3/7/2022 4:13:01 PM
|
Project Closed
|
|
3/7/2022 4:13:01 PM
|
Project Approved: 3/7/2022
|
|
3/3/2022 12:15:39 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
|
3/3/2022 8:40:35 AM
|
Request for Review Comments sent for Project Falcon Marketplace Lot 7 Site Dev Plan for review by Lori Seago on behalf of County Attorney - Development Review
|
|
3/3/2022 8:39:08 AM
|
Request for Review Comments sent for Project Falcon Marketplace Lot 7 Site Dev Plan for review by Lori Seago on behalf of County Attorney - Development Review
|
|
3/3/2022 8:38:05 AM
|
Submission request canceled
|
|
3/3/2022 8:17:42 AM
|
Submission request sent to Applicant
|
|
2/22/2022 1:59:11 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
|
2/22/2022 1:13:49 PM
|
Request for Review Comments email sent for Project Falcon Marketplace Lot 7 Site Dev Plan for review by Lori Seago on behalf of County Attorney - Development Review
|
|
2/22/2022 1:11:36 PM
|
Submission Triaged
|
|
2/21/2022 7:49:52 AM
|
Submission received from Applicant
|
|
2/10/2022 3:09:06 PM
|
Submission request sent to Applicant
|
|
2/10/2022 2:54:34 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
|
2/7/2022 10:17:33 AM
|
Request for Review Comments email sent for Project Falcon Marketplace Lot 7 Site Dev Plan for review by Lori Seago on behalf of County Attorney - Development Review
|
|
2/7/2022 9:16:42 AM
|
Submission Triaged
|
|
2/7/2022 9:14:51 AM
|
Submission received from Applicant
|
|
2/4/2022 3:12:33 PM
|
Submission request sent to Applicant
|
|
1/27/2022 9:16:29 AM
|
Request for Review Comments returned by PCD Project Manager
|
|
1/25/2022 3:02:12 PM
|
Request for Review Comments returned by PCD Engineering Division
|
|
1/24/2022 9:04:47 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
|
1/13/2022 10:07:43 AM
|
Project Manager Assigned: Kylie Bagley
|
|
1/4/2022 7:50:42 AM
|
Request for Review Comments email sent for Project Falcon Marketplace Lot 7 Site Dev Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
|
1/4/2022 7:50:40 AM
|
Request for Review Comments email sent for Project Falcon Marketplace Lot 7 Site Dev Plan for review by Mercedes Rivas on behalf of PCD Project Manager
|
|
1/4/2022 7:50:34 AM
|
Request for Review Comments email sent for Project Falcon Marketplace Lot 7 Site Dev Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
|
1/3/2022 2:23:42 PM
|
Submission Triaged
|
|
1/3/2022 1:37:29 PM
|
Submission received from Applicant
|
|
12/29/2021 12:55:05 PM
|
Submission request sent to Applicant
|
|
12/29/2021 12:53:48 PM
|
Request for Review Comments returned by PCD Project Manager
|
|
12/27/2021 4:49:56 PM
|
Request for Review Comments returned by PCD Engineering Division
|
|
12/26/2021 12:09:15 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
|
12/6/2021 12:20:35 PM
|
Request for Review Comments email sent for Project Falcon Marketplace Lot 7 Site Dev Plan for review by Mercedes Rivas on behalf of PCD Project Manager
|
|
12/6/2021 12:16:45 PM
|
Request for Review Comments email sent for Project Falcon Marketplace Lot 7 Site Dev Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
|
12/6/2021 12:16:42 PM
|
Request for Review Comments email sent for Project Falcon Marketplace Lot 7 Site Dev Plan for review by Mercedes Rivas on behalf of PCD Project Manager
|
|
12/6/2021 12:16:36 PM
|
Request for Review Comments email sent for Project Falcon Marketplace Lot 7 Site Dev Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
|
12/6/2021 12:14:21 PM
|
Submission Triaged
|
|
12/3/2021 8:16:33 AM
|
Submission received from Applicant
|
|
11/18/2021 5:03:26 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
|
11/18/2021 8:41:53 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
|
11/17/2021 8:52:56 AM
|
Submission request sent to Applicant
|
|
11/17/2021 8:50:16 AM
|
Request for Review Comments returned by PCD Project Manager
|
|
11/16/2021 8:32:57 AM
|
Request for Review Comments returned by PCD Engineering Division
|
|
11/5/2021 2:25:45 PM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
|
10/27/2021 3:07:19 PM
|
Request for Review Comments email sent for Project Falcon Marketplace Lot 7 Site Dev Plan for review by UDS Admin Staff on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
|
10/27/2021 3:07:17 PM
|
Request for Review Comments email sent for Project Falcon Marketplace Lot 7 Site Dev Plan for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
|
10/27/2021 3:07:13 PM
|
Request for Review Comments email sent for Project Falcon Marketplace Lot 7 Site Dev Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
|
10/27/2021 3:07:10 PM
|
Request for Review Comments email sent for Project Falcon Marketplace Lot 7 Site Dev Plan for review by Mercedes Rivas on behalf of PCD Project Manager
|
|
10/27/2021 3:07:03 PM
