5/3/2024 4:18:24 PM
|
Project Closed
|
5/3/2024 4:18:24 PM
|
Project Approved: 5/3/2024
|
5/3/2024 4:17:52 PM
|
Project Ready for Approval requests. Review Comment period is complete.
|
4/30/2024 3:36:51 PM
|
Request for Review Comments returned by PCD Engineering Division
|
4/25/2024 4:22:02 PM
|
Request for Review Comments sent for Project Colorado Kids Ranch - Pumpkin Patch Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
|
4/25/2024 4:21:15 PM
|
Submission Triaged
|
4/25/2024 3:54:59 PM
|
Submission received from Applicant
|
4/25/2024 3:46:26 PM
|
Submission request sent to Applicant
|
4/25/2024 3:40:59 PM
|
Request for Review Comments returned by PCD Engineering Division
|
4/18/2024 9:51:12 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
4/12/2024 8:52:28 AM
|
Request for Review Comments email sent for Project Colorado Kids Ranch - Pumpkin Patch Site Development Plan for review by Shannon Mustoe on behalf of EPC Stormwater Review
|
4/12/2024 8:52:26 AM
|
Request for Review Comments email sent for Project Colorado Kids Ranch - Pumpkin Patch Site Development Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
4/12/2024 8:52:24 AM
|
Request for Review Comments email sent for Project Colorado Kids Ranch - Pumpkin Patch Site Development Plan for review by Glenn Reese on behalf of EPC Stormwater Review
|
4/12/2024 8:52:23 AM
|
Request for Review Comments email sent for Project Colorado Kids Ranch - Pumpkin Patch Site Development Plan for review by Christina Prete on behalf of EPC Stormwater Review
|
4/12/2024 8:52:19 AM
|
Request for Review Comments email sent for Project Colorado Kids Ranch - Pumpkin Patch Site Development Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
|
4/12/2024 8:52:17 AM
|
Request for Review Comments email sent for Project Colorado Kids Ranch - Pumpkin Patch Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
|
4/12/2024 8:49:34 AM
|
Submission Triaged
|
4/12/2024 8:48:56 AM
|
Submission received from Applicant
|
4/12/2024 8:44:57 AM
|
Submission request sent to Applicant
|
4/12/2024 8:44:14 AM
|
Submission Triaged
|
4/11/2024 9:21:52 PM
|
Submission received from Applicant
|
4/11/2024 3:53:13 PM
|
Submission request sent to Applicant
|
3/20/2024 5:09:14 PM
|
Submission request sent to Applicant
|
3/20/2024 3:37:44 PM
|
Request for Review Comments returned by PCD Engineering Division
|
3/19/2024 4:07:27 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
3/19/2024 12:44:11 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
3/18/2024 10:55:20 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
3/15/2024 9:34:40 AM
|
Request for Review Comments returned by PCD Project Manager
|
3/5/2024 9:11:18 AM
|
Request for Review Comments email sent for Project Colorado Kids Ranch - Pumpkin Patch Site Development Plan for review by General Email on behalf of Mountain View Electric Association, Inc.
