10/10/2022 9:18:22 AM
|
Project Closed
|
|
10/10/2022 9:18:22 AM
|
Project Approved: 10/10/2022
|
|
10/3/2022 11:45:47 AM
|
Submission Triaged
|
|
10/3/2022 10:43:33 AM
|
Submission received from Applicant
|
|
10/3/2022 9:25:50 AM
|
Submission request sent to Applicant
|
|
10/3/2022 9:24:07 AM
|
Submission request sent to Applicant
|
|
9/30/2022 4:05:29 PM
|
Submission request sent to Applicant
|
|
9/26/2022 3:15:29 PM
|
Request for Review Comments returned by PCD Engineering Division
|
|
9/22/2022 12:04:50 PM
|
Submission Triaged
|
|
9/22/2022 11:56:58 AM
|
Submission received from Applicant
|
|
9/22/2022 10:23:59 AM
|
Submission request sent to Applicant
|
|
9/19/2022 9:07:56 AM
|
Submission request sent to Applicant
|
|
9/18/2022 9:46:04 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
|
9/14/2022 11:38:38 AM
|
Request for Review Comments returned by PCD Project Manager
|
|
9/14/2022 9:23:31 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
|
9/13/2022 12:58:39 PM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
|
9/13/2022 12:58:38 PM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Lori Seago on behalf of County Attorney - Development Review
|
|
9/13/2022 12:58:35 PM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Kari Parsons on behalf of PCD Project Manager
|
|
9/13/2022 12:58:33 PM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
|
9/13/2022 12:56:49 PM
|
Submission Triaged
|
|
9/13/2022 12:55:27 PM
|
Submission received from Applicant
|
|
9/13/2022 12:51:53 PM
|
Submission request sent to Applicant
|
|
9/6/2022 5:14:05 PM
|
Request for Review Comments returned by PCD Engineering Division
|
|
9/6/2022 11:29:58 AM
|
Request for Review Comments returned by PCD Project Manager
|
|
8/26/2022 4:23:24 PM
|
Submission Triaged
|
|
8/26/2022 7:04:35 AM
|
Submission received from Applicant
|
|
8/25/2022 3:06:38 PM
|
Submission request sent to Applicant
|
|
8/25/2022 1:29:17 PM
|
Request for Review Comments returned by County Attorney - Water
|
|
8/24/2022 3:45:05 PM
|
Submission Triaged
|
|
8/24/2022 3:29:43 PM
|
Submission received from Applicant
|
|
8/24/2022 2:46:09 PM
|
Submission request sent to Applicant
|
|
8/23/2022 11:13:36 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Edi Anderson on behalf of County Attorney - Water
|
|
8/23/2022 7:38:09 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Kari Parsons on behalf of PCD Project Manager
|
|
8/23/2022 7:38:07 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
|
8/18/2022 7:33:52 AM
|
Submission Triaged
|
|
8/18/2022 7:05:34 AM
|
Submission received from Applicant
|
|
8/10/2022 11:20:23 AM
|
Submission request sent to Applicant
|
|
8/10/2022 11:18:13 AM
|
Request for Review Comments returned by PCD Project Manager
|
|
8/9/2022 7:51:44 PM
|
Request for Review Comments returned by PCD Engineering Division
|
|
8/9/2022 10:36:47 AM
|
Submission Triaged
|
|
8/8/2022 11:21:00 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
|
8/8/2022 9:40:10 AM
|
Submission received from Applicant
|
|
8/2/2022 2:11:49 PM
|
Submission request sent to Applicant
|
|
8/2/2022 12:37:35 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
|
7/16/2022 2:18:31 PM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
|
7/16/2022 2:18:29 PM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Lori Seago on behalf of County Attorney - Development Review
|
|
7/16/2022 2:18:25 PM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Kari Parsons on behalf of PCD Project Manager
|
|
7/16/2022 2:18:23 PM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
|
7/16/2022 2:16:24 PM
|
Submission Triaged
|
|
7/15/2022 11:35:14 AM
|
Submission received from Applicant
|
|
7/12/2022 3:14:52 PM
|
Submission request sent to Applicant
|
|
6/20/2022 5:39:39 PM
|
Submission request sent to Applicant
|
|
6/20/2022 5:36:05 PM
|
Request for Review Comments returned by PCD Project Manager
|
|
6/20/2022 1:15:05 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
|
6/17/2022 10:11:48 AM
|
Request for Review Comments returned by PCD Engineering Division
|
|
5/23/2022 4:45:35 PM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
|
5/23/2022 4:45:33 PM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Kari Parsons on behalf of PCD Project Manager
|
|
5/23/2022 4:45:31 PM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
|
5/23/2022 4:42:24 PM
|
Submission Triaged
|
|
5/23/2022 3:59:07 PM
|
Submission received from Applicant
|
|
4/2/2022 5:20:11 PM
|
Request for Review Comments returned by EPC Health Department
|
|
3/31/2022 6:58:50 AM
|
Submission request sent to Applicant
|
|
3/31/2022 6:56:23 AM
|
Request for Review Comments returned by PCD Project Manager
|
|
3/30/2022 3:03:10 PM
|
Request for Review Comments returned by PCD Engineering Division
|
|
3/29/2022 10:40:34 AM
|
Request for Review Comments returned by Colorado Springs Public Works
|
|
3/25/2022 10:40:20 AM
|
Request for Review Comments returned by Colorado Parks and Wildlife
|
|
3/18/2022 2:15:06 PM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
|
3/15/2022 11:52:22 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
