8/26/2021 9:00:21 AM
|
Project Closed
|
8/26/2021 9:00:21 AM
|
Project Cancelled: 8/26/2021
|
5/13/2021 11:33:38 AM
|
Request for Review Comments returned by PCD Engineering Division
|
5/12/2021 7:10:21 AM
|
Request for Review Comments email sent for Project Woodmen Hills Filing No. 12 for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
5/11/2021 5:29:06 PM
|
Submission Triaged
|
5/11/2021 8:09:09 AM
|
Submission received from Applicant
|
5/11/2021 7:38:23 AM
|
Submission request sent to Applicant
|
5/11/2021 7:25:34 AM
|
Submission Triaged
|
5/10/2021 3:45:41 PM
|
Submission received from Applicant
|
4/29/2021 4:43:12 PM
|
Submission request sent to Applicant
|
4/29/2021 4:16:07 PM
|
Request for Review Comments returned by PCD Engineering Division
|
4/14/2021 5:02:06 PM
|
Request for Review Comments email sent for Project Woodmen Hills Filing No. 12 for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
4/14/2021 4:51:02 PM
|
Request for Review Comments email sent for Project Woodmen Hills Filing No. 12 for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
4/2/2021 2:12:26 PM
|
Submission Triaged
|
4/2/2021 1:41:53 PM
|
Submission received from Applicant
|
4/2/2021 12:27:18 PM
|
Submission request sent to Applicant
|
4/2/2021 12:26:57 PM
|
Submission Triaged
|
4/1/2021 4:07:24 PM
|
Submission received from Applicant
|
3/30/2021 10:31:56 AM
|
Submission request sent to Applicant
|
3/24/2021 4:08:38 PM
|
Request for Review Comments returned by PCD Engineering Division
|
3/17/2021 2:51:54 PM
|
Request for Review Comments email sent for Project McLaughlin Road Plat Amendment for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
3/9/2021 4:31:05 PM
|
Submission Triaged
|
3/9/2021 2:28:30 PM
|
Submission received from Applicant
|
3/9/2021 12:07:08 PM
|
Submission request sent to Applicant
|
3/9/2021 11:21:49 AM
|
Request for Review Comments returned by PCD Engineering Division
|
3/9/2021 10:42:48 AM
|
Request for Review Comments returned by PCD Project Manager
|
3/9/2021 10:02:08 AM
|
Request for Review Comments email sent for Project McLaughlin Road Plat Amendment for review by Ryan Howser on behalf of PCD Project Manager
|
3/9/2021 10:02:02 AM
|
Request for Review Comments email sent for Project McLaughlin Road Plat Amendment for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
3/9/2021 9:52:30 AM
|
Submission Triaged
|
3/8/2021 7:57:58 AM
|
Submission received from Applicant
|
3/3/2021 2:25:55 PM
|
Submission request sent to Applicant
|
2/26/2021 10:08:34 AM
|
Submission request sent to Applicant
|
2/25/2021 3:49:49 PM
|
Request for Review Comments returned by PCD Project Manager
|
2/24/2021 7:22:05 AM
|
Request for Review Comments returned by PCD Engineering Division
|
1/26/2021 1:43:08 PM
|
Request for Review Comments email sent for Project McLaughlin Road Plat Amendment for review by Ryan Howser on behalf of PCD Project Manager
|
1/26/2021 1:43:01 PM
|
Request for Review Comments email sent for Project McLaughlin Road Plat Amendment for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
1/26/2021 11:38:03 AM
|
Submission Triaged
|
1/26/2021 7:32:48 AM
|
Submission received from Applicant
|
1/25/2021 9:09:15 AM
|
Request for Review Comments returned by County Attorney - Water
|
1/20/2021 3:59:15 PM
|
Submission request sent to Applicant
|
1/20/2021 3:56:50 PM
|
Request for Review Comments returned by PCD Project Manager
|
1/20/2021 3:53:05 PM
|
Request for Review Comments email resent for Project McLaughlin Road Plat Amendment for review by Ryan Howser on behalf of PCD Project Manager
|
1/19/2021 3:05:21 PM
|
Request for Review Comments returned by PCD Engineering Division
|
