Project Details

Search


File Number
SF223
Project Name
Falcon Acres Final Plat (Reconsideration)
Description
Reconsideration for final plat 07014, creation of 8 parcels.
Parcels
4404000014 4404000014
Applicant
Thousand Hills LLC
Richard Elliott ( thousandhills88@gmail.com )
(719) 238-4234
Richard Elliott ( thousandhills88@gmail.com )
(719) 238-4234
File Prefix
SF - Final Plat
Year
2022
Project Manager
Ryan Howser
Status
Closed
Created
3/25/2021 2:56:58 PM

View: Review Comments


Approved Documents (10)

Link Document
View Grading & Erosion Control checklist
View Erosion and Stormwater Quality Control Permit (ESQCP)
View Financial Assurance Forms
View PBMP Applicability Form
View PDB/BMP Operations & Maintenance Manual
View SWMP checklist
View Construction Drawings (Plans/Profiles)
View Grading & Erosion Control Plan
View Drainage Report - Final
View Traffic Impact Study


Additional Documents (8)

Link Document Comment
View Mailing Packet: Notice, Map and Labels
View Posting Photos
View Approved BoCC Resolution
View Recorded Private Dentention Basin, Stormwater Quality Best Managment Practice Maintenance Agreement and Easement
View Recorded Plat - 225715512
View Recorded - Escrow Agreement
View Recorded SIA
View Recorded Declaration of Covenants


Review Documents (49)

Link Document Date
View Adjacent Property Owner Notification (Includes letter and certified mailing receipts) 12/14/2021 3:58:23 PM
View Application/Petition Form 12/14/2021 3:58:53 PM
View Grading & Erosion Control checklist 8/17/2023 11:54:44 AM
View Legal Description (MS WORD Version required) 8/18/2023 11:45:19 AM
View Letter of Intent 1/11/2024 2:38:43 PM
View OWTS Report 2/28/2023 11:46:11 AM
View Title Commitment (Current within 30 days of submittal) 12/14/2021 4:11:32 PM
View Vicinity/Location Map 2/27/2023 4:28:24 PM
View Erosion and Stormwater Quality Control Permit (ESQCP) 2/28/2023 9:41:07 AM
View Financial Assurance Forms 10/17/2023 1:15:40 PM
View Mineral Rights Certification 12/14/2021 4:09:16 PM
View MS4 Post Construction Form 12/14/2021 4:22:23 PM
View PBMP Applicability Form 12/14/2021 4:21:28 PM
View PDB/BMP Operations & Maintenance Manual 2/27/2023 4:37:08 PM
View Stormwater Detention & Infiltration Design Data Worksheet (SDI Worksheet) 12/14/2021 4:18:49 PM
View SWMP checklist 2/27/2023 4:37:10 PM
View Construction Drawings (Plans/Profiles) 10/17/2023 1:15:39 PM
View Final Plat Drawings 1/11/2024 7:06:44 PM
View Grading & Erosion Control Plan 10/17/2023 1:16:27 PM
View Storm Water Management Plan (SWMP) 2/27/2023 4:34:52 PM
View Electric Provider Commitment Letter 12/14/2021 4:00:42 PM
View Fire Commitment Letter 12/22/2021 9:50:01 AM
View Natural Gas Commitment Letter 12/14/2021 4:09:16 PM
View Drainage Report - Final 8/18/2023 11:58:38 AM
View Fire Protection Report 12/14/2021 4:05:56 PM
View Soils & Geology Report 10/17/2023 1:16:26 PM
View Subdivision Summary Sheet 8/17/2023 11:45:37 AM
View Traffic Impact Study 8/15/2023 9:44:03 AM
View Wildland Fire & Hazard Mitigation Plan 12/14/2021 4:14:32 PM
View Escrow Agreement 12/6/2024 4:07:02 PM
View Maintenance Agreement (MS Word version required attachments included) 12/6/2024 4:07:01 PM
View Subdivision Improvement Agreement (MS Word version required) 11/8/2024 11:01:52 AM
View Signed court decrees, including augmentation plans 12/14/2021 4:10:25 PM
View Water Resources Report 12/12/2024 3:55:33 PM
View Water Supply Information Summary 10/17/2023 1:36:25 PM
View Well Permits (if water source is wells) 8/17/2023 12:03:23 PM
View Declaration of Covenants (MS Word version required) 11/8/2024 10:24:25 AM
View Water conveyance deeds and 300-year augmentation supply to HOA (MS Word version required) 8/17/2023 12:03:23 PM
View Closures Sheet (Survey) 8/18/2023 12:10:42 PM
View Construction Drawings Engineering Comment Responses 8/15/2023 9:44:06 AM
View Construction Drawings Stormwater Comment Responses 8/15/2023 9:44:05 AM
View Drainage Report Comment Responses 8/15/2023 9:44:04 AM
View Email correspondence with state engineer 8/15/2023 9:55:25 AM
View Previous construction drawing submittal with comments addressed. 2/28/2023 11:54:26 AM
View Previous drainage report submittal with comments addressed. 2/28/2023 11:54:27 AM
View Previous financial assurance submittal with comments addressed. 2/28/2023 11:54:28 AM
View Previous GEC submittal with comments addressed. 2/28/2023 11:54:28 AM
View Proof of submittal of non-jurisdictional water impoundment structure form 12/23/2021 1:20:41 PM
View Wetland Report 2/28/2023 11:54:29 AM



