7/14/2022 2:43:11 PM
|
Project Closed
|
7/14/2022 2:43:11 PM
|
Project Approved: 7/14/2022
|
7/13/2022 10:42:42 AM
|
Request for Review Comments returned by PCD Project Manager
|
7/6/2022 3:38:35 PM
|
Request for Review Comments returned by PCD Engineering Division
|
6/20/2022 9:14:14 AM
|
Request for Review Comments email sent for Project Black Forest Meadows Site Development Plan for review by Kylie Bagley on behalf of PCD Project Manager
|
6/20/2022 9:14:12 AM
|
Request for Review Comments email sent for Project Black Forest Meadows Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
6/20/2022 9:11:52 AM
|
Submission Triaged
|
6/13/2022 7:44:53 PM
|
Submission received from Applicant
|
6/13/2022 2:39:45 PM
|
Submission request sent to Applicant
|
6/13/2022 2:39:21 PM
|
Request for Review Comments returned by PCD Project Manager
|
6/8/2022 10:34:19 AM
|
Request for Review Comments returned by PCD Engineering Division
|
5/20/2022 3:30:32 PM
|
Request for Review Comments email sent for Project Black Forest Meadows Site Development Plan for review by Kylie Bagley on behalf of PCD Project Manager
|
5/20/2022 3:30:30 PM
|
Request for Review Comments email sent for Project Black Forest Meadows Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
5/20/2022 3:24:30 PM
|
Submission Triaged
|
5/18/2022 2:51:55 PM
|
Submission received from Applicant
|
5/18/2022 10:32:29 AM
|
Submission request sent to Applicant
|
5/13/2022 8:32:09 AM
|
Submission Triaged
|
5/12/2022 9:20:26 AM
|
Submission received from Applicant
|
5/10/2022 12:13:57 PM
|
Project Manager Assigned: Kylie Bagley
|
5/9/2022 5:11:29 PM
|
Submission request sent to Applicant
|
5/9/2022 5:11:11 PM
|
Request for Review Comments returned by PCD Project Manager
|
4/27/2022 3:10:13 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
4/26/2022 12:03:39 PM
|
Request for Review Comments returned by PCD Engineering Division
|
4/25/2022 10:44:37 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
4/12/2022 10:04:06 AM
|
Project Manager Assigned: Nina Ruiz
|
4/7/2022 10:16:26 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
4/6/2022 10:11:42 AM
|
Request for Review Comments email sent for Project Black Forest Meadows Site Development Plan for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
4/6/2022 10:11:40 AM
|
Request for Review Comments email sent for Project Black Forest Meadows Site Development Plan for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
4/6/2022 10:11:38 AM
|
Request for Review Comments email sent for Project Black Forest Meadows Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
4/6/2022 10:11:36 AM
|
Request for Review Comments email sent for Project Black Forest Meadows Site Development Plan for review by Catherine McGarvy on behalf of EPC Health Department
|
4/6/2022 10:11:25 AM
|
Request for Review Comments email sent for Project Black Forest Meadows Site Development Plan for review by John Green on behalf of PCD Project Manager
|
4/6/2022 10:11:23 AM
|
Request for Review Comments email sent for Project Black Forest Meadows Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
4/6/2022 10:10:32 AM
|
Submission Triaged
|
4/5/2022 3:27:37 PM
|
Submission received from Applicant
|
11/15/2021 9:03:45 PM
|
Request for Review Comments returned by EPC Health Department
|
10/27/2021 3:53:28 PM
|
Submission request sent to Applicant
|
10/27/2021 3:52:54 PM
|
Request for Review Comments returned by PCD Project Manager
|
10/27/2021 3:52:01 PM
|
Request for Review Comments email resent for Project Black Forest Meadows Site Development Plan for review by John Green on behalf of PCD Project Manager
|
10/27/2021 3:48:14 PM
|
Request for Review Comments returned by PCD Project Manager
|
10/26/2021 8:23:58 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
10/25/2021 4:55:58 PM
|
Request for Review Comments returned by PCD Engineering Division
|
10/25/2021 10:32:44 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
10/22/2021 2:17:00 PM
|
Request for Review Comments returned by EPC Parks Department
|
10/21/2021 11:40:47 AM
|
Request for Review Comments returned by Colorado Parks and Wildlife
|
10/21/2021 8:20:59 AM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
10/18/2021 1:46:26 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
10/14/2021 6:26:59 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
10/12/2021 10:42:36 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
10/8/2021 11:39:32 AM
|
Request for Review Comments returned by EPC Environmental Services
|
10/5/2021 10:33:39 AM
|
Request for Review Comments email sent for Project Black Forest Meadows Site Development Plan for review by General Email on behalf of Mountain View Electric Association, Inc.
