File Number
PPR2244
Project Name
Tri-State-Monument Substation Replacement Site Dev. Plan
Description
Replacement of old substation and its components to correct reliability issues. Substation to remain under 50kV, no additional capacity proposed. Exemption from 1041 approved.; Full Landscape not required with Utility
Location
13382 deposit no.
Parcels
6100000088 6100000088 6121003005 6121003005
Applicant
Tri-State Generation and Transmission Association, Inc.
Transmission Siting, Permitting and Environmental Planning Manage Karl Myers ( kmyers@tristategt.org )
(303) 916-5367
Transmission Siting, Permitting and Environmental Planning Manage Karl Myers ( kmyers@tristategt.org )
(303) 916-5367
File Prefix
PPR - Plot Plan Review
Year
2022
Project Manager
Kylie Bagley
Status
Closed
Created
3/11/2021 7:27:00 AM

View: Review Comments


Approved Documents (12)

Link Document
View Grading & Erosion Control checklist
View Erosion and Stormwater Quality Control Permit (ESQCP)
View Financial Assurance Forms
View Maintenance Agreement (MS Word version required attachments included)
View MS4 Post Construction Form
View PBMP Applicability Form
View PDB/BMP Operations & Maintenance Manual
View Stormwater Detention & Infiltration Design Data Worksheet (SDI Worksheet)
View SWMP checklist
View Grading & Erosion Control Plan
View Site Development Plan
View Drainage Report - Final


Review Documents (24)

Link Document Date
View Application/Petition Form 11/17/2022 8:35:34 AM
View Grading & Erosion Control checklist 3/2/2023 10:02:04 AM
View Legal Description (MS WORD Version required) 11/15/2022 5:15:11 PM
View Letter of Intent 11/16/2022 2:02:46 PM
View Title Commitment (Current within 30 days of submittal) 11/15/2022 5:15:15 PM
View Vicinity/Location Map 11/15/2022 5:15:16 PM
View Erosion and Stormwater Quality Control Permit (ESQCP) 11/22/2022 6:44:27 AM
View Financial Assurance Forms 3/2/2023 10:02:00 AM
View MS4 Post Construction Form 11/22/2022 6:44:28 AM
View O&M Manual 11/22/2022 6:44:29 AM
View PBMP Applicability Form 11/15/2022 5:15:24 PM
View Stormwater Detention & Infiltration Design Data Worksheet (SDI Worksheet) 11/22/2022 6:44:29 AM
View SWMP checklist 11/15/2022 5:15:23 PM
View Grading & Erosion Control Plan 3/31/2023 12:29:05 PM
View Haul Route Plan 11/15/2022 5:15:20 PM
View Landscape Plan drawings 11/15/2022 5:15:10 PM
View Lighting Plan 3/2/2023 10:13:02 AM
View Site Development Plan 3/2/2023 10:02:02 AM
View Drainage Report - Final 3/31/2023 12:29:04 PM
View Detention Maintenance Agreement (MS WORD version required - attachments included) 11/22/2022 6:44:26 AM
View Detention Pond Agreement V3 2/1/2023 2:42:50 PM
View Elevation Plans 11/15/2022 5:15:05 PM
View Proof of submittal of non-jurisdictional water impoundment structure form 3/2/2023 10:02:03 AM
View Stormwater Management Plan 11/15/2022 5:15:25 PM



Events (89)