Events (239)

Date Comment
4/4/2025 3:58:20 PM Project Closed
4/4/2025 3:58:20 PM Project Approved: 4/4/2025
12/17/2024 8:20:01 AM Project Ready for Approval requests. Review Comment period is complete.
12/16/2024 9:14:35 PM Request for Review Comments returned by EPC Health Department
12/12/2024 4:41:51 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Mike McCarthy on behalf of EPC Health Department
12/12/2024 4:41:49 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Catherine McGarvy on behalf of EPC Health Department
12/12/2024 4:41:47 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by HEAEH LandUse on behalf of EPC Health Department
12/12/2024 4:40:19 PM Submission Triaged
12/12/2024 3:55:40 PM Submission received from Applicant
12/10/2024 2:47:02 PM Request for Review Comments returned by County Attorney - Development Review
12/6/2024 4:17:26 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Lori Seago on behalf of County Attorney - Development Review
12/6/2024 4:17:24 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Erika Keech on behalf of County Attorney - Development Review
12/6/2024 4:17:22 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by April Willie on behalf of County Attorney - Development Review
12/6/2024 4:16:45 PM Submission request sent to Applicant
12/6/2024 4:16:27 PM Submission Triaged
12/6/2024 4:07:18 PM Submission received from Applicant
12/6/2024 2:37:00 PM Request for Review Comments returned by EPC Health Department
12/6/2024 9:01:07 AM Submission request sent to Applicant
12/6/2024 8:11:05 AM Request for Review Comments returned by County Attorney - Development Review
11/26/2024 11:54:09 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Lori Seago on behalf of County Attorney - Development Review
11/26/2024 11:54:07 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Erika Keech on behalf of County Attorney - Development Review
11/26/2024 11:54:05 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by April Willie on behalf of County Attorney - Development Review
11/26/2024 11:53:25 AM Submission Triaged
11/26/2024 10:36:02 AM Submission received from Applicant
11/26/2024 9:00:51 AM Submission request sent to Applicant
11/25/2024 9:50:36 AM Request for Review Comments returned by County Attorney - Development Review
11/8/2024 11:45:05 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Mike McCarthy on behalf of EPC Health Department
11/8/2024 11:45:03 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Catherine McGarvy on behalf of EPC Health Department
11/8/2024 11:45:01 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by HEAEH LandUse on behalf of EPC Health Department
11/8/2024 11:44:59 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Lori Seago on behalf of County Attorney - Development Review
11/8/2024 11:44:58 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Erika Keech on behalf of County Attorney - Development Review
11/8/2024 11:44:56 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by April Willie on behalf of County Attorney - Development Review
11/8/2024 11:43:03 AM Submission Triaged
11/8/2024 11:02:20 AM Submission received from Applicant
8/16/2024 3:03:25 PM Submission request sent to Applicant
8/16/2024 2:58:44 PM Request for Review Comments returned by EPC Health Department
8/16/2024 10:24:30 AM Submission request sent to Applicant
7/28/2024 3:03:00 PM Request for Review Comments returned by County Attorney - Development Review
7/9/2024 2:42:17 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Mike McCarthy on behalf of EPC Health Department
7/9/2024 2:42:15 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Catherine McGarvy on behalf of EPC Health Department
7/9/2024 2:42:13 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by HEAEH LandUse on behalf of EPC Health Department
7/9/2024 2:42:10 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Lori Seago on behalf of County Attorney - Development Review
7/9/2024 2:42:08 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Erika Keech on behalf of County Attorney - Development Review
7/9/2024 2:42:07 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by April Willie on behalf of County Attorney - Development Review
7/9/2024 2:39:23 PM Submission Triaged
7/9/2024 2:10:02 PM Submission received from Applicant
7/9/2024 1:40:24 PM Submission request sent to Applicant
7/9/2024 1:39:27 PM Submission Triaged
7/9/2024 11:01:35 AM Submission received from Applicant
