3/29/2022 9:23:07 AM
|
Project Closed
|
3/29/2022 9:23:07 AM
|
Project Approved: 3/29/2022
|
8/26/2021 3:51:32 PM
|
Submission request sent to Applicant
|
8/18/2021 2:11:19 PM
|
Project Ready for Approval requests. Review Comment period is complete.
|
6/18/2021 5:17:13 PM
|
Submission Triaged
|
6/18/2021 4:49:57 PM
|
Submission received from Applicant
|
6/9/2021 1:30:24 PM
|
Submission request sent to Applicant
|
6/8/2021 9:22:58 AM
|
Request for Review Comments returned by County Attorney - Water
|
5/27/2021 5:29:59 PM
|
Request for Review Comments returned by PCD Engineering Division
|
5/13/2021 2:27:09 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Edi Anderson on behalf of County Attorney - Water
|
5/13/2021 2:24:15 PM
|
Request for Review Comments returned by PCD Project Manager
|
5/13/2021 2:23:47 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Edi Anderson on behalf of County Attorney - Water
|
5/13/2021 2:23:45 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Ryan Howser on behalf of PCD Project Manager
|
5/13/2021 2:23:40 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
5/13/2021 2:21:56 PM
|
Submission Triaged
|
5/13/2021 1:18:54 PM
|
Submission received from Applicant
|
5/11/2021 7:22:06 AM
|
Submission request sent to Applicant
|
5/7/2021 4:49:46 PM
|
Submission request sent to Applicant
|
5/7/2021 4:22:26 PM
|
Request for Review Comments returned by PCD Engineering Division
|
5/6/2021 9:44:37 AM
|
Request for Review Comments returned by PCD Project Manager
|
5/6/2021 9:43:36 AM
|
Request for Review Comments email resent for Project Eagle Forest PUDSP for review by Ryan Howser on behalf of PCD Project Manager
|
5/6/2021 9:42:55 AM
|
Request for Review Comments returned by PCD Project Manager
|
5/3/2021 5:30:25 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
4/13/2021 1:42:40 PM
|
Request for Review Comments returned by EPC Environmental Services
|
4/13/2021 8:38:18 AM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
4/13/2021 8:38:15 AM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Kathy Andrew on behalf of EPC Environmental Services
|
4/13/2021 8:38:13 AM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Edi Anderson on behalf of County Attorney - Water
|
4/13/2021 8:38:11 AM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Ryan Howser on behalf of PCD Project Manager
|
4/13/2021 8:38:07 AM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
4/13/2021 8:31:09 AM
|
Submission Triaged
|
4/12/2021 6:22:41 PM
|
Submission received from Applicant
|
4/8/2021 3:25:43 PM
|
Submission request sent to Applicant
|
4/8/2021 3:25:26 PM
|
Submission Triaged
|
4/8/2021 1:10:28 PM
|
Submission received from Applicant
|
3/23/2021 3:32:38 PM
|
Submission request sent to Applicant
|
3/11/2021 2:43:05 PM
|
Request for Review Comments returned by PCD Engineering Division
|
3/4/2021 1:31:11 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
3/4/2021 1:19:39 PM
|
Submission Triaged
|
3/4/2021 12:45:00 PM
|
Submission received from Applicant
|
3/4/2021 12:37:44 PM
|
Submission request sent to Applicant
|
3/2/2021 12:18:53 PM
|
Request for Review Comments returned by EPC Environmental Services
|
2/26/2021 4:57:41 PM
|
Request for Review Comments returned by PCD Project Manager
|
2/26/2021 4:53:07 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Kathy Andrew on behalf of EPC Environmental Services
|
2/26/2021 4:42:12 PM
|
Request for Review Comments email resent for Project Eagle Forest PUDSP for review by Ryan Howser on behalf of PCD Project Manager
|
2/26/2021 4:01:52 PM
|
Request for Review Comments returned by PCD Engineering Division
|
2/26/2021 1:34:40 PM
|
Request for Review Comments returned by County Attorney - Water
|
2/26/2021 7:31:28 AM
|
Request for Review Comments returned by PCD Project Manager
|
2/19/2021 7:08:10 AM
|
Submission Triaged
|
2/18/2021 5:50:34 PM
|
Submission received from Applicant
|
2/17/2021 1:08:47 PM
|
Submission request sent to Applicant
|
2/17/2021 1:08:01 PM
|
Submission Triaged
|
1/29/2021 8:54:51 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
1/28/2021 10:51:12 AM
|
Request for Review Comments returned by EPC Environmental Services
|
1/26/2021 4:58:38 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
1/26/2021 4:58:36 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Kathy Andrew on behalf of EPC Environmental Services
|
1/26/2021 4:58:34 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Edi Anderson on behalf of County Attorney - Water
|
1/26/2021 4:58:32 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Ryan Howser on behalf of PCD Project Manager
|
1/26/2021 4:58:28 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
1/26/2021 4:57:20 PM
|
Submission Triaged
|
1/26/2021 4:50:23 PM
|
Submission received from Applicant
|
1/26/2021 4:24:45 PM
|
Submission request sent to Applicant
|
1/26/2021 4:23:45 PM
|
Submission Triaged
|
1/26/2021 1:42:16 PM
|
Submission received from Applicant
|
12/27/2020 2:03:15 PM
|
Project Manager Assigned: Ryan Howser
|
10/7/2020 11:09:42 PM
|
Submission request sent to Applicant
|
10/7/2020 11:07:15 PM
|
Request for Review Comments returned by PCD Project Manager
|
10/7/2020 5:37:50 PM
|
Request for Review Comments returned by EPC Health Department
|
10/7/2020 5:22:56 PM
|
Request for Review Comments returned by PCD Engineering Division
|
10/7/2020 4:35:24 PM
|
Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