Date Comment
5/12/2023 3:28:26 PM Project Closed
5/12/2023 3:28:26 PM Project Approved: 5/12/2023
4/19/2023 11:43:32 AM Project Ready for Approval requests. Review Comment period is complete.
4/10/2023 10:28:27 AM Request for Review Comments returned by PCD Project Manager
4/9/2023 12:54:06 PM Request for Review Comments returned by EPC Stormwater Review
4/6/2023 6:23:26 PM Request for Review Comments returned by PCD Engineering Division
4/3/2023 8:24:11 AM Request for Review Comments email sent for Project Tri-State-Monument Substation Replacement Site Dev. Plan for review by Kylie Bagley on behalf of PCD Project Manager
4/3/2023 8:23:45 AM Request for Review Comments email sent for Project Tri-State-Monument Substation Replacement Site Dev. Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
4/3/2023 8:22:42 AM Submission Triaged
3/31/2023 12:30:59 PM Submission received from Applicant
3/29/2023 2:01:42 PM Submission request sent to Applicant
3/29/2023 1:59:13 PM Request for Review Comments returned by PCD Project Manager
3/29/2023 11:19:45 AM Request for Review Comments returned by PCD Engineering Division
3/28/2023 3:29:52 PM Request for Review Comments email sent for Project Tri-State-Monument Substation Replacement Site Dev. Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
3/28/2023 3:29:48 PM Request for Review Comments email sent for Project Tri-State-Monument Substation Replacement Site Dev. Plan for review by Kylie Bagley on behalf of PCD Project Manager
3/28/2023 3:29:46 PM Request for Review Comments email sent for Project Tri-State-Monument Substation Replacement Site Dev. Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
3/28/2023 3:29:04 PM Submission Triaged
3/28/2023 12:11:28 PM Submission received from Applicant
3/24/2023 8:53:37 AM Submission request sent to Applicant
3/23/2023 5:50:55 PM Request for Review Comments returned by EPC Stormwater Review
3/21/2023 1:13:54 PM Request for Review Comments returned by PCD Engineering Division
3/20/2023 3:12:29 PM Request for Review Comments returned by PCD Project Manager
3/16/2023 10:00:51 AM Request for Review Comments returned by Pikes Peak Regional Building Department
3/6/2023 11:29:28 AM Request for Review Comments email sent for Project Tri-State-Monument Substation Replacement Site Dev. Plan for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
3/6/2023 11:29:25 AM Request for Review Comments email sent for Project Tri-State-Monument Substation Replacement Site Dev. Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
3/6/2023 11:29:21 AM Request for Review Comments email sent for Project Tri-State-Monument Substation Replacement Site Dev. Plan for review by Kylie Bagley on behalf of PCD Project Manager
3/6/2023 11:29:18 AM Request for Review Comments email sent for Project Tri-State-Monument Substation Replacement Site Dev. Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
3/6/2023 11:23:28 AM Submission Triaged
3/2/2023 6:13:05 PM Submission received from Applicant
2/10/2023 2:42:28 PM Project Manager Assigned: Kylie Bagley
1/18/2023 7:32:50 PM Request for Review Comments returned by EPC Health Department
12/12/2022 9:12:49 PM Submission request sent to Applicant
12/12/2022 9:09:20 PM Request for Review Comments returned by PCD Project Manager
12/12/2022 1:21:47 PM Request for Review Comments returned by PCD Engineering Division
12/11/2022 6:26:46 PM Request for Review Comments returned by EPC Stormwater Review
12/11/2022 4:13:52 PM Request for Review Comments returned by El Paso County Conservation Dist
11/30/2022 10:52:34 AM Request for Review Comments returned by Pikes Peak Regional Building Department
11/22/2022 4:52:52 PM Request for Review Comments email sent for Project Tri-State-Monument Substation Replacement Site Dev. Plan for review by Planning Director Nina Ruiz on behalf of Monument
11/22/2022 4:52:50 PM Request for Review Comments email sent for Project Tri-State-Monument Substation Replacement Site Dev. Plan for review by District Manager Mariah Hudson on behalf of El Paso County Conservation Dist
11/22/2022 4:52:49 PM Request for Review Comments email sent for Project Tri-State-Monument Substation Replacement Site Dev. Plan for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
11/22/2022 4:52:47 PM Request for Review Comments email sent for Project Tri-State-Monument Substation Replacement Site Dev. Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
11/22/2022 4:52:44 PM Request for Review Comments email sent for Project Tri-State-Monument Substation Replacement Site Dev. Plan for review by Catherine McGarvy on behalf of EPC Health Department
11/22/2022 4:52:38 PM Request for Review Comments email sent for Project Tri-State-Monument Substation Replacement Site Dev. Plan for review by HR Green EPC Consultant on behalf of PCD Project Manager
