Project Details
- File Number
- CON2125
- Project Name
- Liberty Tree Site Development Plan Phase 2
- Description
- Parking lot addition
- Parcels
- 4232302001 4232302001
- Applicant
-
Carhuff+Cueva Architects
David Kline ( Dave_Kline@matrixdesigngroup.com )
(719) 575-0100 David Kline ( Dave_Kline@matrixdesigngroup.com )
(719) 575-0100 - File Prefix
- CON - Construction Permit
- Year
- 2021
- Project Manager
- David Parkerson
- Status
- Closed
- Created
- 5/24/2021 4:51:38 PM
View: Review Comments
Document | Comment | ||
---|---|---|---|
View | Unsigned Con Permit | 5/25/2021 9:47:14 AM | |
View | PCD PL 1-18-2023 | 1/18/2023 9:25:55 AM | |
View | PL Email sent to Jesse with Roche Const. 1-23 | 1/18/2023 9:33:05 AM | |
View | Stormwater Punchlist FA 01/17/2023 | 1/25/2023 3:07:30 PM |
Document | Date | |
---|---|---|
View | Approved CD'S | 5/24/2021 4:56:36 PM |
View | Approved Drainage Report | 5/24/2021 4:56:40 PM |
View | Approved FAE | 5/24/2021 4:56:41 PM |
View | Approved G&E Checklist | 5/24/2021 4:56:41 PM |
View | Approved Pavement Design | 8/3/2021 11:53:55 AM |
View | As Builts | 1/26/2023 7:53:06 AM |
View | FAE Bond 6/21 | 6/4/2021 2:15:21 PM |
View | Letter of Responsibility | 6/4/2021 10:51:21 AM |
View | Reciept for Con Fees | 6/2/2021 6:58:16 AM |
View | Reciept for Con Fees | 6/4/2021 10:47:04 AM |
View | ROW for Eastonville Rd | 6/24/2021 8:18:23 AM |
View | TCP per DPW | 5/24/2021 5:22:43 PM |
View | Traffic Study | 5/24/2021 4:56:41 PM |
View | Unapp. Sign and Stripping Plan | 5/24/2021 4:59:15 PM |
Date | Comment |
---|---|
2/12/2025 8:54:50 AM | Project Closed |
2/12/2025 8:54:50 AM | Project Approved: 2/12/2025 |
2/23/2023 8:51:30 AM | Request for Review Comments returned by PCD Engineering Inspections |
2/12/2023 9:33:50 AM | Request for Review Comments returned by EPC Stormwater Review |
1/26/2023 8:08:17 AM | Request for Review Comments email sent for Project Liberty Tree Site Development Plan Phase 2 for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review |
1/26/2023 8:08:15 AM | Request for Review Comments email sent for Project Liberty Tree Site Development Plan Phase 2 for review by Brad Walters on behalf of PCD Engineering Inspections |
6/28/2022 4:12:09 PM | Project Manager Assigned: David Parkerson |
2/22/2022 3:54:06 PM | Fees paid: 2/22/2022 (Receipt: 1005855) |
5/24/2021 4:51:44 PM | Project Manager Assigned: Rick Spears |
5/24/2021 4:51:39 PM | Project Created. Parent Project: Liberty Tree Site Development Plan (PPR2018) |