6/25/2024 4:59:23 PM Submission request sent to Applicant
6/25/2024 11:50:02 AM Request for Review Comments returned by County Attorney - Development Review
6/21/2024 11:30:48 AM Request for Review Comments returned by EPC Health Department
6/18/2024 1:16:47 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Lori Seago on behalf of County Attorney - Development Review
6/18/2024 1:16:46 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Erika Keech on behalf of County Attorney - Development Review
6/18/2024 1:16:44 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by April Willie on behalf of County Attorney - Development Review
6/18/2024 1:15:56 PM Submission Triaged
6/18/2024 1:12:53 PM Submission received from Applicant
5/23/2024 4:16:48 PM Submission request sent to Applicant
5/23/2024 3:48:32 PM Request for Review Comments returned by County Attorney - Development Review
5/10/2024 9:16:14 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Mike McCarthy on behalf of EPC Health Department
5/10/2024 9:16:12 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Catherine McGarvy on behalf of EPC Health Department
5/10/2024 9:16:10 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by HEAEH LandUse on behalf of EPC Health Department
5/10/2024 9:16:08 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Lori Seago on behalf of County Attorney - Development Review
5/10/2024 9:16:06 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Erika Keech on behalf of County Attorney - Development Review
5/10/2024 9:16:04 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by April Willie on behalf of County Attorney - Development Review
5/10/2024 9:14:32 AM Submission Triaged
5/10/2024 8:01:43 AM Submission received from Applicant
3/14/2024 4:37:21 PM Request for Review Comments returned by Colorado Division of Water Resources
3/14/2024 8:02:46 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Mike McCarthy on behalf of EPC Health Department
3/14/2024 8:02:44 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Catherine McGarvy on behalf of EPC Health Department
3/14/2024 8:02:42 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by HEAEH LandUse on behalf of EPC Health Department
3/12/2024 2:35:21 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Melissa Van Der Poel on behalf of Colorado Division of Water Resources
3/12/2024 2:35:19 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Joanna Williams on behalf of Colorado Division of Water Resources
2/15/2024 5:00:05 PM Submission request sent to Applicant
2/15/2024 4:25:51 PM Request for Review Comments returned by County Attorney - Development Review
2/13/2024 8:22:30 AM Submission request sent to Applicant
2/10/2024 2:30:15 PM Request for Review Comments returned by EPC Health Department
2/1/2024 8:19:43 AM Request for Review Comments returned by PCD Project Manager
1/18/2024 4:55:54 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Mike McCarthy on behalf of EPC Health Department
1/18/2024 4:55:52 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Catherine McGarvy on behalf of EPC Health Department
1/18/2024 4:55:49 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by HEAEH LandUse on behalf of EPC Health Department
1/18/2024 4:55:47 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Lori Seago on behalf of County Attorney - Development Review
1/18/2024 4:55:44 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by April Willie on behalf of County Attorney - Development Review
1/18/2024 4:53:28 PM Submission Triaged
1/18/2024 4:11:41 PM Submission received from Applicant
1/11/2024 10:18:39 AM Submission request sent to Applicant
1/11/2024 10:18:03 AM Submission Triaged
1/11/2024 8:59:44 AM Submission received from Applicant
1/2/2024 2:10:58 PM Submission request sent to Applicant
12/1/2023 9:50:09 AM Submission request sent to Applicant
12/1/2023 9:39:31 AM Request for Review Comments returned by County Attorney - Development Review
11/21/2023 9:20:43 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Lori Seago on behalf of County Attorney - Development Review
11/21/2023 9:20:41 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by April Willie on behalf of County Attorney - Development Review
11/21/2023 9:19:34 AM Submission Triaged
11/21/2023 8:57:35 AM Submission received from Applicant
11/20/2023 2:44:20 PM Request for Review Comments returned by County Attorney - Water
