5/8/2025 2:47:43 PM
|
Project Closed
|
5/8/2025 2:47:42 PM
|
Project Cancelled: 5/8/2025
|
1/13/2023 2:00:01 PM
|
Submission request sent to Applicant
|
1/13/2023 1:42:26 PM
|
Request for Review Comments returned by PCD Project Manager
|
1/12/2023 12:31:04 PM
|
Request for Review Comments returned by PCD Engineering Division
|
1/12/2023 12:25:24 PM
|
Project Manager Assigned: Ashlyn Mathy
|
1/12/2023 12:13:08 PM
|
Submission Triaged
|
1/12/2023 12:10:17 PM
|
Project Manager Assigned: Cristel Madden
|
1/12/2023 11:54:47 AM
|
Request for Review Comments email resent for Project Fuel Missions Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
1/12/2023 11:52:35 AM
|
Submission Triaged
|
1/12/2023 11:09:13 AM
|
Project Manager Assigned: Christian Haas
|
1/12/2023 8:34:09 AM
|
Request for Review Comments returned by PCD Engineering Division
|
1/11/2023 8:54:03 AM
|
Project Manager Assigned: Cristel Madden
|
1/10/2023 2:35:36 PM
|
Request for Review Comments email resent for Project Fuel Missions Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
1/9/2023 4:04:57 PM
|
Request for Review Comments returned by PCD Engineering Division
|
1/9/2023 2:28:38 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
1/4/2023 11:33:07 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
12/21/2022 2:15:24 PM
|
Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
|
12/21/2022 1:47:03 PM
|
Request for Review Comments email sent for Project Fuel Missions Site Development Plan for review by Division Chief Jamey Bumgarner on behalf of Tri-Lakes-Monument Fire Protection District
|
12/21/2022 1:47:02 PM
|
Request for Review Comments email sent for Project Fuel Missions Site Development Plan for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
12/21/2022 1:47:00 PM
|
Request for Review Comments email sent for Project Fuel Missions Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
12/21/2022 1:46:52 PM
|
Request for Review Comments email sent for Project Fuel Missions Site Development Plan for review by Christian Haas on behalf of PCD Project Manager
|
12/21/2022 1:46:51 PM
|
Request for Review Comments email sent for Project Fuel Missions Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
12/21/2022 1:34:52 PM
|
Submission Triaged
|
12/21/2022 8:00:36 AM
|
Project Manager Assigned: Christian Haas
|
12/21/2022 7:58:41 AM
|
Submission received from Applicant
|
3/8/2022 1:45:11 PM
|
Submission request sent to Applicant
|
3/8/2022 1:44:06 PM
|
Request for Review Comments returned by PCD Project Manager
|
3/8/2022 1:39:57 PM
|
Request for Review Comments email resent for Project Fuel Missions Site Development Plan for review by Kylie Bagley on behalf of PCD Project Manager
|
3/8/2022 12:29:41 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
3/7/2022 10:13:55 PM
|
Request for Review Comments returned by PCD Engineering Division
|
3/7/2022 8:41:26 AM
|
Request for Review Comments returned by PCD Project Manager
|
2/11/2022 2:55:52 PM
|
Request for Review Comments email sent for Project Fuel Missions Site Development Plan for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
2/11/2022 2:55:41 PM
|
Request for Review Comments email sent for Project Fuel Missions Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
2/11/2022 2:55:35 PM
|
Request for Review Comments email sent for Project Fuel Missions Site Development Plan for review by Kylie Bagley on behalf of PCD Project Manager
|
2/11/2022 2:55:31 PM
|
Request for Review Comments email sent for Project Fuel Missions Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
2/11/2022 2:41:34 PM
|
Submission Triaged
|
2/11/2022 1:51:51 PM
|
Submission received from Applicant
|
1/24/2022 8:54:06 AM
|
Submission request sent to Applicant
|
1/13/2022 11:06:51 AM
|
Project Manager Assigned: Kylie Bagley
|
8/26/2021 4:09:20 PM
|
Request for Review Comments returned by US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
8/8/2021 9:29:09 PM
|
Request for Review Comments returned by EPC Health Department
|
8/3/2021 4:09:13 PM
|
Submission request sent to Applicant
|
8/3/2021 4:08:06 PM
|
Request for Review Comments returned by PCD Project Manager
|
8/3/2021 4:04:45 PM
|
Request for Review Comments email resent for Project Fuel Missions Site Development Plan for review by Mercedes Rivas on behalf of PCD Project Manager
|
8/2/2021 6:15:51 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
8/2/2021 5:22:43 PM
|
Request for Review Comments returned by PCD Engineering Division
|
7/29/2021 12:24:39 PM
|
Request for Review Comments returned by PCD Project Manager
|
7/15/2021 1:50:46 PM
|
Request for Review Comments email sent for Project Fuel Missions Site Development Plan for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
7/15/2021 1:50:42 PM
|
Request for Review Comments email sent for Project Fuel Missions Site Development Plan for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
7/15/2021 1:50:38 PM
|
Request for Review Comments email sent for Project Fuel Missions Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
7/15/2021 1:50:31 PM
|
Request for Review Comments email sent for Project Fuel Missions Site Development Plan for review by Catherine McGarvy on behalf of EPC Health Department
|
