10/23/2020 4:30:43 PM
|
Updated from Master Parcel 6132006011 to new Parcel 6132006012
|
9/29/2020 8:41:54 AM
|
Project Closed
|
9/29/2020 8:41:54 AM
|
Project Approved: 9/29/2020
|
9/17/2020 1:13:54 PM
|
Submission Triaged
|
9/17/2020 11:42:20 AM
|
Submission received from Applicant
|
9/17/2020 10:44:56 AM
|
Submission request sent to Applicant
|
9/17/2020 10:43:39 AM
|
Submission Triaged
|
9/17/2020 10:33:33 AM
|
Submission received from Applicant
|
9/17/2020 8:46:26 AM
|
Submission request sent to Applicant
|
9/11/2020 4:38:30 PM
|
Submission Triaged
|
9/9/2020 5:29:51 PM
|
Submission received from Applicant
|
7/31/2020 2:16:06 PM
|
Submission request sent to Applicant
|
7/31/2020 1:54:15 PM
|
Submission Triaged
|
7/30/2020 4:57:48 PM
|
Submission received from Applicant
|
7/21/2020 8:19:28 AM
|
Project Ready for Approval requests. Review Comment period is complete.
|
7/21/2020 8:19:03 AM
|
Submission request sent to Applicant
|
7/21/2020 8:16:09 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
7/16/2020 1:30:56 PM
|
Request for Review Comments returned by PCD Project Manager
|
7/7/2020 11:07:24 AM
|
Request for Review Comments email sent for Project 1670 Spring Valley Plat Amendment for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
7/7/2020 11:07:23 AM
|
Request for Review Comments email sent for Project 1670 Spring Valley Plat Amendment for review by Lindsay Darden on behalf of PCD Project Manager
|
7/7/2020 11:06:50 AM
|
Submission Triaged
|
7/7/2020 9:25:21 AM
|
Submission received from Applicant
|
7/7/2020 8:15:20 AM
|
Submission request sent to Applicant
|
7/6/2020 10:17:14 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
7/1/2020 1:53:32 PM
|
Request for Review Comments returned by PCD Engineering Division
|
6/30/2020 5:21:27 PM
|
Request for Review Comments returned by PCD Project Manager
|
6/22/2020 1:55:13 PM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
6/19/2020 12:20:14 PM
|
Request for Review Comments email sent for Project 1670 Spring Valley Plat Amendment for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
6/19/2020 12:20:13 PM
|
Request for Review Comments email sent for Project 1670 Spring Valley Plat Amendment for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
6/19/2020 12:20:12 PM
|
Request for Review Comments email sent for Project 1670 Spring Valley Plat Amendment for review by Lindsay Darden on behalf of PCD Project Manager
|
6/19/2020 12:20:11 PM
|
Request for Review Comments email sent for Project 1670 Spring Valley Plat Amendment for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
6/19/2020 12:19:20 PM
|
Submission Triaged
|
6/19/2020 10:58:22 AM
|
Submission received from Applicant
|
6/4/2020 7:53:13 AM
|
Submission request sent to Applicant
|
6/2/2020 11:47:46 PM
|
Request for Review Comments returned by PCD Project Manager
|
6/2/2020 3:19:25 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
5/28/2020 11:42:17 AM
|
Request for Review Comments returned by PCD Engineering Division
|
5/27/2020 11:46:07 AM
|
Request for Review Comments returned by Donald Wescott Fire Protection District
|
5/21/2020 12:33:02 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
5/21/2020 7:16:50 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
5/14/2020 10:48:08 PM
|
Request for Review Comments email sent for Project 1670 Spring Valley Plat Amendment for review by John Bender on behalf of Tri Lakes Land Use Committee
|
5/14/2020 10:48:06 PM
|
Request for Review Comments email sent for Project 1670 Spring Valley Plat Amendment for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
|
5/14/2020 10:48:05 PM
|
Request for Review Comments email sent for Project 1670 Spring Valley Plat Amendment for review by Vern Champlin on behalf of Donald Wescott Fire Protection District
|
5/14/2020 10:48:04 PM
|
Request for Review Comments email sent for Project 1670 Spring Valley Plat Amendment for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
5/14/2020 10:48:02 PM
|
Request for Review Comments email sent for Project 1670 Spring Valley Plat Amendment for review by Anthony Pastorello on behalf of Academy Water & Sanitation
|
5/14/2020 10:48:01 PM
|
Request for Review Comments email sent for Project 1670 Spring Valley Plat Amendment for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
5/14/2020 10:48:00 PM
|
Request for Review Comments email sent for Project 1670 Spring Valley Plat Amendment for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
5/14/2020 10:47:59 PM
|
Request for Review Comments email sent for Project 1670 Spring Valley Plat Amendment for review by Catherine McGarvy on behalf of EPC Health Department
|
5/14/2020 10:47:56 PM
|
Request for Review Comments email sent for Project 1670 Spring Valley Plat Amendment for review by Lindsay Darden on behalf of PCD Project Manager
|
5/14/2020 10:47:55 PM
|
Request for Review Comments email sent for Project 1670 Spring Valley Plat Amendment for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
5/14/2020 11:19:21 AM
|
Fees paid: 5/14/2020 (Receipt: 1002745)
|
5/12/2020 3:52:33 PM
|
Payment Request sent: 5/12/2020
|
5/12/2020 3:52:19 PM
|
Submission Triaged
|
5/12/2020 2:25:35 PM
|
Submission received from Applicant
|
5/11/2020 1:20:22 PM
|
File # Assigned: VR203
|
5/11/2020 10:46:19 AM
|
Submission request sent to Applicant
|
5/11/2020 10:46:09 AM
|
Submission Triaged
|
5/11/2020 10:29:18 AM
|
Submission received from Applicant
|
5/7/2020 5:07:27 PM
|
Submission request sent to Applicant
|
4/20/2020 1:54:23 PM
|
Submission request sent to Applicant
|
4/20/2020 1:42:18 PM
|
Project Manager Assigned: Lindsay Darden
|
4/20/2020 1:42:18 PM
|
EA Assigned: EA19119
|
4/20/2020 1:42:18 PM
|
Project Created
|