1/15/2021 8:09:08 AM
|
Request for Review Comments returned by PCD Project Manager
|
1/6/2021 1:57:33 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
12/22/2020 2:49:43 PM
|
Request for Review Comments email sent for Project McLaughlin Road Plat Amendment for review by Edi Anderson on behalf of County Attorney - Water
|
12/22/2020 2:48:52 PM
|
Submission Triaged
|
12/22/2020 2:48:02 PM
|
Submission received from Applicant
|
12/22/2020 12:10:28 PM
|
Submission request sent to Applicant
|
12/17/2020 4:03:22 PM
|
Request for Review Comments returned by County Attorney - Water
|
12/17/2020 2:51:34 PM
|
Request for Review Comments returned by EPC Environmental Services
|
12/17/2020 9:43:56 AM
|
Request for Review Comments email sent for Project McLaughlin Road Plat Amendment for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
12/17/2020 9:43:54 AM
|
Request for Review Comments email sent for Project McLaughlin Road Plat Amendment for review by Kathy Andrew on behalf of EPC Environmental Services
|
12/17/2020 9:43:52 AM
|
Request for Review Comments email sent for Project McLaughlin Road Plat Amendment for review by Edi Anderson on behalf of County Attorney - Water
|
12/17/2020 9:43:50 AM
|
Request for Review Comments email sent for Project McLaughlin Road Plat Amendment for review by Ryan Howser on behalf of PCD Project Manager
|
12/17/2020 9:43:46 AM
|
Request for Review Comments email sent for Project McLaughlin Road Plat Amendment for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
12/17/2020 9:22:04 AM
|
Submission Triaged
|
12/17/2020 8:23:29 AM
|
Submission received from Applicant
|
11/5/2020 7:39:59 AM
|
Submission request sent to Applicant
|
11/4/2020 6:07:08 PM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
11/4/2020 2:24:48 PM
|
Request for Review Comments returned by Upper Black Squirrel Creek GWMD
|
11/3/2020 4:21:59 PM
|
Request for Review Comments returned by PCD Project Manager
|
11/3/2020 4:20:42 PM
|
Request for Review Comments email resent for Project McLaughlin Road Plat Amendment for review by Ryan Howser on behalf of PCD Project Manager
|
11/3/2020 4:20:09 PM
|
Request for Review Comments returned by PCD Project Manager
|
11/3/2020 4:14:14 PM
|
Request for Review Comments email resent for Project McLaughlin Road Plat Amendment for review by Ryan Howser on behalf of PCD Project Manager
|
11/3/2020 2:49:46 PM
|
Request for Review Comments returned by PCD Engineering Division
|
11/2/2020 3:42:24 PM
|
Request for Review Comments returned by PCD Project Manager
|
11/2/2020 9:15:59 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
10/22/2020 2:15:00 PM
|
Request for Review Comments returned by Falcon Fire Protection District
|
10/21/2020 1:47:56 PM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
10/20/2020 10:54:10 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
10/19/2020 4:43:59 PM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
10/19/2020 11:43:41 AM
|
Request for Review Comments returned by EPC Parks Department
|
10/13/2020 3:27:29 PM
|
Request for Review Comments returned by EPC Environmental Services
|
10/9/2020 1:01:58 PM
|
Request for Review Comments returned by Woodmen Hills Metro
|
10/9/2020 8:50:16 AM
|
Request for Review Comments returned by County Attorney - Water
|
10/9/2020 7:49:28 AM
|
Request for Review Comments email sent for Project McLaughlin Road Plat Amendment for review by Jerry Jacobson on behalf of Woodmen Hills Metro
|
10/9/2020 7:49:25 AM
|
Request for Review Comments email sent for Project McLaughlin Road Plat Amendment for review by Administrative Assistant Cathy Hansen-Lee on behalf of Mountain View Electric Association, Inc.