|
3/5/2024 9:11:16 AM
|
Request for Review Comments email sent for Project Colorado Kids Ranch - Pumpkin Patch Site Development Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
3/5/2024 9:11:14 AM
|
Request for Review Comments email sent for Project Colorado Kids Ranch - Pumpkin Patch Site Development Plan for review by Glenn Reese on behalf of EPC Stormwater Review
|
3/5/2024 9:11:12 AM
|
Request for Review Comments email sent for Project Colorado Kids Ranch - Pumpkin Patch Site Development Plan for review by Christina Prete on behalf of EPC Stormwater Review
|
3/5/2024 9:11:10 AM
|
Request for Review Comments email sent for Project Colorado Kids Ranch - Pumpkin Patch Site Development Plan for review by Lori Seago on behalf of County Attorney - Development Review
|
3/5/2024 9:11:08 AM
|
Request for Review Comments email sent for Project Colorado Kids Ranch - Pumpkin Patch Site Development Plan for review by April Willie on behalf of County Attorney - Development Review
|
3/5/2024 9:11:02 AM
|
Request for Review Comments email sent for Project Colorado Kids Ranch - Pumpkin Patch Site Development Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
|
3/5/2024 9:11:01 AM
|
Request for Review Comments email sent for Project Colorado Kids Ranch - Pumpkin Patch Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
|
3/5/2024 9:09:10 AM
|
Submission Triaged
|
3/4/2024 2:35:15 PM
|
Submission received from Applicant
|
2/16/2024 6:07:55 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
2/16/2024 7:41:54 AM
|
Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
|
2/2/2024 2:05:56 PM
|
Submission request sent to Applicant
|
2/2/2024 1:56:05 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
2/2/2024 9:11:44 AM
|
Request for Review Comments email sent for Project Colorado Kids Ranch - Pumpkin Patch Site Development Plan for review by Lori Seago on behalf of County Attorney - Development Review
|
2/2/2024 9:11:42 AM
|
Request for Review Comments email sent for Project Colorado Kids Ranch - Pumpkin Patch Site Development Plan for review by April Willie on behalf of County Attorney - Development Review
|
2/1/2024 4:51:28 PM
|
Request for Review Comments returned by PCD Project Manager
|
2/1/2024 4:51:15 PM
|
Request for Review Comments returned by PCD Engineering Division
|
2/1/2024 2:52:34 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
2/1/2024 8:45:34 AM
|
Request for Review Comments returned by RBD Floodplain
|
2/1/2024 8:31:23 AM
|
Request for Review Comments email sent for Project Colorado Kids Ranch - Pumpkin Patch Site Development Plan for review by Keith Curtis on behalf of RBD Floodplain
|
1/31/2024 9:51:10 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
1/18/2024 2:11:56 PM
|
Request for Review Comments email sent for Project Colorado Kids Ranch - Pumpkin Patch Site Development Plan for review by Jamey Bumgarner on behalf of Tri-Lakes-Monument Fire Protection District
|
1/18/2024 2:11:54 PM
|
Request for Review Comments email sent for Project Colorado Kids Ranch - Pumpkin Patch Site Development Plan for review by General Email on behalf of Mountain View Electric Association, Inc.
|
1/18/2024 2:11:52 PM
|
Request for Review Comments email sent for Project Colorado Kids Ranch - Pumpkin Patch Site Development Plan for review by on behalf of Pikes Peak Regional Building Department
|
1/18/2024 2:11:50 PM
|
Request for Review Comments email sent for Project Colorado Kids Ranch - Pumpkin Patch Site Development Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
1/18/2024 2:11:48 PM
|
Request for Review Comments email sent for Project Colorado Kids Ranch - Pumpkin Patch Site Development Plan for review by Glenn Reese on behalf of EPC Stormwater Review
|
1/18/2024 2:11:46 PM
|
Request for Review Comments email sent for Project Colorado Kids Ranch - Pumpkin Patch Site Development Plan for review by Christina Prete on behalf of EPC Stormwater Review
|
1/18/2024 2:11:40 PM
|
Request for Review Comments email sent for Project Colorado Kids Ranch - Pumpkin Patch Site Development Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
|
1/18/2024 2:11:38 PM
|
Request for Review Comments email sent for Project Colorado Kids Ranch - Pumpkin Patch Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
|
1/18/2024 2:10:33 PM
|
Submission Triaged
|
1/18/2024 12:00:07 PM
|
