10/14/2022 4:47:20 PM
|
Project Closed
|
10/14/2022 4:47:20 PM
|
Project Approved: 10/14/2022
|
9/15/2022 10:27:42 AM
|
Project Ready for Approval requests. Review Comment period is complete.
|
9/14/2022 12:47:40 PM
|
Project reopened for Review Comments
|
5/18/2022 10:29:45 AM
|
Project Ready for Approval requests. Review Comment period is complete.
|
3/29/2022 3:39:43 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
3/24/2022 9:17:28 AM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Lori Seago on behalf of County Attorney - Development Review
|
3/23/2022 4:07:31 PM
|
Submission Triaged
|
3/22/2022 2:30:42 PM
|
Submission received from Applicant
|
3/22/2022 7:30:28 AM
|
Submission request sent to Applicant
|
3/8/2022 5:05:20 PM
|
Submission Triaged
|
3/8/2022 2:08:05 PM
|
Submission received from Applicant
|
3/3/2022 4:43:29 PM
|
Submission request sent to Applicant
|
3/3/2022 1:01:31 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
2/25/2022 1:43:23 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Lori Seago on behalf of County Attorney - Development Review
|
2/25/2022 1:42:20 PM
|
Submission Triaged
|
2/24/2022 5:19:46 PM
|
Submission received from Applicant
|
2/3/2022 3:03:07 PM
|
Submission request sent to Applicant
|
2/3/2022 10:29:46 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
2/1/2022 3:16:58 PM
|
Request for Review Comments returned by Black Forest Fire Protection District
|
2/1/2022 1:41:45 PM
|
Request for Review Comments email resent for Project Eagle Forest Filing 1 Final Plat for review by Deputy Chief James Rebitski on behalf of Black Forest Fire Protection District
|
2/1/2022 1:37:46 PM
|
Request for Review Comments returned by PCD Project Manager
|
2/1/2022 1:12:02 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
2/1/2022 9:13:01 AM
|
Request for Review Comments returned by Black Forest Fire Protection District
|
1/31/2022 5:30:18 PM
|
Request for Review Comments returned by PCD Engineering Division
|
1/20/2022 12:14:49 PM
|
Request for Review Comments returned by EPC Environmental Services
|
1/11/2022 1:52:54 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Deputy Chief James Rebitski on behalf of Black Forest Fire Protection District
|
1/11/2022 1:52:50 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
1/11/2022 1:52:46 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Kathy Andrew on behalf of EPC Environmental Services
|
1/11/2022 1:52:44 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Lori Seago on behalf of County Attorney - Development Review
|
1/11/2022 1:52:42 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Ryan Howser on behalf of PCD Project Manager
|
1/11/2022 1:52:38 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
1/11/2022 1:49:19 PM
|
Submission Triaged
|
1/10/2022 12:03:23 PM
|
Submission received from Applicant
|
12/16/2021 5:11:33 PM
|
Submission request sent to Applicant
|
12/7/2021 9:45:39 AM
|
Request for Review Comments returned by PCD Engineering Division
|
12/3/2021 8:38:33 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
12/3/2021 1:39:07 PM
|
Request for Review Comments returned by PCD Project Manager
|
12/2/2021 1:23:09 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
11/19/2021 9:46:35 AM
|
Request for Review Comments returned by Black Forest Fire Protection District
|
11/17/2021 2:00:09 PM
|
Request for Review Comments returned by EPC Environmental Services
|
11/12/2021 5:09:54 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Ryan Howser on behalf of PCD Project Manager
|
11/12/2021 5:09:17 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Deputy Chief James Rebitski on behalf of Black Forest Fire Protection District
|
11/12/2021 5:09:13 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
11/12/2021 5:09:10 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Kathy Andrew on behalf of EPC Environmental Services
|
11/12/2021 5:09:08 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Lori Seago on behalf of County Attorney - Development Review
|
11/12/2021 5:09:05 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Ryan Howser on behalf of PCD Project Manager
|
11/12/2021 5:09:01 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
11/12/2021 4:55:53 PM
|
Submission Triaged
|
11/12/2021 1:22:36 PM
|
Submission received from Applicant
|
11/12/2021 11:20:31 AM
|
Submission request sent to Applicant
|
11/12/2021 11:19:57 AM
|
Submission Triaged
|
11/11/2021 1:56:11 PM
|
Submission received from Applicant
|
11/3/2021 4:54:33 PM
|
Submission request sent to Applicant
|
10/26/2021 9:45:13 AM
|
Request for Review Comments returned by Black Forest Fire Protection District
|
10/25/2021 3:36:02 PM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
10/22/2021 1:22:46 PM
|
Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
|
10/22/2021 11:53:47 AM
|
Request for Review Comments returned by Parks Advisory Board
|
10/13/2021 1:07:24 PM
|
Request for Review Comments returned by PCD Project Manager
|
10/13/2021 12:53:05 PM
|
Request for Review Comments returned by PCD Engineering Division
|
10/11/2021 8:47:45 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
10/9/2021 9:54:18 AM
|
Request for Review Comments returned by Colorado Parks and Wildlife
|
10/7/2021 9:37:14 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
10/4/2021 3:44:45 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
9/29/2021 11:38:43 AM
|
Request for Review Comments returned by Colorado Geological Survey
|
9/24/2021 8:46:59 AM
|
Request for Review Comments returned by Colorado State Forest Service
|
9/20/2021 1:31:20 PM
|
Request for Review Comments returned by EPC Environmental Services
|
9/20/2021 9:36:03 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
9/16/2021 1:29:32 PM
|
Request for Review Comments returned by EPC Parks Department
|
9/15/2021 8:44:18 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
9/14/2021 9:49:49 AM
|
Request for Review Comments returned by County Attorney - Water
|
9/14/2021 8:56:43 AM
|
Request for Review Comments returned by Academy SD 20 Building Fund
|
9/13/2021 4:06:22 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by General Email on behalf of Mountain View Electric Association, Inc.