11/17/2023 4:09:57 PM Submission request sent to Applicant
11/9/2023 12:51:39 PM Request for Review Comments returned by County Attorney - Development Review
11/1/2023 7:44:40 AM Request for Review Comments returned by PCD Project Manager
10/31/2023 5:04:27 PM Request for Review Comments returned by PCD Engineering Division
10/30/2023 3:33:02 PM Request for Review Comments returned by Colorado Geological Survey
10/19/2023 3:09:26 PM Request for Review Comments returned by Colorado Division of Water Resources
10/19/2023 7:13:50 AM Request for Review Comments returned by EPC Stormwater Review
10/17/2023 5:17:16 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Colorado Geological Survey on behalf of Colorado Geological Survey
10/17/2023 5:17:10 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Joanna Williams on behalf of Colorado Division of Water Resources
10/17/2023 5:17:06 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
10/17/2023 5:16:58 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by EHS Mike McCarthy on behalf of EPC Health Department
10/17/2023 5:16:38 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Edi Anderson on behalf of County Attorney - Water
10/17/2023 5:16:32 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Lori Seago on behalf of County Attorney - Development Review
10/17/2023 5:16:30 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Ryan Howser on behalf of PCD Project Manager
10/17/2023 5:16:24 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Engineering Manager on behalf of PCD Engineering Division
10/17/2023 5:16:22 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Engineering Manager on behalf of PCD Engineering Division
10/17/2023 5:14:40 PM Submission Triaged
10/17/2023 1:36:32 PM Submission received from Applicant
10/13/2023 2:33:39 PM Request for Review Comments returned by EPC Health Department
9/19/2023 7:37:32 AM Submission request sent to Applicant
9/18/2023 11:14:47 AM Request for Review Comments returned by PCD Engineering Division
9/15/2023 10:24:10 AM Request for Review Comments returned by PCD Project Manager
9/13/2023 5:29:19 PM Request for Review Comments returned by EPC Stormwater Review
9/12/2023 3:06:38 PM Request for Review Comments returned by County Attorney - Development Review
9/12/2023 1:37:38 PM Request for Review Comments returned by Colorado Geological Survey
9/7/2023 10:46:46 AM Request for Review Comments returned by 911 Authority - El Paso/Teller County
9/1/2023 3:42:34 PM Request for Review Comments returned by County Attorney - Water
8/29/2023 12:27:55 PM Request for Review Comments returned by Colorado Division of Water Resources
8/22/2023 8:15:20 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
8/22/2023 8:15:19 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Colorado Geological Survey on behalf of Colorado Geological Survey
8/22/2023 8:15:17 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Joanna Williams on behalf of Colorado Division of Water Resources
8/22/2023 8:15:14 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
8/22/2023 8:15:09 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by EHS Mike McCarthy on behalf of EPC Health Department
8/22/2023 8:14:59 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Edi Anderson on behalf of County Attorney - Water
8/22/2023 8:14:56 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Lori Seago on behalf of County Attorney - Development Review
8/22/2023 8:14:55 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Ryan Howser on behalf of PCD Project Manager
8/22/2023 8:14:52 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Engineering Manager on behalf of PCD Engineering Division
8/22/2023 8:14:51 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Engineering Manager on behalf of PCD Engineering Division
8/22/2023 8:12:11 AM Submission Triaged
8/19/2023 1:10:54 PM Submission received from Applicant
8/18/2023 4:20:05 PM Submission request sent to Applicant
8/18/2023 4:19:57 PM Submission Triaged
8/18/2023 12:11:58 PM Submission received from Applicant
4/21/2023 7:17:49 AM Submission request sent to Applicant
4/20/2023 9:18:20 AM Request for Review Comments returned by Colorado Division of Water Resources
4/12/2023 1:15:04 PM Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
3/29/2023 2:14:49 PM Submission request sent to Applicant
3/29/2023 2:10:17 PM Request for Review Comments returned by EPC Stormwater Review
