3/12/2021 10:47:00 AM
|
Project Closed
|
3/12/2021 10:47:00 AM
|
Project Approved: 3/12/2021
|
3/3/2021 7:56:30 AM
|
Request for Review Comments returned by PCD Project Manager
|
3/2/2021 8:10:39 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
3/1/2021 5:44:59 PM
|
Request for Review Comments returned by PCD Engineering Division
|
2/23/2021 4:28:02 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
2/23/2021 4:14:54 PM
|
Request for Review Comments email sent for Project Haddock Metal Roof PPR for review by Ryan Howser on behalf of PCD Project Manager
|
2/23/2021 4:13:37 PM
|
Request for Review Comments email sent for Project Haddock Metal Roof PPR for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
2/23/2021 4:12:36 PM
|
Submission Triaged
|
2/23/2021 12:59:44 PM
|
Submission received from Applicant
|
2/19/2021 12:21:39 PM
|
Request for Review Comments email sent for Project Haddock Metal Roof PPR for review by Lori Seago on behalf of County Attorney - Development Review
|
2/19/2021 12:20:51 PM
|
Request for Review Comments email sent for Project Haddock Metal Roof PPR for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
2/19/2021 12:16:58 PM
|
Submission request sent to Applicant
|
2/19/2021 12:16:11 PM
|
Submission Triaged
|
2/19/2021 9:21:34 AM
|
Submission received from Applicant
|
2/18/2021 5:27:54 PM
|
Submission request sent to Applicant
|
2/18/2021 5:27:33 PM
|
Submission Triaged
|
2/18/2021 12:49:48 PM
|
Submission received from Applicant
|
2/11/2021 5:19:51 PM
|
Submission request sent to Applicant
|
2/11/2021 5:15:59 PM
|
Request for Review Comments returned by PCD Project Manager
|
2/11/2021 5:13:00 PM
|
Request for Review Comments email resent for Project Haddock Metal Roof PPR for review by Ryan Howser on behalf of PCD Project Manager
|
2/11/2021 2:20:58 PM
|
Request for Review Comments returned by PCD Engineering Division
|
2/10/2021 3:16:23 PM
|
Request for Review Comments returned by PCD Project Manager
|
2/10/2021 11:30:27 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
2/9/2021 3:27:04 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
1/27/2021 1:21:35 PM
|
Submission Triaged
|
1/27/2021 12:50:05 PM
|
Submission received from Applicant
|
1/26/2021 11:20:19 AM
|
Submission request sent to Applicant
|
1/20/2021 3:51:55 PM
|
Request for Review Comments email sent for Project Haddock Metal Roof PPR for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
1/20/2021 3:51:52 PM
|
Request for Review Comments email sent for Project Haddock Metal Roof PPR for review by Lori Seago on behalf of County Attorney - Development Review
|
1/20/2021 3:51:50 PM
|
Request for Review Comments email sent for Project Haddock Metal Roof PPR for review by Ryan Howser on behalf of PCD Project Manager
|
1/20/2021 3:51:46 PM
|
Request for Review Comments email sent for Project Haddock Metal Roof PPR for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
1/20/2021 3:46:40 PM
|
Submission Triaged
|
1/20/2021 2:49:13 PM
|
Submission received from Applicant
|
1/8/2021 10:12:43 AM
|
Submission request sent to Applicant
|
1/8/2021 10:11:38 AM
|
Request for Review Comments returned by PCD Project Manager
|
1/8/2021 10:08:52 AM
|
Request for Review Comments email resent for Project Haddock Metal Roof PPR for review by Ryan Howser on behalf of PCD Project Manager
|
1/7/2021 5:24:41 PM
|
Request for Review Comments returned by PCD Project Manager
|
1/7/2021 5:18:22 PM
|
Request for Review Comments email resent for Project Haddock Metal Roof PPR for review by Ryan Howser on behalf of PCD Project Manager
|
1/7/2021 2:38:08 PM
|
Request for Review Comments returned by PCD Engineering Division
|
1/6/2021 3:38:18 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
12/30/2020 1:51:22 PM
|
Request for Review Comments email sent for Project Haddock Metal Roof PPR for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
12/30/2020 1:48:59 PM
|
Request for Review Comments returned by PCD Project Manager
|
12/29/2020 12:48:52 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
12/22/2020 4:47:33 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
12/15/2020 11:58:54 AM
|
Request for Review Comments email sent for Project Haddock Metal Roof PPR for review by Lori Seago on behalf of County Attorney - Development Review
|
12/15/2020 11:50:26 AM
|
Submission Triaged
|
12/14/2020 3:36:20 PM
|
Submission received from Applicant
|
12/14/2020 1:53:59 PM
|
Submission request sent to Applicant
|
12/11/2020 4:24:11 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
12/10/2020 8:37:52 AM
|
