Project Details

Search


File Number
PPR2112
Project Name
Discount Tire - Falcon Marketplace Site Development Plan
Description
Major Commercial Site Development Plan for Firestone at Falcon Marketplace
Parcels
5301402002 5301402002
Applicant
Kimley-Horn
Joseph Menke ( Joseph.Menke@kimley-horn.com )
(719) 284-7310
Joseph Menke ( Joseph.Menke@kimley-horn.com )
(719) 284-7310
EA Number
EA20162
File Prefix
PPR - Plot Plan Review
Year
2021
Project Manager
Ryan Howser
Status
Closed
Created
12/4/2020 2:24:25 PM

View: Review Comments


Approved Documents (11)

Link Document
View Grading & Erosion Control checklist
View Erosion and Stormwater Quality Control Permit (ESQCP)
View Financial Assurance Forms
View PBMP Applicability Form
View SWMP checklist
View Construction Drawings (Plans/Profiles)
View Grading & Erosion Control Plan
View Site Development Plan
View Storm Water Management Plan (SWMP)
View Drainage Report - Final
View Traffic Memo


Additional Documents (2)

Link Document Comment
View Recorded Escrow Agreement
View Revised CDs utility details


Review Documents (27)

Link Document Date
View Application/Petition Form 9/7/2021 2:14:33 PM
View Grading & Erosion Control checklist 9/7/2021 2:14:56 PM
View Legal Description (MS WORD Version required) 2/23/2021 11:14:19 AM
View Letter of Intent 4/23/2021 3:50:24 PM
View Title Commitment (Current within 30 days of submittal) 2/23/2021 11:16:38 AM
View Vicinity/Location Map 2/23/2021 11:16:40 AM
View Erosion and Stormwater Quality Control Permit (ESQCP) 9/7/2021 2:14:44 PM
View Financial Assurance Forms 9/7/2021 2:14:36 PM
View Floor Plans (24" x 36") 2/23/2021 11:14:19 AM
View PBMP Applicability Form 9/7/2021 2:14:58 PM
View SWMP checklist 9/7/2021 2:14:57 PM
View Construction Drawings (Plans/Profiles) 9/7/2021 2:14:34 PM
View Grading & Erosion Control Plan 9/7/2021 2:14:37 PM
View Landscape Plan drawings 9/7/2021 2:14:44 PM
View Lighting Plan 4/23/2021 3:50:24 PM
View Sign Plan 2/23/2021 11:14:22 AM
View Site Development Plan 9/30/2021 12:28:42 PM
View Storm Water Management Plan (SWMP) 9/7/2021 2:14:45 PM
View Commitment letter from waste water service provider 2/24/2021 12:05:14 PM
View Commitment letter from water service provider 2/24/2021 12:05:13 PM
View Drainage Report - Final 9/7/2021 2:14:36 PM
View Traffic Impact Study 2/23/2021 11:16:39 AM
View Detention Maintenance Agreement (MS WORD version required - attachments included) 2/23/2021 11:12:43 AM
View Escrow agreement 10/1/2021 10:07:41 AM
View Comment Response Letter 4/23/2021 3:48:52 PM
View Comment Response Letter 9/7/2021 2:20:43 PM
View Elevation Plans 2/23/2021 11:13:10 AM



Events (90)

