12/7/2021 8:27:09 AM
|
Project Closed
|
12/7/2021 8:27:09 AM
|
Project Approved: 12/7/2021
|
11/16/2021 2:10:30 PM
|
Submission request sent to Applicant
|
9/8/2021 12:00:41 PM
|
Request for Review Comments returned by County Attorney - Water
|
9/8/2021 11:36:39 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by Jackie Evans on behalf of Kiowa Conservation Dist
|
9/8/2021 11:36:37 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by Melissa Andrews on behalf of Falcon School District 49
|
9/8/2021 11:36:35 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
9/8/2021 11:36:30 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by Edi Anderson on behalf of County Attorney - Water
|
9/1/2021 8:31:14 AM
|
Request for Review Comments returned by County Attorney - Water
|
8/17/2021 11:01:05 AM
|
Submission request sent to Applicant
|
8/17/2021 10:55:55 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by Edi Anderson on behalf of County Attorney - Water
|
8/17/2021 10:54:42 AM
|
Submission request sent to Applicant
|
8/17/2021 10:52:58 AM
|
Request for Review Comments returned by PCD Project Manager
|
8/17/2021 10:51:47 AM
|
Request for Review Comments email resent for Project 10675 Hardy Road - Minor Subdivision for review by John Green on behalf of PCD Project Manager
|
7/29/2021 10:13:20 AM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
7/26/2021 4:14:51 PM
|
Request for Review Comments returned by PCD Engineering Division
|
7/25/2021 2:43:16 PM
|
Request for Review Comments returned by PCD Project Manager
|
7/15/2021 11:33:07 AM
|
Request for Review Comments returned by County Attorney - Development Review
|
7/6/2021 1:00:38 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
7/6/2021 8:03:50 AM
|
Request for Review Comments returned by County Attorney - Water
|
7/6/2021 7:17:41 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
7/6/2021 7:17:37 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
7/6/2021 7:17:33 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by Edi Anderson on behalf of County Attorney - Water
|
7/6/2021 7:17:31 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by Lori Seago on behalf of County Attorney - Development Review
|
7/6/2021 7:17:29 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by John Green on behalf of PCD Project Manager
|
7/6/2021 7:17:25 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
7/6/2021 7:15:42 AM
|
Submission Triaged
|
7/5/2021 12:44:10 PM
|
Submission received from Applicant
|
6/28/2021 12:25:14 PM
|
Submission request sent to Applicant
|
6/28/2021 12:24:16 PM
|
Request for Review Comments returned by PCD Project Manager
|
6/28/2021 12:23:07 PM
|
Request for Review Comments email resent for Project 10675 Hardy Road - Minor Subdivision for review by John Green on behalf of PCD Project Manager
|
6/15/2021 4:45:51 PM
|
Submission request sent to Applicant
|
6/15/2021 4:44:13 PM
|
Request for Review Comments returned by PCD Project Manager
|
6/15/2021 4:39:28 PM
|
Request for Review Comments email resent for Project 10675 Hardy Road - Minor Subdivision for review by John Green on behalf of PCD Project Manager
|
6/15/2021 4:39:02 PM
|
Request for Review Comments email resent for Project 10675 Hardy Road - Minor Subdivision for review by John Green on behalf of PCD Project Manager
|
6/15/2021 9:32:46 AM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
6/10/2021 4:50:41 PM
|
Request for Review Comments returned by PCD Project Manager
|
6/8/2021 5:17:29 PM
|
Request for Review Comments returned by PCD Engineering Division
|
6/7/2021 9:43:45 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
5/27/2021 2:15:01 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
5/21/2021 8:05:31 AM
|
Request for Review Comments returned by County Attorney - Water
|
5/20/2021 4:12:12 PM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by General Email on behalf of Mountain View Electric Association, Inc.