|
Request for Review Comments email sent for Project Falcon Marketplace Lot 7 Site Dev Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
|
10/27/2021 2:55:33 PM
|
Submission Triaged
|
|
10/22/2021 9:29:22 AM
|
Submission received from Applicant
|
|
10/20/2021 12:55:47 PM
|
Submission request sent to Applicant
|
|
10/7/2021 9:48:22 AM
|
Submission request sent to Applicant
|
|
10/7/2021 9:45:23 AM
|
Request for Review Comments returned by PCD Project Manager
|
|
10/7/2021 9:38:22 AM
|
Request for Review Comments email resent for Project Falcon Marketplace Lot 7 Site Dev Plan for review by Mercedes Rivas on behalf of PCD Project Manager
|
|
10/6/2021 3:41:31 PM
|
Request for Review Comments returned by Upper Black Squirrel Creek GWMD
|
|
10/5/2021 2:28:03 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
|
10/4/2021 4:07:26 PM
|
Request for Review Comments returned by PCD Engineering Division
|
|
9/30/2021 4:55:27 PM
|
Request for Review Comments returned by PCD Project Manager
|
|
9/30/2021 12:14:06 PM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
|
9/30/2021 8:42:44 AM
|
Request for Review Comments returned by Colorado Springs Public Works
|
|
9/30/2021 8:10:15 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
|
9/29/2021 8:25:14 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
|
9/13/2021 9:51:41 AM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
|
9/9/2021 4:31:30 PM
|
Request for Review Comments returned by Woodmen Road Metro
|
|
9/9/2021 3:58:57 PM
|
Request for Review Comments email sent for Project Falcon Marketplace Lot 7 Site Dev Plan for review by Rebecca Hardekopf on behalf of Woodmen Road Metro
|
|
9/9/2021 3:58:55 PM
|
Request for Review Comments email sent for Project Falcon Marketplace Lot 7 Site Dev Plan for review by Jerry Jacobson on behalf of Woodmen Hills Metro
|
|
9/9/2021 3:58:52 PM
|
Request for Review Comments email sent for Project Falcon Marketplace Lot 7 Site Dev Plan for review by General Email on behalf of Mountain View Electric Association, Inc.
|
|
9/9/2021 3:58:50 PM
|
Request for Review Comments email sent for Project Falcon Marketplace Lot 7 Site Dev Plan for review by Fire Chief Trent Harwig on behalf of Falcon Fire Protection District
|
|
9/9/2021 3:58:47 PM
|
Request for Review Comments email sent for Project Falcon Marketplace Lot 7 Site Dev Plan for review by District Manager Pamela Davison on behalf of El Paso County Conservation Dist
|
|
9/9/2021 3:58:45 PM
|
Request for Review Comments email sent for Project Falcon Marketplace Lot 7 Site Dev Plan for review by UDS Admin Staff on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
|
9/9/2021 3:58:43 PM
|
Request for Review Comments email sent for Project Falcon Marketplace Lot 7 Site Dev Plan for review by Rae Carlson on behalf of Colorado Springs Public Works
|
|
9/9/2021 3:58:41 PM
|
Request for Review Comments email sent for Project Falcon Marketplace Lot 7 Site Dev Plan for review by Katie Carleo on behalf of Colorado Springs Planning & Community Development
|
|
9/9/2021 3:58:39 PM
|
Request for Review Comments email sent for Project Falcon Marketplace Lot 7 Site Dev Plan for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
|
|
9/9/2021 3:58:37 PM
|
Request for Review Comments email sent for Project Falcon Marketplace Lot 7 Site Dev Plan for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
|
9/9/2021 3:58:35 PM
|
Request for Review Comments email sent for Project Falcon Marketplace Lot 7 Site Dev Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
|
9/9/2021 3:58:32 PM
|
Request for Review Comments email sent for Project Falcon Marketplace Lot 7 Site Dev Plan for review by Catherine McGarvy on behalf of EPC Health Department
|
|
9/9/2021 3:58:20 PM
|
Request for Review Comments email sent for Project Falcon Marketplace Lot 7 Site Dev Plan for review by Mercedes Rivas on behalf of PCD Project Manager
|
|
9/9/2021 3:58:18 PM
|
Request for Review Comments email sent for Project Falcon Marketplace Lot 7 Site Dev Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
|
9/3/2021 10:43:07 AM
|
Fees paid: 9/3/2021 (Receipt: 1005044)
|
|
8/30/2021 3:50:36 PM
|
Project Manager Assigned: Mercedes Rivas
|
|
8/30/2021 3:50:20 PM
|
Payment Request sent: 8/30/2021
|
|
8/30/2021 3:50:19 PM
|
File # Assigned: PPR2142
|
|
8/30/2021 3:50:12 PM
|
Submission Triaged
|
|
8/28/2021 9:15:25 PM
|
Submission received from Applicant
|
|
7/20/2021 2:50:41 PM
|
Submission request sent to Applicant
|
|
7/20/2021 2:50:28 PM
|
Set Applicant to DREXEL, BARRELL & CO.
|
|
7/20/2021 2:31:33 PM
|
Submission request sent to Applicant
|
|
7/16/2021 4:31:07 PM
|
Project Manager Assigned: Kari Parsons
|
|
7/16/2021 4:31:07 PM
|
EA Assigned: EA21128
|
|
7/16/2021 4:31:07 PM
|
Project Created
|