Request for Review Comments email sent for Project Haddock Metal Roof PPR for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
12/10/2020 8:37:48 AM
|
Request for Review Comments email sent for Project Haddock Metal Roof PPR for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
12/10/2020 8:37:46 AM
|
Request for Review Comments email sent for Project Haddock Metal Roof PPR for review by Lori Seago on behalf of County Attorney - Development Review
|
12/10/2020 8:37:44 AM
|
Request for Review Comments email sent for Project Haddock Metal Roof PPR for review by Ryan Howser on behalf of PCD Project Manager
|
12/10/2020 8:37:40 AM
|
Request for Review Comments email sent for Project Haddock Metal Roof PPR for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
12/10/2020 7:42:09 AM
|
Submission Triaged
|
12/9/2020 12:29:07 PM
|
Submission received from Applicant
|
12/7/2020 11:25:34 AM
|
Project Manager Assigned: Ryan Howser
|
11/4/2020 5:24:27 PM
|
Submission request sent to Applicant
|
10/29/2020 5:47:26 AM
|
Request for Review Comments returned by Black Forest Land Use Committee
|
10/23/2020 9:29:35 AM
|
Submission request sent to Applicant
|
10/23/2020 9:19:53 AM
|
Request for Review Comments returned by PCD Project Manager
|
10/22/2020 2:45:48 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
10/22/2020 2:26:12 PM
|
Request for Review Comments returned by PCD Engineering Division
|
10/15/2020 4:06:55 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
10/14/2020 8:35:08 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
10/7/2020 3:38:19 PM
|
Request for Review Comments returned by EPC Environmental Services
|
10/5/2020 2:48:49 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
10/5/2020 7:27:50 AM
|
Request for Review Comments returned by Academy SD 20 Building Fund
|
10/1/2020 8:46:41 AM
|
Request for Review Comments email sent for Project Haddock Metal Roof PPR for review by Administrative Assistant Cathy Hansen-Lee on behalf of Mountain View Electric Association, Inc.
|
10/1/2020 8:46:39 AM
|
Request for Review Comments email sent for Project Haddock Metal Roof PPR for review by Meggan Herington on behalf of Colorado Springs Planning & Community Development
|
10/1/2020 8:46:37 AM
|
Request for Review Comments email sent for Project Haddock Metal Roof PPR for review by Terry Stokka on behalf of Black Forest Land Use Committee
|
10/1/2020 8:46:35 AM
|
Request for Review Comments email sent for Project Haddock Metal Roof PPR for review by Deputy Chief James Rebitski on behalf of Black Forest Fire Protection District
|
10/1/2020 8:46:32 AM
|
Request for Review Comments email sent for Project Haddock Metal Roof PPR for review by Plannig Consultant Donald Smith on behalf of Academy SD 20 Building Fund
|
10/1/2020 8:46:30 AM
|
Request for Review Comments email sent for Project Haddock Metal Roof PPR for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
10/1/2020 8:46:28 AM
|
Request for Review Comments email sent for Project Haddock Metal Roof PPR for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
10/1/2020 8:46:24 AM
|
Request for Review Comments email sent for Project Haddock Metal Roof PPR for review by Catherine McGarvy on behalf of EPC Health Department
|
10/1/2020 8:46:16 AM
|
Request for Review Comments email sent for Project Haddock Metal Roof PPR for review by Kathy Andrew on behalf of EPC Environmental Services
|
10/1/2020 8:46:14 AM
|
Request for Review Comments email sent for Project Haddock Metal Roof PPR for review by Lori Seago on behalf of County Attorney - Development Review
|
10/1/2020 8:46:12 AM
|
Request for Review Comments email sent for Project Haddock Metal Roof PPR for review by Rad Dickson on behalf of PCD Project Manager
|
10/1/2020 8:46:09 AM
|
Request for Review Comments email sent for Project Haddock Metal Roof PPR for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
9/29/2020 4:52:46 PM
|
Fees paid: 9/29/2020 (Receipt: 1003317)
|
9/29/2020 12:04:21 PM
|
Payment Request sent: 9/29/2020
|
9/29/2020 12:04:14 PM
|
Submission Triaged
|
9/29/2020 9:17:34 AM
|
Submission received from Applicant
|
9/28/2020 5:22:40 PM
|
Submission request sent to Applicant
|
9/28/2020 5:22:24 PM
|
Submission Triaged
|
9/28/2020 8:16:29 AM
|
Submission received from Applicant
|
9/23/2020 7:27:09 AM
|
Submission request sent to Applicant
|
9/23/2020 7:26:47 AM
|
Submission Triaged
|
9/22/2020 1:27:50 PM
|
Submission received from Applicant
|
7/28/2020 1:04:03 PM
|
File # Assigned: PPR2023
|
5/28/2020 11:48:20 AM
|
Submission request sent to Applicant
|
5/6/2020 11:26:01 AM
|
Project Manager Assigned: Rad Dickson
|
5/6/2020 11:26:01 AM
|
Project Created
|