Project Details

Search


File Number
COM2113
Project Name
Black Forest Center On-Site Storage - Screening
Description
Commercial site plan for screening of on-site storage containers
Parcels
5208001008 5208001008
Applicant
Black Forest Center
Michael Esty ( mesty01@gmail.com )
(719) 799-6425
Michael Esty ( mesty01@gmail.com )
(719) 799-6425
File Prefix
COM - Commercial over the counter
Year
2021
Project Manager
Ryan Howser
Status
Closed
Created
1/27/2021 2:36:04 PM

View: Review Comments


Approved Documents (1)

Link Document
View Site Plan Drawing


Review Documents (2)

Link Document Date
View Letter of Intent 4/14/2021 7:24:58 AM
View Site Plan Drawing 3/29/2021 12:33:06 PM



Events (25)

Date Comment
5/5/2021 2:17:00 PM Project Closed
5/5/2021 2:17:00 PM Project Approved: 5/5/2021
4/14/2021 4:40:50 PM Request for Review Comments returned by PCD Project Manager
4/14/2021 4:40:09 PM Request for Review Comments email sent for Project Black Forest Center On-Site Storage - Screening for review by Ryan Howser on behalf of PCD Project Manager
4/14/2021 4:39:51 PM Submission Triaged
4/14/2021 7:25:16 AM Submission received from Applicant
4/7/2021 1:21:32 PM Submission request sent to Applicant
4/2/2021 12:46:57 PM Request for Review Comments returned by PCD Project Manager
3/30/2021 9:03:19 AM Request for Review Comments email sent for Project Black Forest Center On-Site Storage - Screening for review by Ryan Howser on behalf of PCD Project Manager
3/30/2021 9:01:24 AM Submission Triaged
3/29/2021 12:33:44 PM Submission received from Applicant
3/19/2021 11:20:16 AM Submission request sent to Applicant
3/19/2021 11:19:37 AM Request for Review Comments returned by PCD Project Manager
3/17/2021 10:29:02 AM Request for Review Comments returned by PCD Engineering Division
3/16/2021 5:13:16 PM Request for Review Comments email sent for Project Black Forest Center On-Site Storage - Screening for review by Mindy Madden on behalf of EPC Code Enforcement
3/16/2021 5:13:14 PM Request for Review Comments email sent for Project Black Forest Center On-Site Storage - Screening for review by Ryan Howser on behalf of PCD Project Manager
3/16/2021 5:13:12 PM Request for Review Comments email sent for Project Black Forest Center On-Site Storage - Screening for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
3/16/2021 8:35:15 AM Fees paid: 3/16/2021 (Receipt: 1004113)
3/16/2021 6:24:30 AM Payment Request sent: 3/16/2021
3/16/2021 6:24:30 AM File # Assigned: COM2113
3/16/2021 6:24:25 AM Submission Triaged
3/15/2021 5:07:25 PM Submission received from Applicant
1/27/2021 2:38:20 PM Submission request sent to Applicant
1/27/2021 2:36:06 PM Project Manager Assigned: Ryan Howser
1/27/2021 2:36:06 PM Project Created