|
10/9/2020 7:49:23 AM
|
Request for Review Comments email sent for Project McLaughlin Road Plat Amendment for review by Fire Chief Trent Harwig on behalf of Falcon Fire Protection District
|
10/9/2020 7:49:21 AM
|
Request for Review Comments email sent for Project McLaughlin Road Plat Amendment for review by District Manager Pamela Davison on behalf of El Paso County Conservation Dist
|
10/9/2020 7:49:19 AM
|
Request for Review Comments email sent for Project McLaughlin Road Plat Amendment for review by UDS Admin Staff on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
10/9/2020 7:49:17 AM
|
Request for Review Comments email sent for Project McLaughlin Road Plat Amendment for review by Meggan Herington on behalf of Colorado Springs Planning & Community Development
|
10/9/2020 7:49:15 AM
|
Request for Review Comments email sent for Project McLaughlin Road Plat Amendment for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
|
10/9/2020 7:49:13 AM
|
Request for Review Comments email sent for Project McLaughlin Road Plat Amendment for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
10/9/2020 7:49:10 AM
|
Request for Review Comments email sent for Project McLaughlin Road Plat Amendment for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
10/9/2020 7:49:08 AM
|
Request for Review Comments email sent for Project McLaughlin Road Plat Amendment for review by Commander John Padgett on behalf of EPC Sheriff's Department
|
10/9/2020 7:49:06 AM
|
Request for Review Comments email sent for Project McLaughlin Road Plat Amendment for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
|
10/9/2020 7:49:04 AM
|
Request for Review Comments email sent for Project McLaughlin Road Plat Amendment for review by on behalf of EPC Parks Department
|
10/9/2020 7:49:02 AM
|
Request for Review Comments email sent for Project McLaughlin Road Plat Amendment for review by Catherine McGarvy on behalf of EPC Health Department
|
10/9/2020 7:48:54 AM
|
Request for Review Comments email sent for Project McLaughlin Road Plat Amendment for review by Kathy Andrew on behalf of EPC Environmental Services
|
10/9/2020 7:48:51 AM
|
Request for Review Comments email sent for Project McLaughlin Road Plat Amendment for review by Edi Anderson on behalf of County Attorney - Water
|
10/9/2020 7:48:48 AM
|
Request for Review Comments email sent for Project McLaughlin Road Plat Amendment for review by Ryan Howser on behalf of PCD Project Manager
|
10/9/2020 7:48:45 AM
|
Request for Review Comments email sent for Project McLaughlin Road Plat Amendment for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
10/8/2020 4:20:46 PM
|
Fees paid: 10/8/2020 (Receipt: 1003369)
|
10/5/2020 4:51:41 PM
|
Payment Request sent: 10/5/2020
|
10/5/2020 4:51:41 PM
|
File # Assigned: SF2022
|
10/5/2020 4:51:32 PM
|
Submission Triaged
|
10/5/2020 4:12:03 PM
|
Submission received from Applicant
|
10/5/2020 5:55:00 AM
|
Submission request sent to Applicant
|
10/5/2020 5:54:45 AM
|
Submission Triaged
|
10/1/2020 2:27:39 PM
|
Submission received from Applicant
|
9/25/2020 2:07:38 PM
|
Submission request sent to Applicant
|
9/25/2020 2:07:17 PM
|
Submission Triaged
|
9/25/2020 10:40:21 AM
|
Submission received from Applicant
|
5/22/2020 9:48:59 AM
|
Submission request sent to Applicant
|
5/18/2020 9:26:04 AM
|
Project Manager Assigned: Ryan Howser
|
5/18/2020 9:26:04 AM
|
EA Assigned: EA2062
|
5/18/2020 9:26:04 AM
|
Project Created
|