11/24/2021 2:19:18 PM
|
Project Closed
|
11/24/2021 2:19:18 PM
|
Project Approved: 11/24/2021
|
11/3/2021 4:49:51 PM
|
Project Ready for Approval requests. Review Comment period is complete.
|
10/11/2021 8:12:34 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
10/1/2021 11:33:59 AM
|
Request for Review Comments returned by PCD Project Manager
|
10/1/2021 11:31:50 AM
|
Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Lori Seago on behalf of County Attorney - Development Review
|
10/1/2021 11:31:48 AM
|
Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Ryan Howser on behalf of PCD Project Manager
|
10/1/2021 11:31:09 AM
|
Submission Triaged
|
10/1/2021 10:28:41 AM
|
Submission received from Applicant
|
9/30/2021 10:39:59 AM
|
Submission request sent to Applicant
|
9/29/2021 4:49:03 PM
|
Request for Review Comments returned by PCD Project Manager
|
9/28/2021 2:54:19 PM
|
Request for Review Comments returned by PCD Engineering Division
|
9/20/2021 11:32:44 AM
|
Request for Review Comments returned by County Attorney - Development Review
|
9/14/2021 11:17:37 AM
|
Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Lori Seago on behalf of County Attorney - Development Review
|
9/14/2021 11:17:35 AM
|
Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Ryan Howser on behalf of PCD Project Manager
|
9/14/2021 11:17:27 AM
|
Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
9/14/2021 10:11:37 AM
|
Submission Triaged
|
9/14/2021 10:02:14 AM
|
Submission received from Applicant
|
9/14/2021 9:40:55 AM
|
Submission request sent to Applicant
|
9/14/2021 9:40:40 AM
|
Submission Triaged
|
9/13/2021 5:23:46 PM
|
Submission received from Applicant
|
9/8/2021 11:29:42 AM
|
Submission request sent to Applicant
|
9/8/2021 11:28:40 AM
|
Submission Triaged
|
9/7/2021 2:21:11 PM
|
Submission received from Applicant
|
9/7/2021 1:19:46 PM
|
Submission request sent to Applicant
|
5/27/2021 8:38:16 AM
|
Submission request sent to Applicant
|
5/20/2021 5:04:26 PM
|
Request for Review Comments returned by PCD Project Manager
|
5/20/2021 4:51:47 PM
|
Request for Review Comments returned by PCD Engineering Division
|
5/14/2021 9:55:45 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
5/12/2021 1:45:32 PM
|
Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Ryan Howser on behalf of PCD Project Manager
|
5/12/2021 1:45:24 PM
|
Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
5/10/2021 3:50:55 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
4/23/2021 4:58:28 PM
|
Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by General Email on behalf of Mountain View Electric Association, Inc.
|
4/23/2021 4:58:24 PM
|
Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
4/23/2021 4:58:21 PM
|
Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Ryan Howser on behalf of PCD Project Manager
|
4/23/2021 4:58:17 PM
|
Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
4/23/2021 4:57:10 PM
|
Submission Triaged
|
4/23/2021 3:58:48 PM
|
Submission received from Applicant
|
4/7/2021 12:11:45 PM
|
Request for Review Comments returned by Woodmen Road Metro
|
4/7/2021 9:12:05 AM
|
Submission request sent to Applicant
|
4/2/2021 2:08:35 PM
|
Request for Review Comments returned by PCD Project Manager
|
4/2/2021 12:49:30 PM
|
Request for Review Comments email resent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Ryan Howser on behalf of PCD Project Manager
|
4/2/2021 11:37:53 AM
|
Request for Review Comments returned by PCD Engineering Division
|
3/25/2021 4:56:58 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
3/22/2021 12:09:01 PM
|
Request for Review Comments returned by Woodmen Hills Metro
|
3/19/2021 11:02:54 AM
|
Request for Review Comments returned by PCD Project Manager
|
3/19/2021 10:48:43 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
3/18/2021 10:40:59 AM
|
Request for Review Comments returned by County Attorney - Development Review
|
3/17/2021 11:03:22 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
3/17/2021 7:36:38 AM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
3/16/2021 2:56:50 PM
|
Request for Review Comments returned by Falcon Fire Protection District
|
3/11/2021 10:37:52 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
3/4/2021 7:15:33 PM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
3/3/2021 2:24:55 PM
|
Request for Review Comments returned by Upper Black Squirrel Creek GWMD
|
3/2/2021 9:40:24 AM
|
Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
2/26/2021 1:01:49 PM
|
Request for Review Comments returned by RBD Floodplain
|
2/26/2021 11:51:09 AM
|
Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Rebecca Hardekopf on behalf of Woodmen Road Metro
|
2/26/2021 11:51:06 AM
|
Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Jerry Jacobson on behalf of Woodmen Hills Metro
|
2/26/2021 11:51:04 AM
|
Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by General Email on behalf of Mountain View Electric Association, Inc.
|
2/26/2021 11:51:02 AM
|
Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Roger Austin on behalf of Mountain Metro Transit (City of COS)
|
2/26/2021 11:51:00 AM
|
Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Fire Chief Trent Harwig on behalf of Falcon Fire Protection District
|
2/26/2021 11:50:58 AM
|
Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by District Manager Pamela Davison on behalf of El Paso County Conservation Dist
|
2/26/2021 11:50:56 AM
|
Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by UDS Admin Staff on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
2/26/2021 11:50:54 AM
|
Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Meggan Herington on behalf of Colorado Springs Planning & Community Development
|
2/26/2021 11:50:52 AM
|
Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
|
2/26/2021 11:50:50 AM
|
Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Keith Curtis on behalf of RBD Floodplain
|
2/26/2021 11:50:48 AM
|
Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
2/26/2021 11:50:45 AM
|
Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
2/26/2021 11:50:43 AM
|
Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Elaine Kelly on behalf of US Postal Service
|
2/26/2021 11:50:41 AM
|
Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
2/26/2021 11:50:36 AM
|
Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
|
2/26/2021 11:50:34 AM
|
Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Catherine McGarvy on behalf of EPC Health Department
|
2/26/2021 11:50:25 AM
|
Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Lori Seago on behalf of County Attorney - Development Review
|
2/26/2021 11:50:23 AM
|
Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Ryan Howser on behalf of PCD Project Manager
|
2/26/2021 11:50:21 AM
|
Request for Review Comments email sent for Project Discount Tire - Falcon Marketplace Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
2/26/2021 10:22:54 AM
|
Fees paid: 2/26/2021 (Receipt: 1004011)
|
2/24/2021 5:28:30 PM
|
Submission Triaged
|
2/24/2021 12:05:40 PM
|
Submission received from Applicant
|
2/24/2021 12:02:29 PM
|
Submission request sent to Applicant
|
2/23/2021 9:02:45 PM
|
Payment Request sent: 2/23/2021
|
2/23/2021 9:02:45 PM
|
File # Assigned: PPR2112
|
2/23/2021 9:02:33 PM
|
Submission Triaged
|
2/23/2021 11:34:24 AM
|
Submission received from Applicant
|
2/23/2021 10:53:08 AM
|
Submission request sent to Applicant
|
2/23/2021 10:08:15 AM
|
Submission Triaged
|
2/22/2021 5:46:13 PM
|
Submission received from Applicant
|
12/9/2020 8:56:45 AM
|
Submission request sent to Applicant
|
12/4/2020 2:24:35 PM
|
Project Manager Assigned: Ryan Howser
|
12/4/2020 2:24:35 PM
|
EA Assigned: EA20162
|
12/4/2020 2:24:35 PM
|
Project Created
|