|
3/15/2022 9:07:51 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
|
3/15/2022 7:58:43 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
|
3/10/2022 1:42:27 PM
|
Request for Review Comments returned by Colorado Geological Survey
|
|
3/9/2022 4:29:23 PM
|
Request for Review Comments returned by Parks Advisory Board
|
|
3/8/2022 3:00:37 PM
|
Request for Review Comments returned by US Postal Service
|
|
3/1/2022 10:37:15 AM
|
Request for Review Comments returned by Fountain
|
|
2/28/2022 11:26:51 AM
|
Request for Review Comments returned by EPC Environmental Services
|
|
2/23/2022 3:12:08 PM
|
Request for Review Comments returned by County Attorney - Water
|
|
2/23/2022 10:37:45 AM
|
Request for Review Comments returned by EPC Parks Department
|
|
2/23/2022 9:35:23 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
|
2/22/2022 3:13:08 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
|
2/22/2022 11:07:58 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Kari Parsons on behalf of PCD Project Manager
|
|
2/22/2022 11:07:56 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
|
2/22/2022 10:05:39 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Brandon Bernard on behalf of Widefield Water & San
|
|
2/22/2022 10:05:36 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Susan Davies on behalf of Trails and Open Space Coalition
|
|
2/22/2022 10:05:34 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by on behalf of Security Fire Protection District
|
|
2/22/2022 10:05:32 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by William Feller on behalf of Peaceful Valley Lake Estates HOA
|
|
2/22/2022 10:05:29 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by General Email on behalf of Mountain View Electric Association, Inc.
|
|
2/22/2022 10:05:27 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Roger Austin on behalf of Mountain Metro Transit (City of COS)
|
|
2/22/2022 10:05:25 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by P.E. Mgr. Gary Steen on behalf of Fountain Mutual Irrigation Company
|
|
2/22/2022 10:05:22 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Kristy Martinez on behalf of Fountain
|
|
2/22/2022 10:05:20 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Rae Carlson on behalf of Colorado Springs Public Works
|
|
2/22/2022 10:04:56 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Katie Carleo on behalf of Colorado Springs Planning & Community Development
|
|
2/22/2022 10:04:50 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
|
2/22/2022 10:04:47 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
|
2/22/2022 10:04:45 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
|
2/22/2022 10:04:42 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Elaine Kelly on behalf of US Postal Service
|
|
2/22/2022 10:04:40 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Justin Osborne on behalf of Colorado State Land Board
|
|
2/22/2022 10:04:37 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Kimberly Berscheid on behalf of Colorado Parks and Wildlife
|
|
2/22/2022 10:04:30 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
|
2/22/2022 10:04:28 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
|
2/22/2022 10:04:26 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Michael Diehl on behalf of Xcel Energy
|
|
2/22/2022 10:04:23 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by on behalf of Parks Advisory Board
|
|
2/22/2022 10:04:20 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
|
2/22/2022 10:04:13 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Commander John Padgett on behalf of EPC Sheriff's Department
|
|
2/22/2022 10:04:11 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by on behalf of EPC Parks Department
|
|
2/22/2022 10:04:09 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Catherine McGarvy on behalf of EPC Health Department
|
|
2/22/2022 10:03:54 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Kathy Andrew on behalf of EPC Environmental Services
|
|
2/22/2022 10:03:52 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Edi Anderson on behalf of County Attorney - Water
|
|
2/22/2022 10:03:50 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Lori Seago on behalf of County Attorney - Development Review
|
|
2/22/2022 10:03:44 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Kari Parsons on behalf of PCD Project Manager
|
|
2/22/2022 10:03:41 AM
|
Request for Review Comments email sent for Project Hillside at Lorson Ranch PUDSP for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
|
2/22/2022 9:27:20 AM
|
Fees paid: 2/22/2022 (Receipt: 1005848)
|
|
2/22/2022 9:18:42 AM
|
Payment Request sent: 2/22/2022
|
|
2/22/2022 9:18:42 AM
|
File # Assigned: PUDSP221
|
|
2/22/2022 9:18:30 AM
|
Submission Triaged
|
|
2/18/2022 9:33:23 AM
|
Submission received from Applicant
|
|
8/4/2021 4:35:12 PM
|
Submission request sent to Applicant
|
|
7/28/2021 4:29:59 PM
|
Project Manager Assigned: Kari Parsons
|
|
7/28/2021 4:29:21 PM
|
EA Assigned: EA20166
|
|
7/28/2021 4:29:21 PM
|
Project Created
|