7/15/2021 1:50:21 PM
|
Request for Review Comments email sent for Project Fuel Missions Site Development Plan for review by Mercedes Rivas on behalf of PCD Project Manager
|
7/15/2021 1:50:17 PM
|
Request for Review Comments email sent for Project Fuel Missions Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
7/15/2021 1:47:16 PM
|
Submission Triaged
|
7/15/2021 11:13:52 AM
|
Submission received from Applicant
|
6/10/2021 5:06:39 PM
|
Project Manager Assigned: Mercedes Rivas
|
1/28/2021 1:45:47 PM
|
Submission request sent to Applicant
|
1/28/2021 1:32:03 PM
|
Request for Review Comments returned by PCD Project Manager
|
1/28/2021 12:53:37 PM
|
Request for Review Comments email resent for Project Fuel Missions Site Development Plan for review by Sophie Kiepe on behalf of PCD Project Manager
|
1/26/2021 8:52:14 PM
|
Request for Review Comments returned by PCD Engineering Division
|
1/21/2021 10:38:31 AM
|
Request for Review Comments returned by PCD Project Manager
|
1/20/2021 4:09:44 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
1/19/2021 10:41:24 AM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
1/14/2021 11:54:46 AM
|
Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
|
1/11/2021 4:41:43 PM
|
Request for Review Comments email sent for Project Fuel Missions Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
1/11/2021 4:00:09 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
1/5/2021 9:02:52 AM
|
Request for Review Comments returned by Lewis Palmer 38
|
1/4/2021 3:50:23 PM
|
Request for Review Comments email resent for Project Fuel Missions Site Development Plan for review by Vicki Wood on behalf of Lewis Palmer 38
|
1/4/2021 2:27:53 PM
|
Request for Review Comments returned by Lewis Palmer 38
|
1/4/2021 2:09:56 PM
|
Request for Review Comments email resent for Project Fuel Missions Site Development Plan for review by Vicki Wood on behalf of Lewis Palmer 38
|
1/4/2021 9:43:21 AM
|
Request for Review Comments returned by Lewis Palmer 38
|
12/30/2020 11:38:09 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
12/30/2020 8:59:23 AM
|
Request for Review Comments email sent for Project Fuel Missions Site Development Plan for review by Sophie Kiepe on behalf of PCD Project Manager
|
12/30/2020 8:49:28 AM
|
Request for Review Comments email sent for Project Fuel Missions Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
12/30/2020 8:48:58 AM
|
Request for Review Comments email sent for Project Fuel Missions Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
12/29/2020 12:01:07 PM
|
Request for Review Comments email sent for Project Fuel Missions Site Development Plan for review by Jamey Bumgarner on behalf of Tri-Lakes-Monument Fire Protection District
|
12/29/2020 12:01:05 PM
|
Request for Review Comments email sent for Project Fuel Missions Site Development Plan for review by Administrative Assistant Cathy Hansen-Lee on behalf of Mountain View Electric Association, Inc.
|
12/29/2020 12:01:02 PM
|
Request for Review Comments email sent for Project Fuel Missions Site Development Plan for review by Vicki Wood on behalf of Lewis Palmer 38
|
12/29/2020 12:01:00 PM
|
Request for Review Comments email sent for Project Fuel Missions Site Development Plan for review by District Manager Pamela Davison on behalf of El Paso County Conservation Dist
|
12/29/2020 12:00:58 PM
|
Request for Review Comments email sent for Project Fuel Missions Site Development Plan for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
12/29/2020 12:00:56 PM
|
Request for Review Comments email sent for Project Fuel Missions Site Development Plan for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
12/29/2020 12:00:54 PM
|
Request for Review Comments email sent for Project Fuel Missions Site Development Plan for review by DeBerry Drew on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
12/29/2020 12:00:52 PM
|
Request for Review Comments email sent for Project Fuel Missions Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
12/29/2020 12:00:46 PM
|
Request for Review Comments email sent for Project Fuel Missions Site Development Plan for review by Catherine McGarvy on behalf of EPC Health Department
|
12/29/2020 12:00:38 PM
|
Request for Review Comments email sent for Project Fuel Missions Site Development Plan for review by Sophie Kiepe on behalf of PCD Project Manager
|
12/29/2020 12:00:36 PM
|
Request for Review Comments email sent for Project Fuel Missions Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
12/29/2020 9:00:25 AM
|
Fees paid: 12/29/2020 (Receipt: 1003727)
|
12/28/2020 1:31:31 PM
|
Payment Request sent: 12/28/2020
|
12/28/2020 1:31:31 PM
|
File # Assigned: PPR2048
|
12/28/2020 1:31:25 PM
|
Submission Triaged
|
12/28/2020 1:31:16 PM
|
Project Manager Assigned: Sophie Kiepe
|
12/28/2020 8:53:31 AM
|
Submission received from Applicant
|
12/25/2020 12:27:20 PM
|
Submission request sent to Applicant
|
12/25/2020 12:26:39 PM
|
Submission Triaged
|
12/23/2020 2:07:34 PM
|
Submission received from Applicant
|
8/23/2020 1:43:58 PM
|
Submission request sent to Applicant
|
8/23/2020 1:42:24 PM
|
Project Manager Assigned: Nina Ruiz
|
8/23/2020 1:42:24 PM
|
EA Assigned: EA2080
|
8/23/2020 1:42:23 PM
|
Project Created
|