|
9/13/2021 4:06:20 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
9/13/2021 4:06:18 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Cheryl Pixley on behalf of Black Forest Trails Association
|
9/13/2021 4:06:16 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Terry Stokka on behalf of Black Forest Land Use Committee
|
9/13/2021 4:06:13 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Deputy Chief James Rebitski on behalf of Black Forest Fire Protection District
|
9/13/2021 4:06:11 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Plannig Consultant Donald Smith on behalf of Academy SD 20 Building Fund
|
9/13/2021 4:06:09 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
9/13/2021 4:06:07 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
9/13/2021 4:06:05 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Mr. Andy Schlosberg on behalf of Colorado State Forest Service
|
9/13/2021 4:06:03 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Kimberly Berscheid on behalf of Colorado Parks and Wildlife
|
9/13/2021 4:05:56 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
9/13/2021 4:05:54 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
9/13/2021 4:05:52 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by CDOT Permits Manager Valerie Vigil on behalf of Colorado Department of Transportation - Pueblo Office
|
9/13/2021 4:05:44 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by on behalf of Colorado Department of Public Health and Environment
|
9/13/2021 4:05:42 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by on behalf of Parks Advisory Board
|
9/13/2021 4:05:40 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
9/13/2021 4:05:36 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Commander John Padgett on behalf of EPC Sheriff's Department
|
9/13/2021 4:05:34 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
|
9/13/2021 4:05:32 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by on behalf of EPC Parks Department
|
9/13/2021 4:05:29 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Catherine McGarvy on behalf of EPC Health Department
|
9/13/2021 4:05:20 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Kathy Andrew on behalf of EPC Environmental Services
|
9/13/2021 4:05:18 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Edi Anderson on behalf of County Attorney - Water
|
9/13/2021 4:05:16 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Lori Seago on behalf of County Attorney - Development Review
|
9/13/2021 4:05:14 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Ryan Howser on behalf of PCD Project Manager
|
9/13/2021 4:05:12 PM
|
Request for Review Comments email sent for Project Eagle Forest Filing 1 Final Plat for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
9/13/2021 3:44:23 PM
|
Fees paid: 9/13/2021 (Receipt: 1005084)
|
9/6/2021 9:49:39 AM
|
Payment Request sent: 9/6/2021
|
9/6/2021 9:49:39 AM
|
File # Assigned: SF2131
|
9/6/2021 9:49:28 AM
|
Submission Triaged
|
9/3/2021 4:53:58 PM
|
Submission received from Applicant
|
8/25/2021 7:52:30 AM
|
Submission request sent to Applicant
|
8/25/2021 7:52:05 AM
|
Submission Triaged
|
8/24/2021 1:07:26 PM
|
Submission received from Applicant
|
7/16/2021 1:17:48 PM
|
Submission request sent to Applicant
|
7/1/2021 5:21:37 PM
|
Submission request sent to Applicant
|
7/1/2021 3:09:17 PM
|
Submission request sent to Applicant
|
1/13/2021 4:39:00 PM
|
Submission request sent to Applicant
|
1/13/2021 4:00:17 PM
|
Project Manager Assigned: Ryan Howser
|
1/13/2021 4:00:17 PM
|
EA Assigned: EA19208
|
1/13/2021 4:00:17 PM
|
Project Created
|