/28/2022 9:30:36 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
|
2/25/2022 8:03:46 AM
|
Request for Review Comments returned by PCD Administrative
|
|
2/21/2022 12:50:59 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
|
2/18/2022 9:33:28 AM
|
Request for Review Comments returned by Colorado Geological Survey
|
|
2/18/2022 7:21:02 AM
|
Request for Review Comments returned by Public Service Company of Colorado dba X-cel Energy
|
|
2/17/2022 2:24:22 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
|
2/17/2022 7:11:07 AM
|
Request for Review Comments returned by EPC Parks Department
|
|
2/16/2022 3:38:37 PM
|
Request for Review Comments returned by Widefield SD 3
|
|
2/16/2022 12:58:32 PM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Elena Krebs on behalf of PCD Administrative
|
|
2/14/2022 12:11:50 PM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
|
2/10/2022 2:43:51 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
|
2/9/2022 1:59:49 PM
|
Request for Review Comments returned by Colorado Parks and Wildlife
|
|
2/4/2022 10:07:58 AM
|
Request for Review Comments returned by EPC Environmental Services
|
|
2/3/2022 7:33:33 AM
|
Request for Review Comments returned by US Postal Service
|
|
2/2/2022 6:27:06 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
|
1/31/2022 2:25:31 PM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
|
1/31/2022 2:25:24 PM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Kari Parsons on behalf of PCD Project Manager
|
|
1/31/2022 2:25:22 PM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
|
1/31/2022 10:26:43 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Brandon Bernard on behalf of Widefield Water & San
|
|
1/31/2022 10:26:40 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by COO Dave Gish on behalf of Widefield SD 3
|
|
1/31/2022 10:26:38 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by on behalf of Security Fire Protection District
|
|
1/31/2022 10:26:36 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Donna George on behalf of Public Service Company of Colorado dba X-cel Energy
|
|
1/31/2022 10:26:34 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by William Feller on behalf of Peaceful Valley Lake Estates HOA
|
|
1/31/2022 10:26:32 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by General Email on behalf of Mountain View Electric Association, Inc.
|
|
1/31/2022 10:26:29 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Roger Austin on behalf of Mountain Metro Transit (City of COS)
|
|
1/31/2022 10:26:27 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Jeff Mark on behalf of Lorson Ranch Metro
|
|
1/31/2022 10:26:25 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Joel Stahn on behalf of Fountain Valley Power
|
|
1/31/2022 10:26:23 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Katie Carleo on behalf of Colorado Springs Planning & Community Development
|
|
1/31/2022 10:26:17 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Bea Romero on behalf of CenturyLink
|
|
1/31/2022 10:26:15 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
|
1/31/2022 10:26:12 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
|
1/31/2022 10:26:10 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
|
1/31/2022 10:26:08 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Elaine Kelly on behalf of US Postal Service
|
|
1/31/2022 10:26:06 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Tim Kroening on behalf of Colorado Parks and Wildlife
|
|
1/31/2022 10:25:50 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
|
1/31/2022 10:25:48 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
|
1/31/2022 10:25:46 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Michael Diehl on behalf of Xcel Energy
|
|
1/31/2022 10:25:44 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by on behalf of Parks Advisory Board
|
|
1/31/2022 10:25:42 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
|
1/31/2022 10:25:35 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Bill Elder on behalf of EPC Sheriff's Department
|
|
1/31/2022 10:25:33 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Bill Elder on behalf of EPC Sheriff's Department
|
|
1/31/2022 10:25:31 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by on behalf of EPC Parks Department
|
|
1/31/2022 10:25:29 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Catherine McGarvy on behalf of EPC Health Department
|
|
1/31/2022 10:25:17 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Kathy Andrew on behalf of EPC Environmental Services
|
|
1/31/2022 10:25:15 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Lori Seago on behalf of County Attorney - Development Review
|
|
1/31/2022 10:25:09 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Kari Parsons on behalf of PCD Project Manager
|
|
1/31/2022 10:25:06 AM
|
Request for Review Comments email sent for Project The Ridge at Lorson Ranch Fil No. 2 for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
|
1/31/2022 10:17:35 AM
|
Fees paid: 1/31/2022 (Receipt: 1005722)
|
|
1/31/2022 10:03:00 AM
|
Payment Request sent: 1/31/2022
|
|
1/31/2022 10:03:00 AM
|
File # Assigned: SF225
|
|
1/31/2022 10:02:50 AM
|
Submission Triaged
|
|
1/31/2022 9:59:37 AM
|
Submission received from Applicant
|
|
10/21/2021 3:24:47 PM
|
Submission request sent to Applicant
|
|
10/21/2021 3:22:46 PM
|
Project Manager Assigned: Kari Parsons
|
|
10/21/2021 3:22:45 PM
|
EA Assigned: EA20166
|
|
10/21/2021 3:22:45 PM
|
Project Created
|