12/1/2022 3:03:27 PM
|
Request for Review Comments sent for Project Gearhead Garage Site Development Plan for review by Brad Walters on behalf of PCD Engineering Inspections
|
|
3/1/2022 7:56:48 AM
|
Project Closed
|
|
3/1/2022 7:56:48 AM
|
Project Approved: 3/1/2022
|
|
2/24/2022 3:36:33 PM
|
Request for Review Comments returned by PCD Project Manager
|
|
2/10/2022 7:51:41 AM
|
Request for Review Comments email sent for Project Gearhead Garage Site Development Plan for review by Kylie Bagley on behalf of PCD Project Manager
|
|
2/10/2022 7:49:58 AM
|
Submission Triaged
|
|
2/8/2022 4:18:18 PM
|
Submission received from Applicant
|
|
1/21/2022 2:06:46 PM
|
Submission request sent to Applicant
|
|
1/21/2022 2:06:27 PM
|
Submission request sent to Applicant
|
|
1/21/2022 2:06:08 PM
|
Submission request canceled
|
|
1/21/2022 2:04:02 PM
|
Request for Review Comments returned by PCD Project Manager
|
|
1/21/2022 11:39:15 AM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
|
1/20/2022 1:55:43 PM
|
Submission request sent to Applicant
|
|
1/20/2022 8:56:15 AM
|
Request for Review Comments returned by Cherokee Metro Dist
|
|
1/18/2022 11:37:35 AM
|
Request for Review Comments returned by PCD Engineering Division
|
|
1/5/2022 10:28:22 AM
|
Request for Review Comments returned by Central Marksheffel Metro
|
|
1/3/2022 8:54:23 AM
|
Request for Review Comments email sent for Project Gearhead Garage Site Development Plan for review by UDS Admin Staff on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
|
1/3/2022 8:54:17 AM
|
Request for Review Comments email sent for Project Gearhead Garage Site Development Plan for review by Jeff Munger on behalf of Cherokee Metro Dist
|
|
1/3/2022 8:54:15 AM
|
Request for Review Comments email sent for Project Gearhead Garage Site Development Plan for review by Rebecca Hardekopf on behalf of Central Marksheffel Metro
|
|
1/3/2022 8:54:12 AM
|
Request for Review Comments email sent for Project Gearhead Garage Site Development Plan for review by Kylie Bagley on behalf of PCD Project Manager
|
|
1/3/2022 8:54:08 AM
|
Request for Review Comments email sent for Project Gearhead Garage Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
|
1/3/2022 8:51:11 AM
|
Submission Triaged
|
|
12/22/2021 11:19:46 AM
|
Submission received from Applicant
|
|
12/20/2021 1:19:39 PM
|
Submission request sent to Applicant
|
|
12/8/2021 7:33:47 PM
|
Request for Review Comments returned by EPC Health Department
|
|
11/29/2021 1:29:03 PM
|
Submission request sent to Applicant
|
|
11/29/2021 1:26:47 PM
|
Request for Review Comments returned by PCD Project Manager
|
|
11/18/2021 5:26:23 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
|
11/18/2021 4:13:44 PM
|
Request for Review Comments returned by PCD Engineering Division
|
|
11/12/2021 4:23:20 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
|
11/12/2021 8:00:18 AM
|
Request for Review Comments returned by Cherokee Metro Dist
|
|
11/10/2021 11:02:28 AM
|
Project Manager Assigned: Kylie Bagley
|
|
11/9/2021 3:33:33 PM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
|
11/4/2021 7:55:14 AM
|
Request for Review Comments email sent for Project Gearhead Garage Site Development Plan for review by Ryan Howser on behalf of PCD Project Manager
|
|
11/4/2021 7:55:10 AM
|
Request for Review Comments email sent for Project Gearhead Garage Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
|
11/2/2021 8:10:11 AM
|
Request for Review Comments returned by Cimarron Hills Fire
|
|
11/1/2021 12:27:35 PM
|
Request for Review Comments returned by Central Marksheffel Metro
|
|
10/29/2021 12:37:24 PM
|
Request for Review Comments email sent for Project Gearhead Garage Site Development Plan for review by UDS Admin Staff on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
|
10/29/2021 12:37:21 PM
|
Request for Review Comments email sent for Project Gearhead Garage Site Development Plan for review by Terry Johns on behalf of Colorado Springs SD 11
|
|
10/29/2021 12:37:19 PM
|
Request for Review Comments email sent for Project Gearhead Garage Site Development Plan for review by Katie Carleo on behalf of Colorado Springs Planning & Community Development
|
|
10/29/2021 12:37:17 PM
|
Request for Review Comments email sent for Project Gearhead Garage Site Development Plan for review by Division Chief John McLeod on behalf of Cimarron Hills Fire
|
|
10/29/2021 12:37:15 PM
|
Request for Review Comments email sent for Project Gearhead Garage Site Development Plan for review by Jeff Munger on behalf of Cherokee Metro Dist
|
|
10/29/2021 12:37:13 PM
|
Request for Review Comments email sent for Project Gearhead Garage Site Development Plan for review by Rebecca Hardekopf on behalf of Central Marksheffel Metro
|
|
10/29/2021 12:37:10 PM
|
Request for Review Comments email sent for Project Gearhead Garage Site Development Plan for review by Pamela Davidson on behalf of Central CO Conservation District
|
|
10/29/2021 12:37:08 PM
|
Request for Review Comments email sent for Project Gearhead Garage Site Development Plan for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
|
10/29/2021 12:37:06 PM
|
Request for Review Comments email sent for Project Gearhead Garage Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
|
10/29/2021 12:37:02 PM
|
Request for Review Comments email sent for Project Gearhead Garage Site Development Plan for review by Catherine McGarvy on behalf of EPC Health Department
|
|
10/29/2021 12:36:46 PM
|
Request for Review Comments email sent for Project Gearhead Garage Site Development Plan for review by Ryan Howser on behalf of PCD Project Manager
|
|
10/29/2021 12:36:43 PM
|
Request for Review Comments email sent for Project Gearhead Garage Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
|
10/28/2021 4:34:42 PM
|
Fees paid: 10/28/2021 (Receipt: 1005326)
|
|
10/27/2021 5:15:40 PM
|
Payment Request sent: 10/27/2021
|
|
10/27/2021 5:15:40 PM
|
File # Assigned: PPR2163
|
|
10/27/2021 5:15:30 PM
|
Submission Triaged
|
|
10/26/2021 3:55:52 PM
|
Submission received from Applicant
|
|
6/11/2021 12:00:50 PM
|
Submission request sent to Applicant
|
|
6/11/2021 11:21:32 AM
|
Submission request sent to Applicant
|
|
3/25/2021 5:09:08 PM
|
Submission request sent to Applicant
|
|
3/25/2021 5:05:44 PM
|
Project Manager Assigned: Ryan Howser
|
|
3/25/2021 5:05:44 PM
|
Project Created
|