6/11/2021 5:22:58 PM
|
Project Closed
|
6/11/2021 5:22:58 PM
|
Project Approved: 6/11/2021
|
3/23/2021 7:52:53 AM
|
Project Ready for Approval requests. Review Comment period is complete.
|
3/12/2021 10:02:17 AM
|
Submission Triaged
|
3/12/2021 8:59:52 AM
|
Submission received from Applicant
|
3/12/2021 8:15:15 AM
|
Submission request sent to Applicant
|
3/2/2021 7:59:58 AM
|
Request for Review Comments returned by PCD Project Manager
|
3/2/2021 7:37:28 AM
|
Request for Review Comments returned by PCD Engineering Division
|
2/26/2021 4:08:32 PM
|
Request for Review Comments email sent for Project HCD Rezone Reconsideration for review by Ryan Howser on behalf of PCD Project Manager
|
2/26/2021 4:08:28 PM
|
Request for Review Comments email sent for Project HCD Rezone Reconsideration for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
2/26/2021 4:08:01 PM
|
Submission Triaged
|
2/26/2021 1:45:55 PM
|
Submission received from Applicant
|
2/24/2021 2:44:11 PM
|
Submission request sent to Applicant
|
2/24/2021 2:43:14 PM
|
Request for Review Comments returned by PCD Project Manager
|
2/24/2021 2:41:35 PM
|
Request for Review Comments email resent for Project HCD Rezone Reconsideration for review by Ryan Howser on behalf of PCD Project Manager
|
2/24/2021 2:18:05 PM
|
Request for Review Comments returned by PCD Engineering Division
|
2/24/2021 7:39:48 AM
|
Request for Review Comments returned by PCD Project Manager
|
2/23/2021 10:32:34 AM
|
Request for Review Comments returned by Colorado Springs Airport Advisory Commission
|
2/17/2021 5:12:11 PM
|
Request for Review Comments returned by EPC Health Department
|
2/2/2021 7:20:14 AM
|
Request for Review Comments email sent for Project HCD Rezone Reconsideration for review by Kristine Andrews on behalf of Colorado Springs Airport Advisory Commission
|
2/2/2021 7:20:12 AM
|
Request for Review Comments email sent for Project HCD Rezone Reconsideration for review by Ryan Howser on behalf of PCD Project Manager
|
2/2/2021 7:20:06 AM
|
Request for Review Comments email sent for Project HCD Rezone Reconsideration for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
2/2/2021 7:17:02 AM
|
Submission Triaged
|
1/29/2021 3:59:56 PM
|
Submission received from Applicant
|
1/26/2021 5:48:40 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
1/26/2021 7:47:45 AM
|
Submission request sent to Applicant
|
1/15/2021 8:55:31 AM
|
Request for Review Comments returned by Parks Advisory Board
|
1/15/2021 8:54:31 AM
|
Request for Review Comments returned by EPC Parks Department
|
1/12/2021 11:23:47 AM
|
Request for Review Comments returned by PCD Project Manager
|
1/12/2021 10:17:52 AM
|
Request for Review Comments email resent for Project HCD Rezone Reconsideration for review by Ryan Howser on behalf of PCD Project Manager
|
1/12/2021 7:18:33 AM
|
Request for Review Comments email sent for Project HCD Rezone Reconsideration for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
1/11/2021 6:29:41 PM
|
Request for Review Comments returned by PCD Engineering Division
|
1/7/2021 5:27:47 PM
|
Request for Review Comments returned by PCD Project Manager
|
1/7/2021 3:33:59 PM
|
Request for Review Comments returned by Colorado Springs Airport Advisory Commission
|
12/29/2020 10:37:53 AM
|
Request for Review Comments returned by Cimarron Hills Fire
|
12/21/2020 11:43:18 AM
|
Request for Review Comments returned by Cherokee Metro Dist
|
12/17/2020 10:45:08 AM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
12/15/2020 5:02:32 PM
|
Request for Review Comments email sent for Project HCD Rezone Reconsideration for review by UDS Admin Staff on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
12/15/2020 5:02:30 PM
|
Request for Review Comments email sent for Project HCD Rezone Reconsideration for review by Terry Johns on behalf of Colorado Springs SD 11
|
12/15/2020 5:02:28 PM
|
Request for Review Comments email sent for Project HCD Rezone Reconsideration for review by Meggan Herington on behalf of Colorado Springs Planning & Community Development
|
12/15/2020 5:02:26 PM
|
Request for Review Comments email sent for Project HCD Rezone Reconsideration for review by Kristine Andrews on behalf of Colorado Springs Airport Advisory Commission
|
12/15/2020 5:02:23 PM
|
Request for Review Comments email sent for Project HCD Rezone Reconsideration for review by Division Chief John McLeod on behalf of Cimarron Hills Fire
|
12/15/2020 5:02:20 PM
|
Request for Review Comments email sent for Project HCD Rezone Reconsideration for review by Jeff Munger on behalf of Cherokee Metro Dist
|
12/15/2020 5:02:16 PM
|
Request for Review Comments email sent for Project HCD Rezone Reconsideration for review by John Sweeney on behalf of Federal Aviation Administration (FAA)
|
12/15/2020 5:02:13 PM
|
Request for Review Comments email sent for Project HCD Rezone Reconsideration for review by on behalf of Parks Advisory Board
|
12/15/2020 5:02:11 PM
|
Request for Review Comments email sent for Project HCD Rezone Reconsideration for review by on behalf of EPC Parks Department
|
12/15/2020 5:02:09 PM
|
Request for Review Comments email sent for Project HCD Rezone Reconsideration for review by Catherine McGarvy on behalf of EPC Health Department
|
12/15/2020 5:02:01 PM
|
Request for Review Comments email sent for Project HCD Rezone Reconsideration for review by Ryan Howser on behalf of PCD Project Manager
|
12/15/2020 5:01:59 PM
|
Request for Review Comments email sent for Project HCD Rezone Reconsideration for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
12/15/2020 10:39:03 AM
|
Fees paid: 12/15/2020 (Receipt: 1003685)
|
10/28/2020 6:39:20 AM
|
Project Manager Assigned: Ryan Howser
|
10/28/2020 6:39:00 AM
|
Payment Request sent: 10/28/2020
|
10/28/2020 6:38:59 AM
|
File # Assigned: CS204
|
10/28/2020 6:38:50 AM
|
Submission Triaged
|
10/27/2020 4:58:46 PM
|
Submission received from Applicant
|
10/21/2020 11:52:21 AM
|
Submission request sent to Applicant
|
10/21/2020 11:47:57 AM
|
Submission Triaged
|
10/20/2020 2:53:21 PM
|
Submission received from Applicant
|
8/7/2020 4:38:30 PM
|
Submission request sent to Applicant
|
8/7/2020 4:35:45 PM
|
Project Manager Assigned: Lindsay Darden
|
8/7/2020 4:35:45 PM
|
EA Assigned: EA1894
|
8/7/2020 4:35:45 PM
|
Project Created
|