Date Comment
11/24/2021 2:19:18 PM Project Closed
11/24/2021 2:19:18 PM Project Approved: 11/24/2021
11/3/2021 4:49:51 PM Project Ready for Approval requests. Review Comment period is complete.
10/11/2021 8:12:34 PM Request for Review Comments returned by County Attorney - Development Review
10/1/2021 11:33:59 AM Request for Review Comments returned by PCD Project Manager
10/1/2021 11:31:50 AM Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Lori Seago on behalf of County Attorney - Development Review
10/1/2021 11:31:48 AM Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Ryan Howser on behalf of PCD Project Manager
10/1/2021 11:31:09 AM Submission Triaged
10/1/2021 10:28:41 AM Submission received from Applicant
9/30/2021 10:39:59 AM Submission request sent to Applicant
9/29/2021 4:49:03 PM Request for Review Comments returned by PCD Project Manager
9/28/2021 2:54:19 PM Request for Review Comments returned by PCD Engineering Division
9/20/2021 11:32:44 AM Request for Review Comments returned by County Attorney - Development Review
9/14/2021 11:17:37 AM Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Lori Seago on behalf of County Attorney - Development Review
9/14/2021 11:17:35 AM Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Ryan Howser on behalf of PCD Project Manager
9/14/2021 11:17:27 AM Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
9/14/2021 10:11:37 AM Submission Triaged
9/14/2021 10:02:14 AM Submission received from Applicant
9/14/2021 9:40:55 AM Submission request sent to Applicant
9/14/2021 9:40:40 AM Submission Triaged
9/13/2021 5:23:46 PM Submission received from Applicant
9/8/2021 11:29:42 AM Submission request sent to Applicant
9/8/2021 11:28:40 AM Submission Triaged
9/7/2021 2:21:11 PM Submission received from Applicant
9/7/2021 1:19:46 PM Submission request sent to Applicant
5/27/2021 8:38:16 AM Submission request sent to Applicant
5/20/2021 5:04:26 PM Request for Review Comments returned by PCD Project Manager
5/20/2021 4:51:47 PM Request for Review Comments returned by PCD Engineering Division
5/14/2021 9:55:45 AM Request for Review Comments returned by EPC Stormwater Review
5/12/2021 1:45:32 PM Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Ryan Howser on behalf of PCD Project Manager
5/12/2021 1:45:24 PM Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
5/10/2021 3:50:55 PM Request for Review Comments returned by Mountain View Electric Association, Inc.
4/23/2021 4:58:28 PM Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by General Email on behalf of Mountain View Electric Association, Inc.
4/23/2021 4:58:24 PM Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
4/23/2021 4:58:21 PM Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Ryan Howser on behalf of PCD Project Manager
4/23/2021 4:58:17 PM Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
4/23/2021 4:57:10 PM Submission Triaged
4/23/2021 3:58:48 PM Submission received from Applicant
4/7/2021 12:11:45 PM Request for Review Comments returned by Woodmen Road Metro
4/7/2021 9:12:05 AM Submission request sent to Applicant
4/2/2021 2:08:35 PM Request for Review Comments returned by PCD Project Manager
4/2/2021 12:49:30 PM Request for Review Comments email resent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Ryan Howser on behalf of PCD Project Manager
4/2/2021 11:37:53 AM Request for Review Comments returned by PCD Engineering Division
3/25/2021 4:56:58 PM Request for Review Comments returned by Mountain View Electric Association, Inc.
3/22/2021 12:09:01 PM Request for Review Comments returned by Woodmen Hills Metro
3/19/2021 11:02:54 AM Request for Review Comments returned by PCD Project Manager
3/19/2021 10:48:43 AM Request for Review Comments returned by Pikes Peak Regional Building Department
3/18/2021 10:40:59 AM Request for Review Comments returned by County Attorney - Development Review
3/17/2021 11:03:22 AM Request for Review Comments returned by EPC Stormwater Review
3/17/2021 7:36:38 AM Request for Review Comments returned by El Paso County Conservation Dist
3/16/2021 2:56:50 PM Request for Review Comments returned by Falcon Fire Protection District
3/11/2021 10:37:52 AM Request for Review Comments returned by 911 Authority - El Paso/Teller County
3/4/2021 7:15:33 PM Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
3/3/2021 2:24:55 PM Request for Review Comments returned by Upper Black Squirrel Creek GWMD
3/2/2021 9:40:24 AM Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
2/26/2021 1:01:49 PM Request for Review Comments returned by RBD Floodplain
2/26/2021 11:51:09 AM Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Rebecca Hardekopf on behalf of Woodmen Road Metro
2/26/2021 11:51:06 AM Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Jerry Jacobson on behalf of Woodmen Hills Metro
2/26/2021 11:51:04 AM Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by General Email on behalf of Mountain View Electric Association, Inc.
2/26/2021 11:51:02 AM Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Roger Austin on behalf of Mountain Metro Transit (City of COS)
2/26/2021 11:51:00 AM Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Fire Chief Trent Harwig on behalf of Falcon Fire Protection District
2/26/2021 11:50:58 AM Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by District Manager Pamela Davison on behalf of El Paso County Conservation Dist
2/26/2021 11:50:56 AM Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by UDS Admin Staff on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
2/26/2021 11:50:54 AM Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Meggan Herington on behalf of Colorado Springs Planning & Community Development
2/26/2021 11:50:52 AM Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
2/26/2021 11:50:50 AM Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Keith Curtis on behalf of RBD Floodplain
2/26/2021 11:50:48 AM Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
2/26/2021 11:50:45 AM Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
2/26/2021 11:50:43 AM Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Elaine Kelly on behalf of US Postal Service
2/26/2021 11:50:41 AM Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
2/26/2021 11:50:36 AM Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
2/26/2021 11:50:34 AM Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Catherine McGarvy on behalf of EPC Health Department
2/26/2021 11:50:25 AM Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Lori Seago on behalf of County Attorney - Development Review
2/26/2021 11:50:23 AM Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Ryan Howser on behalf of PCD Project Manager
2/26/2021 11:50:21 AM Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
2/26/2021 10:22:54 AM Fees paid: 2/26/2021 (Receipt: 1004011)
2/24/2021 5:28:30 PM Submission Triaged
2/24/2021 12:05:40 PM Submission received from Applicant
2/24/2021 12:02:29 PM Submission request sent to Applicant
2/23/2021 9:02:45 PM Payment Request sent: 2/23/2021
2/23/2021 9:02:45 PM File # Assigned: PPR2112
2/23/2021 9:02:33 PM Submission Triaged
2/23/2021 11:34:24 AM Submission received from Applicant
2/23/2021 10:53:08 AM Submission request sent to Applicant
2/23/2021 10:08:15 AM Submission Triaged
2/22/2021 5:46:13 PM Submission received from Applicant
12/9/2020 8:56:45 AM Submission request sent to Applicant
12/4/2020 2:24:35 PM Project Manager Assigned: Ryan Howser
12/4/2020 2:24:35 PM EA Assigned: EA20162
12/4/2020 2:24:35 PM Project Created