3/28/2023 12:49:25 PM Request for Review Comments returned by PCD Project Manager
3/28/2023 12:48:47 PM Request for Review Comments email resent for Project Falcon Acres Final Plat (Reconsideration) for review by Ryan Howser on behalf of PCD Project Manager
3/28/2023 8:11:14 AM Submission request sent to Applicant
3/28/2023 8:09:47 AM Request for Review Comments returned by PCD Engineering Division
3/28/2023 8:09:05 AM Request for Review Comments returned by PCD Project Manager
3/28/2023 8:05:43 AM Request for Review Comments email resent for Project Falcon Acres Final Plat (Reconsideration) for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
3/28/2023 7:10:11 AM Request for Review Comments returned by PCD Engineering Division
3/22/2023 6:15:16 AM Request for Review Comments returned by Pikes Peak Regional Building Department
3/21/2023 5:06:46 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Joanna Williams on behalf of Colorado Division of Water Resources
3/21/2023 3:42:50 PM Request for Review Comments email resent for Project Falcon Acres Final Plat (Reconsideration) for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
3/21/2023 12:59:25 PM Request for Review Comments returned by County Attorney - Development Review
3/21/2023 11:43:16 AM Request for Review Comments returned by County Attorney - Water
3/16/2023 11:00:37 AM Request for Review Comments returned by Pikes Peak Regional Building Department
2/28/2023 4:38:29 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
2/28/2023 4:38:28 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Joseph Martinez on behalf of US Army Corps of Engineers-Pueblo
2/28/2023 4:38:27 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by CDOT Permits Manager Valerie Vigil on behalf of Colorado Department of Transportation - Pueblo Office
2/28/2023 4:38:23 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
2/28/2023 4:38:20 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Catherine McGarvy on behalf of EPC Health Department
2/28/2023 4:38:11 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Edi Anderson on behalf of County Attorney - Water
2/28/2023 4:38:10 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Lori Seago on behalf of County Attorney - Development Review
2/28/2023 4:38:09 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Ryan Howser on behalf of PCD Project Manager
2/28/2023 4:38:07 PM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
2/28/2023 4:27:16 PM Submission Triaged
2/28/2023 3:51:03 PM Submission received from Applicant
2/28/2023 3:16:11 PM Submission request sent to Applicant
2/28/2023 3:15:59 PM Submission Triaged
2/28/2023 11:54:54 AM Submission received from Applicant
2/28/2023 11:31:53 AM Submission request sent to Applicant
2/28/2023 11:29:40 AM Submission request sent to Applicant
2/7/2023 8:22:35 AM Project Manager Assigned: Ryan Howser
5/3/2022 7:23:47 PM Project Manager Assigned: Kylie Bagley
3/19/2022 8:22:31 PM Request for Review Comments returned by EPC Health Department
3/15/2022 7:50:49 AM Request for Review Comments returned by PCD Project Manager
3/15/2022 7:49:53 AM Request for Review Comments email resent for Project Falcon Acres Final Plat (Reconsideration) for review by John Green on behalf of PCD Project Manager
3/7/2022 2:20:14 PM Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
3/1/2022 7:51:48 AM Submission request sent to Applicant
3/1/2022 7:49:52 AM Request for Review Comments returned by PCD Project Manager
3/1/2022 7:44:27 AM Request for Review Comments email resent for Project Falcon Acres Final Plat (Reconsideration) for review by John Green on behalf of PCD Project Manager
2/28/2022 9:00:54 PM Request for Review Comments returned by EPC Stormwater Review
2/28/2022 2:17:03 PM Request for Review Comments returned by Upper Black Squirrel Creek GWMD
2/25/2022 8:44:12 AM Request for Review Comments returned by Colorado Division of Water Resources
2/23/2022 4:36:13 PM Request for Review Comments returned by PCD Project Manager
2/18/2022 1:07:10 PM Submission Triaged
2/17/2022 12:57:31 PM Request for Review Comments returned by Falcon Fire Protection District
2/17/2022 12:24:25 PM Submission received from Applicant
2/16/2022 1:27:18 PM Request for Review Comments returned by Colorado Geological Survey
2/15/2022 5:26:04 PM Submission request sent to Applicant
2/15/2022 12:56:08 PM Request for Review Comments returned by Pikes Peak Regional Building Department