|
10/7/2020 10:23:18 AM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
10/6/2020 8:29:44 AM
|
Request for Review Comments returned by County Attorney - Development Review
|
10/1/2020 5:46:17 PM
|
Request for Review Comments returned by Colorado Geological Survey
|
10/1/2020 2:19:31 PM
|
Request for Review Comments returned by Colorado Department of Public Health and Environment
|
9/30/2020 2:49:02 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
9/30/2020 9:07:44 AM
|
Request for Review Comments returned by Parks Advisory Board
|
9/30/2020 9:04:51 AM
|
Request for Review Comments returned by EPC Parks Department
|
9/28/2020 12:56:51 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
9/24/2020 1:12:51 PM
|
Request for Review Comments returned by EPC Environmental Services
|
9/22/2020 7:51:31 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
9/21/2020 2:52:57 PM
|
Request for Review Comments returned by Colorado Parks and Wildlife
|
9/16/2020 8:11:25 AM
|
Request for Review Comments returned by Colorado State Forest Service
|
9/15/2020 3:37:09 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
9/14/2020 7:26:57 AM
|
Request for Review Comments returned by Academy SD 20 Building Fund
|
9/10/2020 3:45:39 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Sean Hackett on behalf of Colorado Department of Public Health and Environment
|
9/10/2020 3:44:03 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Sean Hackett on behalf of Colorado Department of Public Health and Environment
|
9/10/2020 3:16:16 PM
|
Request for Review Comments returned by County Attorney - Water
|
9/10/2020 2:47:10 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
|
9/10/2020 2:47:09 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
9/10/2020 2:47:08 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Cheryl Pixley on behalf of Black Forest Trails Association
|
9/10/2020 2:47:06 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Terry Stokka on behalf of Black Forest Land Use Committee
|
9/10/2020 2:47:06 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by P.J. Langmaid on behalf of Black Forest Fire Protection District
|
9/10/2020 2:47:05 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Plannig Consultant Donald Smith on behalf of Academy SD 20 Building Fund
|
9/10/2020 2:47:04 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
9/10/2020 2:47:03 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
9/10/2020 2:47:02 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Mr. Andy Schlosberg on behalf of Colorado State Forest Service
|
9/10/2020 2:47:01 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Energy and Land Use Specialist Karen Voltura on behalf of Colorado Parks and Wildlife
|
9/10/2020 2:47:00 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
9/10/2020 2:46:59 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
9/10/2020 2:46:58 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Permits Manager Valerie Sword on behalf of Colorado Department of Transportation - Pueblo Office
|
9/10/2020 2:46:57 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Sean Hackett on behalf of Colorado Department of Public Health and Environment
|
9/10/2020 2:46:56 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by on behalf of Parks Advisory Board
|
9/10/2020 2:46:55 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
9/10/2020 2:46:54 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Commander John Padgett on behalf of EPC Sheriff's Department
|
9/10/2020 2:46:53 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
|
9/10/2020 2:46:52 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by on behalf of EPC Parks Department
|
9/10/2020 2:46:50 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by on behalf of EPC Health Department
|
9/10/2020 2:46:47 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Kathy Andrew on behalf of EPC Environmental Services
|
9/10/2020 2:46:46 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Edi Anderson on behalf of County Attorney - Water
|
9/10/2020 2:46:45 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Lori Seago on behalf of County Attorney - Development Review
|
9/10/2020 2:46:44 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Lindsay Darden on behalf of PCD Project Manager
|
9/10/2020 2:46:43 PM
|
Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
9/8/2020 11:29:46 AM
|
Fees paid: 9/8/2020 (Receipt: 1003208)
|
8/24/2020 6:01:30 AM
|
Payment Request sent: 8/24/2020
|
8/24/2020 6:01:30 AM
|
File # Assigned: PUDSP206
|
8/24/2020 6:01:26 AM
|
Submission Triaged
|
8/21/2020 5:26:12 PM
|
Submission received from Applicant
|
8/6/2020 11:07:53 AM
|
Submission request sent to Applicant
|
8/4/2020 4:53:51 PM
|
Submission request sent to Applicant
|
8/4/2020 6:32:41 AM
|
Project Manager Assigned: Lindsay Darden
|
8/4/2020 6:29:56 AM
|
Submission request sent to Applicant
|
8/4/2020 6:29:24 AM
|
Submission Triaged
|
8/3/2020 2:33:18 PM
|
Submission received from Applicant
|
7/14/2020 4:28:19 PM
|
Submission request sent to Applicant
|
3/4/2020 7:29:21 AM
|
Submission request sent to Applicant
|
2/3/2020 9:22:39 AM
|
Submission request sent to Applicant
|
2/3/2020 8:59:10 AM
|
Submission request sent to Applicant
|
2/3/2020 7:48:30 AM
|
Project Manager Assigned: Gabe Sevigny
|
2/3/2020 7:48:30 AM
|
EA Assigned: EA19208
|
2/3/2020 7:48:30 AM
|
Project Created
|