|
10/5/2021 10:33:37 AM
|
Request for Review Comments email sent for Project Black Forest Meadows Site Development Plan for review by Melissa Andrews on behalf of Falcon School District 49
|
10/5/2021 10:33:35 AM
|
Request for Review Comments email sent for Project Black Forest Meadows Site Development Plan for review by Fire Chief Trent Harwig on behalf of Falcon Fire Protection District
|
10/5/2021 10:33:33 AM
|
Request for Review Comments email sent for Project Black Forest Meadows Site Development Plan for review by District Manager Pamela Davison on behalf of El Paso County Conservation Dist
|
10/5/2021 10:33:31 AM
|
Request for Review Comments email sent for Project Black Forest Meadows Site Development Plan for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
10/5/2021 10:33:28 AM
|
Request for Review Comments email sent for Project Black Forest Meadows Site Development Plan for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
10/5/2021 10:33:26 AM
|
Request for Review Comments email sent for Project Black Forest Meadows Site Development Plan for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
10/5/2021 10:33:24 AM
|
Request for Review Comments email sent for Project Black Forest Meadows Site Development Plan for review by Tim Kroening on behalf of Colorado Parks and Wildlife
|
10/5/2021 10:33:22 AM
|
Request for Review Comments email sent for Project Black Forest Meadows Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
10/5/2021 10:33:16 AM
|
Request for Review Comments email sent for Project Black Forest Meadows Site Development Plan for review by Bill Elder on behalf of EPC Sheriff's Department
|
10/5/2021 10:33:15 AM
|
Request for Review Comments email sent for Project Black Forest Meadows Site Development Plan for review by Bill Elder on behalf of EPC Sheriff's Department
|
10/5/2021 10:33:12 AM
|
Request for Review Comments email sent for Project Black Forest Meadows Site Development Plan for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
|
10/5/2021 10:33:10 AM
|
Request for Review Comments email sent for Project Black Forest Meadows Site Development Plan for review by on behalf of EPC Parks Department
|
10/5/2021 10:33:07 AM
|
Request for Review Comments email sent for Project Black Forest Meadows Site Development Plan for review by Catherine McGarvy on behalf of EPC Health Department
|
10/5/2021 10:32:55 AM
|
Request for Review Comments email sent for Project Black Forest Meadows Site Development Plan for review by Kathy Andrew on behalf of EPC Environmental Services
|
10/5/2021 10:32:53 AM
|
Request for Review Comments email sent for Project Black Forest Meadows Site Development Plan for review by Lori Seago on behalf of County Attorney - Development Review
|
10/5/2021 10:32:50 AM
|
Request for Review Comments email sent for Project Black Forest Meadows Site Development Plan for review by John Green on behalf of PCD Project Manager
|
10/5/2021 10:32:48 AM
|
Request for Review Comments email sent for Project Black Forest Meadows Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
9/21/2021 2:09:13 PM
|
Fees paid: 9/21/2021 (Receipt: 1005136)
|
9/21/2021 1:18:29 PM
|
Payment Request sent: 9/21/2021
|
9/21/2021 1:18:29 PM
|
File # Assigned: PPR2149
|
9/21/2021 1:18:23 PM
|
Submission Triaged
|
9/20/2021 5:21:59 PM
|
Submission received from Applicant
|
9/18/2021 1:31:53 PM
|
Submission request sent to Applicant
|
9/18/2021 1:31:44 PM
|
Submission Triaged
|
9/16/2021 11:11:11 AM
|
Submission received from Applicant
|
8/19/2021 12:50:38 PM
|
Submission request sent to Applicant
|
8/19/2021 12:44:27 PM
|
Project Manager Assigned: John Green
|
8/19/2021 12:44:27 PM
|
Project Created
|