Submission received from Applicant
|
9/19/2023 12:38:19 PM
|
Submission request sent to Applicant
|
9/19/2023 7:25:55 AM
|
Submission request sent to Applicant
|
9/19/2023 7:24:45 AM
|
Set Applicant to Vertex Consulting Services
|
11/23/2022 8:58:28 AM
|
Project Manager Assigned: Ryan Howser
|
10/20/2022 3:44:22 PM
|
Request for Review Comments returned by PCD Project Manager
|
10/17/2022 10:30:28 AM
|
Request for Review Comments email sent for Project 18065 Saddlewood Road Agritainment for review by Planner Dan Feuerbach on behalf of PCD Project Manager
|
10/17/2022 10:29:50 AM
|
Project Manager Assigned: Planner Dan Feuerbach
|
8/23/2022 5:30:05 PM
|
Submission request sent to Applicant
|
8/6/2022 9:39:46 PM
|
Request for Review Comments returned by EPC Health Department
|
7/20/2022 5:48:47 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
7/19/2022 10:01:38 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
7/19/2022 8:40:53 AM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
7/18/2022 3:39:42 PM
|
Request for Review Comments returned by PCD Project Manager
|
7/18/2022 3:06:20 PM
|
Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
|
7/14/2022 8:22:02 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
7/11/2022 4:18:14 PM
|
Request for Review Comments returned by PCD Engineering Division
|
6/30/2022 11:07:04 AM
|
Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
|
6/29/2022 1:17:22 PM
|
Request for Review Comments returned by PCD Administrative Notice
|
6/29/2022 8:58:59 AM
|
Request for Review Comments email sent for Project 18065 Saddlewood Road Agritainment for review by on behalf of PCD Administrative Notice
|
6/29/2022 8:58:03 AM
|
Project Manager Assigned: Matthew Fitzsimmons
|
6/28/2022 8:34:01 AM
|
Request for Review Comments email sent for Project 18065 Saddlewood Road Agritainment for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
6/28/2022 8:33:03 AM
|
Request for Review Comments email sent for Project 18065 Saddlewood Road Agritainment for review by Division Chief Jamey Bumgarner on behalf of Tri-Lakes-Monument Fire Protection District
|
6/28/2022 8:33:02 AM
|
Request for Review Comments email sent for Project 18065 Saddlewood Road Agritainment for review by General Email on behalf of Mountain View Electric Association, Inc.
|
6/28/2022 8:33:00 AM
|
Request for Review Comments email sent for Project 18065 Saddlewood Road Agritainment for review by District Manager Pamela Davison on behalf of El Paso County Conservation Dist
|
6/28/2022 8:32:59 AM
|
Request for Review Comments email sent for Project 18065 Saddlewood Road Agritainment for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
6/28/2022 8:32:58 AM
|
Request for Review Comments email sent for Project 18065 Saddlewood Road Agritainment for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
6/28/2022 8:32:57 AM
|
Request for Review Comments email sent for Project 18065 Saddlewood Road Agritainment for review by CDOT Permits Manager Valerie Vigil on behalf of Colorado Department of Transportation - Pueblo Office
|
6/28/2022 8:32:53 AM
|
Request for Review Comments email sent for Project 18065 Saddlewood Road Agritainment for review by Catherine McGarvy on behalf of EPC Health Department
|
6/28/2022 8:32:46 AM
|
Request for Review Comments email sent for Project 18065 Saddlewood Road Agritainment for review by Ashlyn Mathy on behalf of PCD Project Manager
|
6/28/2022 8:32:44 AM
|
Request for Review Comments email sent for Project 18065 Saddlewood Road Agritainment for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
6/24/2022 3:06:09 PM
|
Fees paid: 6/24/2022 (Receipt: 1006540)
|
6/20/2022 12:29:14 PM
|
Project Manager Assigned: Ashlyn Mathy
|
6/20/2022 12:28:53 PM
|
Payment Request sent: 6/20/2022
|
6/20/2022 12:28:53 PM
|
File # Assigned: PPR2235
|
6/20/2022 12:28:50 PM
|
Submission Triaged
|
6/16/2022 12:16:53 PM
|
Submission received from Applicant
|
1/26/2022 4:38:53 PM
|
Submission request sent to Applicant
|
9/16/2021 9:15:56 AM
|
Submission request sent to Applicant
|
9/16/2021 9:15:48 AM
|
Submission Triaged
|
9/15/2021 3:26:16 PM
|
Submission received from Applicant
|
8/19/2021 2:05:17 PM
|
Submission request sent to Applicant
|
8/19/2021 2:04:26 PM
|
Project Manager Assigned: John Green
|
8/19/2021 2:04:26 PM
|
EA Assigned: EA18109
|
8/19/2021 2:04:26 PM
|
Project Created
|