2/14/2022 11:26:21 AM Request for Review Comments returned by Mountain View Electric Association, Inc.
2/14/2022 10:08:31 AM Request for Review Comments returned by PCD Engineering Division
2/10/2022 5:15:33 PM Request for Review Comments returned by Colorado Parks and Wildlife
2/8/2022 1:01:55 PM Request for Review Comments returned by County Attorney - Development Review
1/28/2022 11:01:38 AM Request for Review Comments returned by 911 Authority - El Paso/Teller County
1/26/2022 8:38:38 AM Request for Review Comments returned by Parks Advisory Board
1/26/2022 8:36:07 AM Request for Review Comments returned by EPC Parks Department
1/21/2022 10:46:20 AM Request for Review Comments returned by EPC Environmental Services
1/19/2022 11:07:52 AM Request for Review Comments returned by El Paso County Conservation Dist
1/19/2022 8:15:50 AM Request for Review Comments returned by Colorado State Forest Service
1/18/2022 9:47:51 AM Request for Review Comments returned by County Attorney - Water
1/18/2022 8:45:29 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by General Email on behalf of Mountain View Electric Association, Inc.
1/18/2022 8:45:27 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Melissa Andrews on behalf of Falcon School District 49
1/18/2022 8:45:25 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Fire Chief Trent Harwig on behalf of Falcon Fire Protection District
1/18/2022 8:45:23 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by District Manager Pamela Davison on behalf of El Paso County Conservation Dist
1/18/2022 8:45:20 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Joe Valdez on behalf of Black Hills Energy-Aquila
1/18/2022 8:45:18 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
1/18/2022 8:45:16 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
1/18/2022 8:45:14 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
1/18/2022 8:45:12 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Mr. Andy Schlosberg on behalf of Colorado State Forest Service
1/18/2022 8:45:10 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Kimberly Berscheid on behalf of Colorado Parks and Wildlife
1/18/2022 8:45:03 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Colorado Geological Survey on behalf of Colorado Geological Survey
1/18/2022 8:45:00 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Joanna Williams on behalf of Colorado Division of Water Resources
1/18/2022 8:44:58 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by CDOT Permits Manager Valerie Vigil on behalf of Colorado Department of Transportation - Pueblo Office
1/18/2022 8:44:50 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by on behalf of Parks Advisory Board
1/18/2022 8:44:48 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
1/18/2022 8:44:44 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Commander John Padgett on behalf of EPC Sheriff's Department
1/18/2022 8:44:42 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
1/18/2022 8:44:40 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by on behalf of EPC Parks Department
1/18/2022 8:44:38 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Catherine McGarvy on behalf of EPC Health Department
1/18/2022 8:44:25 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Kathy Andrew on behalf of EPC Environmental Services
1/18/2022 8:44:21 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Edi Anderson on behalf of County Attorney - Water
1/18/2022 8:44:19 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Lori Seago on behalf of County Attorney - Development Review
1/18/2022 8:44:16 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by John Green on behalf of PCD Project Manager
1/18/2022 8:44:14 AM Request for Review Comments email sent for Project Falcon Acres Final Plat (Reconsideration) for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
1/14/2022 10:09:29 AM Fees paid: 1/14/2022 (Receipt: 1005643)
1/13/2022 10:49:52 AM Project Manager Assigned: John Green
1/13/2022 10:49:35 AM Payment Request sent: 1/13/2022
1/13/2022 10:49:35 AM File # Assigned: SF223
1/13/2022 10:49:27 AM Submission Triaged
1/13/2022 8:14:38 AM Submission received from Applicant
12/19/2021 7:51:15 AM Submission request sent to Applicant
12/19/2021 7:51:05 AM Submission Triaged
12/14/2021 4:32:33 PM Submission received from Applicant
3/29/2021 9:37:03 AM Submission request sent to Applicant
3/25/2021 2:57:31 PM Project Manager Assigned: Sophie Kiepe
3/25/2021 2:57:31 PM Project Created