|
5/20/2021 4:12:08 PM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
5/20/2021 4:12:04 PM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
5/20/2021 4:12:02 PM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by Edi Anderson on behalf of County Attorney - Water
|
5/20/2021 4:12:00 PM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by John Green on behalf of PCD Project Manager
|
5/20/2021 4:11:54 PM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
5/20/2021 4:10:13 PM
|
Submission Triaged
|
5/16/2021 2:08:51 PM
|
Submission received from Applicant
|
4/13/2021 8:09:04 PM
|
Request for Review Comments returned by EPC Health Department
|
4/7/2021 7:27:15 AM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
4/6/2021 11:54:04 AM
|
Submission request sent to Applicant
|
4/6/2021 11:49:32 AM
|
Request for Review Comments returned by PCD Project Manager
|
4/6/2021 9:25:53 AM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
4/5/2021 5:36:57 PM
|
Request for Review Comments returned by PCD Engineering Division
|
4/1/2021 5:39:17 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
3/30/2021 7:36:05 AM
|
Request for Review Comments returned by Colorado Geological Survey
|
3/29/2021 2:17:06 PM
|
Request for Review Comments email resent for Project 10675 Hardy Road - Minor Subdivision for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
3/29/2021 2:08:25 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
3/29/2021 2:02:11 PM
|
Request for Review Comments returned by US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
3/29/2021 12:53:23 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
3/25/2021 12:00:24 PM
|
Request for Review Comments returned by Colorado Geological Survey
|
3/23/2021 11:10:11 AM
|
Request for Review Comments returned by EPC Environmental Services
|
3/18/2021 10:02:15 AM
|
Request for Review Comments returned by EPC Parks Department
|
3/17/2021 9:46:29 AM
|
Request for Review Comments returned by County Attorney - Development Review
|
3/16/2021 10:18:27 AM
|
Request for Review Comments returned by Colorado State Forest Service
|
3/16/2021 8:40:42 AM
|
Request for Review Comments returned by Colorado Parks and Wildlife
|
3/16/2021 8:34:58 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
3/9/2021 3:47:42 PM
|
Request for Review Comments returned by Falcon Fire Protection District
|
3/8/2021 9:51:46 AM
|
Request for Review Comments returned by County Attorney - Water
|
3/8/2021 9:27:25 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by John Green on behalf of PCD Project Manager
|
3/8/2021 9:27:22 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
3/8/2021 9:26:18 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by General Email on behalf of Mountain View Electric Association, Inc.
|
3/8/2021 9:26:16 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by Jackie Evans on behalf of Kiowa Conservation Dist
|
3/8/2021 9:26:14 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by Melissa Andrews on behalf of Falcon School District 49
|
3/8/2021 9:26:12 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by Fire Chief Trent Harwig on behalf of Falcon Fire Protection District
|
3/8/2021 9:26:10 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by District Manager Pamela Davison on behalf of El Paso County Conservation Dist
|
3/8/2021 9:26:08 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
3/8/2021 9:26:03 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
3/8/2021 9:26:01 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
3/8/2021 9:25:59 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by DeBerry Drew on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
3/8/2021 9:25:56 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by Mr. Andy Schlosberg on behalf of Colorado State Forest Service
|
3/8/2021 9:25:54 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by Energy and Land Use Specialist Karen Voltura on behalf of Colorado Parks and Wildlife
|
3/8/2021 9:25:52 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
3/8/2021 9:25:50 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
3/8/2021 9:25:48 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
3/8/2021 9:25:46 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by on behalf of EPC Parks Department
|
3/8/2021 9:25:44 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by Catherine McGarvy on behalf of EPC Health Department
|
3/8/2021 9:25:36 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by Kathy Andrew on behalf of EPC Environmental Services
|
3/8/2021 9:25:33 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by Edi Anderson on behalf of County Attorney - Water
|
3/8/2021 9:25:31 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by Lori Seago on behalf of County Attorney - Development Review
|
3/8/2021 9:25:29 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by John Green on behalf of PCD Project Manager
|
3/8/2021 9:25:27 AM
|
Request for Review Comments email sent for Project 10675 Hardy Road - Minor Subdivision for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
3/1/2021 9:22:11 PM
|
Fees paid: 3/1/2021 (Receipt: 1004026)
|
3/1/2021 9:07:23 PM
|
Payment Request sent: 3/1/2021
|
3/1/2021 9:07:22 PM
|
File # Assigned: MS213
|
3/1/2021 9:07:16 PM
|
Submission Triaged
|
2/28/2021 9:03:02 PM
|
Submission received from Applicant
|
2/24/2021 5:28:11 PM
|
Submission request sent to Applicant
|
2/24/2021 5:28:03 PM
|
Submission Triaged
|
2/24/2021 5:15:23 PM
|
Submission received from Applicant
|
2/23/2021 8:21:49 PM
|
Submission request sent to Applicant
|
2/23/2021 8:12:10 PM
|
Submission Triaged
|
2/22/2021 9:57:26 PM
|
Project Manager Assigned: John Green
|
2/22/2021 8:57:12 AM
|
Submission received from Applicant
|
2/22/2021 8:24:09 AM
|
Submission request sent to Applicant
|
2/8/2021 1:11:41 PM
|
Submission request sent to Applicant
|
2/5/2021 2:06:25 PM
|
Submission request sent to Applicant
|
1/28/2021 11:36:00 AM
|
Submission request sent to Applicant
|
1/19/2021 1:18:12 PM
|
Submission request sent to Applicant
|
12/31/2020 9:31:34 AM
|
Submission request sent to Applicant
|
10/27/2020 10:50:33 AM
|
Submission request sent to Applicant
|
9/25/2020 9:45:13 AM
|
Project Manager Assigned: Sophie Kiepe
|
9/25/2020 9:45:13 AM
|
Project Created
|