Project Details

Search


File Number
OAR2198
Project Name
SUBMITTAL - Corvallis Preliminary Plat and 30% Construction Drawings
Description
The Applicant for the Corvallis development has submitted the Phase 1 Preliminary Plat and 30% Construction Drawings
Parcels
5500000401 5500000401
Applicant
CIty of Fountain
Planning Supervisor Kristy Martinez ( Kristy@fountaincolorado.org )
(719) 322-2015
Planning Supervisor Kristy Martinez ( Kristy@fountaincolorado.org )
(719) 322-2015
File Prefix
OAR - Outside Agency Review
Year
2021
Project Manager
Mercedes Rivas
Status
Closed
Created
9/30/2021 4:10:17 PM

View: Review Comments


Approved Documents (1)

Link Document
View Review Comments


Review Documents (5)

Link Document Date
View Buck slip 9/30/2021 4:23:26 PM
View Final Plat Drawings 9/30/2021 4:23:22 PM
View Drainage Report - Final 9/30/2021 4:23:16 PM
View Traffic Impact Study 9/30/2021 4:23:25 PM
View letter addressing the County’s comments 12/2/2021 3:44:15 PM



Events (16)

Date Comment
12/21/2021 7:26:12 AM Project Closed
12/21/2021 7:26:12 AM Project Approved: 12/21/2021
12/20/2021 1:03:33 PM Request for Review Comments returned by PCD Engineering Division
12/16/2021 3:54:39 PM Request for Review Comments returned by PCD Project Manager
12/2/2021 3:45:16 PM Request for Review Comments email sent for Project SUBMITTAL - Corvallis Preliminary Plat and 30% Construction Drawings for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
12/2/2021 3:45:13 PM Request for Review Comments email sent for Project SUBMITTAL - Corvallis Preliminary Plat and 30% Construction Drawings for review by Mercedes Rivas on behalf of PCD Project Manager
12/2/2021 3:45:09 PM Request for Review Comments email sent for Project SUBMITTAL - Corvallis Preliminary Plat and 30% Construction Drawings for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
10/18/2021 5:44:33 PM Request for Review Comments returned by PCD Project Manager
10/18/2021 3:13:43 PM Request for Review Comments returned by PCD Engineering Division
9/30/2021 4:23:59 PM Request for Review Comments email sent for Project SUBMITTAL - Corvallis Preliminary Plat and 30% Construction Drawings for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
9/30/2021 4:23:57 PM Request for Review Comments email sent for Project SUBMITTAL - Corvallis Preliminary Plat and 30% Construction Drawings for review by Mercedes Rivas on behalf of PCD Project Manager
9/30/2021 4:23:55 PM Request for Review Comments email sent for Project SUBMITTAL - Corvallis Preliminary Plat and 30% Construction Drawings for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
9/30/2021 4:10:22 PM No Fees
9/30/2021 4:10:22 PM File # Assigned: OAR2198
9/30/2021 4:10:21 PM Project Manager Assigned: Mercedes Rivas
9/30/2021 4:10:21 PM Project Created