11/22/2022 4:52:36 PM Request for Review Comments email sent for Project Tri-State-Monument Substation Replacement Site Dev. Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
11/22/2022 4:25:17 PM Submission Triaged
11/22/2022 1:38:28 PM Submission received from Applicant
11/21/2022 5:03:44 PM Submission request sent to Applicant
11/21/2022 4:56:24 PM Submission Triaged
11/21/2022 2:28:24 PM Submission received from Applicant
11/21/2022 1:41:03 PM Submission request sent to Applicant
11/21/2022 1:39:58 PM Submission Triaged
11/19/2022 12:12:11 PM Submission received from Applicant
11/17/2022 3:38:38 PM Submission request sent to Applicant
11/17/2022 2:34:35 PM Submission Triaged
11/17/2022 8:41:38 AM Submission received from Applicant
11/17/2022 8:16:48 AM Submission request sent to Applicant
9/12/2022 8:36:29 PM Request for Review Comments returned by EPC Health Department
8/30/2022 7:24:57 PM Submission request sent to Applicant
8/30/2022 7:22:51 PM Request for Review Comments returned by PCD Project Manager
8/30/2022 6:08:21 PM Request for Review Comments returned by PCD Engineering Division
8/30/2022 5:40:28 PM Request for Review Comments returned by EPC Stormwater Review
8/30/2022 3:55:07 PM Request for Review Comments email resent for Project Tri-State-Monument Substation Replacement Site Dev. Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
8/25/2022 4:57:05 PM Request for Review Comments returned by PCD Engineering Division
8/21/2022 7:33:40 PM Request for Review Comments returned by El Paso County Conservation Dist
8/17/2022 8:40:14 AM Request for Review Comments returned by Pikes Peak Regional Building Department
8/9/2022 12:08:14 PM Request for Review Comments email sent for Project Tri-State-Monument Substation Replacement Site Dev. Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
8/9/2022 12:08:11 PM Request for Review Comments email sent for Project Tri-State-Monument Substation Replacement Site Dev. Plan for review by HR Green EPC Consultant on behalf of PCD Project Manager
8/9/2022 12:08:10 PM Request for Review Comments email sent for Project Tri-State-Monument Substation Replacement Site Dev. Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
8/3/2022 11:48:16 AM Request for Review Comments returned by Monument
8/3/2022 11:46:01 AM Request for Review Comments email sent for Project Tri-State-Monument Substation Replacement Site Dev. Plan for review by Division Chief Jamey Bumgarner on behalf of Tri-Lakes-Monument Fire Protection District
8/3/2022 11:46:00 AM Request for Review Comments email sent for Project Tri-State-Monument Substation Replacement Site Dev. Plan for review by Planning Director Nina Ruiz on behalf of Monument
8/3/2022 11:45:59 AM Request for Review Comments email sent for Project Tri-State-Monument Substation Replacement Site Dev. Plan for review by District Manager Mariah Hudson on behalf of El Paso County Conservation Dist
8/3/2022 11:45:58 AM Request for Review Comments email sent for Project Tri-State-Monument Substation Replacement Site Dev. Plan for review by Joe Valdez on behalf of Black Hills Energy-Aquila
8/3/2022 11:45:56 AM Request for Review Comments email sent for Project Tri-State-Monument Substation Replacement Site Dev. Plan for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
8/3/2022 11:45:55 AM Request for Review Comments email sent for Project Tri-State-Monument Substation Replacement Site Dev. Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
8/3/2022 11:45:51 AM Request for Review Comments email sent for Project Tri-State-Monument Substation Replacement Site Dev. Plan for review by Catherine McGarvy on behalf of EPC Health Department
8/3/2022 11:45:45 AM Request for Review Comments email sent for Project Tri-State-Monument Substation Replacement Site Dev. Plan for review by HR Green EPC Consultant on behalf of PCD Project Manager
8/3/2022 11:45:44 AM Request for Review Comments email sent for Project Tri-State-Monument Substation Replacement Site Dev. Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
7/20/2022 1:55:23 PM Fees paid: 7/20/2022 (Receipt: 1006673)
7/13/2022 11:59:02 AM Project Manager Assigned: HR Green EPC Consultant
7/13/2022 11:58:06 AM Payment Request sent: 7/13/2022
7/13/2022 11:58:06 AM File # Assigned: PPR2244
7/13/2022 11:58:01 AM Submission Triaged
7/13/2022 11:55:24 AM Submission received from Applicant
10/26/2021 12:29:16 PM Submission request sent to Applicant
6/15/2021 1:21:16 PM Submission request sent to Applicant
3/11/2021 7:32:15 AM Submission request sent to Applicant
3/11/2021 7:29:03 AM Project Manager Assigned: Kari Parsons
3/11/2021 7:27:15 AM Project Created