6/8/2022 10:09:31 AM
|
Project Closed
|
6/8/2022 10:09:31 AM
|
Project Approved: 6/8/2022
|
6/8/2022 8:54:05 AM
|
Project reopened for Review Comments
|
6/8/2022 8:53:33 AM
|
Request for Approval returned by PCD Project Manager
|
6/8/2022 8:52:53 AM
|
Request for Approval sent for Project WISP TOWER, Special Use for review by Matthew Fitzsimmons on behalf of PCD Project Manager
|
6/8/2022 8:48:07 AM
|
Project reopened for Approval requests
|
6/2/2022 2:54:18 PM
|
Project Closed
|
6/2/2022 2:54:18 PM
|
Project Approved: 6/2/2022
|
5/23/2022 9:02:32 AM
|
Request for Review Comments returned by PCD Project Manager
|
5/23/2022 9:00:47 AM
|
Request for Review Comments email resent for Project WISP TOWER, Special Use for review by Matthew Fitzsimmons on behalf of PCD Project Manager
|
5/23/2022 8:51:44 AM
|
Request for Review Comments returned by PCD Project Manager
|
5/14/2022 10:23:12 PM
|
Request for Review Comments returned by EPC Health Department
|
5/12/2022 9:04:05 AM
|
Project Manager Assigned: Matthew Fitzsimmons
|
5/3/2022 11:53:35 AM
|
Request for Review Comments returned by PCD Engineering Division
|
4/29/2022 11:30:05 AM
|
Request for Review Comments email sent for Project WISP TOWER, Special Use for review by Kylie Bagley on behalf of PCD Project Manager
|
4/29/2022 11:30:03 AM
|
Request for Review Comments email sent for Project WISP TOWER, Special Use for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
4/29/2022 11:26:44 AM
|
Submission Triaged
|
4/27/2022 4:27:30 PM
|
Submission received from Applicant
|
4/22/2022 1:51:23 PM
|
Submission request sent to Applicant
|
4/22/2022 1:50:48 PM
|
Request for Review Comments returned by PCD Project Manager
|
4/20/2022 8:51:09 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
4/18/2022 1:25:55 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
4/13/2022 4:12:57 PM
|
Request for Review Comments returned by PCD Engineering Division
|
4/8/2022 10:52:53 AM
|
Request for Review Comments returned by Ellicott Fire Protection District
|
4/4/2022 8:00:10 AM
|
Request for Review Comments returned by PCD Administrative Notice
|
3/31/2022 8:21:07 AM
|
Request for Review Comments email sent for Project WISP TOWER, Special Use for review by General Email on behalf of Mountain View Electric Association, Inc.
|
3/31/2022 8:21:05 AM
|
Request for Review Comments email sent for Project WISP TOWER, Special Use for review by Bookkeeper Peggy Current on behalf of Ellicott Metro
|
3/31/2022 8:21:04 AM
|
Request for Review Comments email sent for Project WISP TOWER, Special Use for review by Michael Henley on behalf of Ellicott Fire Protection District
|
3/31/2022 8:21:03 AM
|
Request for Review Comments email sent for Project WISP TOWER, Special Use for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
3/31/2022 8:21:02 AM
|
Request for Review Comments email sent for Project WISP TOWER, Special Use for review by Catherine McGarvy on behalf of EPC Health Department
|
3/31/2022 8:20:46 AM
|
Request for Review Comments email sent for Project WISP TOWER, Special Use for review by Kylie Bagley on behalf of PCD Project Manager
|
3/31/2022 8:20:45 AM
|
Request for Review Comments email sent for Project WISP TOWER, Special Use for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
3/31/2022 8:20:41 AM
|
Request for Review Comments email sent for Project WISP TOWER, Special Use for review by Elena Krebs on behalf of PCD Administrative Notice
|
3/31/2022 8:20:40 AM
|
Request for Review Comments email sent for Project WISP TOWER, Special Use for review by Mindy Madden on behalf of EPC Code Enforcement Inspections
|
3/29/2022 3:38:17 PM
|
Project Manager Assigned: Kylie Bagley
|
3/28/2022 8:50:47 AM
|
Fees paid: 3/28/2022 (Receipt: 1006061)
|
3/27/2022 10:09:23 AM
|
Payment Request sent: 3/27/2022
|
3/27/2022 10:09:23 AM
|
File # Assigned: AL222
|
3/27/2022 10:09:20 AM
|
Submission Triaged
|
3/24/2022 6:27:27 PM
|
Submission received from Applicant
|
3/24/2022 9:49:06 AM
|
Submission request sent to Applicant
|
3/24/2022 9:48:58 AM
|
Submission Triaged
|
3/24/2022 9:05:12 AM
|
Submission received from Applicant
|
11/8/2021 2:29:34 PM
|
Submission request sent to Applicant
|
11/8/2021 2:27:54 PM
|
Submission request sent to Applicant
|
9/21/2021 8:23:44 AM
|
Project Manager Assigned: Mercedes Rivas
|
9/21/2021 8:23:44 AM
|
EA Assigned: EA21162
|
9/21/2021 8:23:44 AM
|
Project Created
|