Project Details

Search


File Number
PUDSP206
Project Name
Eagle Forest PUDSP
Description
A request for an amendment to the PUD and a preliminary plan
Location
7360 Shoup Road
Parcels
5208000071 5208000071
Applicant
Eagle Forest Development LLC
Peter Patten ( ppatten@pattenassociates.com )
(970) 846-9111
Peter Patten ( ppatten@pattenassociates.com )
(970) 846-9111
EA Number
EA19208
File Prefix
PUDSP - Combined PUD/Preliminary Plan
Year
2020
Project Manager
Ryan Howser
Status
Closed
Created
2/3/2020 7:48:16 AM

View: Review Comments



Additional Documents (11)

Link Document Comment
View Mailing Packet: Notice, Map and Labels
View Posting Photos
View PC Staff Report with Attachments
View BoCC Staff Report
View PC Approval Letter
View BoCC Approval Letter
View Shoppers Press Confirmation
View BoCC Resolution 21-293
View PC Resolution
View Recorded PUD
View Citizen Comments Please also see applicants letter of intent for history on project


Review Documents (40)

Link Document Date
View Adjacent Property Owner Notification (Includes letter and certified mailing receipts) 1/26/2021 1:39:54 PM
View Application/Petition Form 8/3/2020 2:32:17 PM
View Legal Description (MS WORD Version required) 8/3/2020 2:32:22 PM
View Letter of Intent 5/13/2021 1:18:21 PM
View OWTS Report 4/12/2021 6:19:33 PM
View PUD Development Plan - can include phasing if proposed 6/18/2021 4:49:10 PM
View Title Commitment (Current within 30 days of submittal) 2/18/2021 5:49:53 PM
View Vicinity/Location Map 8/3/2020 2:32:28 PM
View Additional Exhibits 8/3/2020 2:32:15 PM
View Colorado Geological Survey Receipt 8/3/2020 2:32:17 PM
View Deviation Request #2 2/19/2021 7:10:16 AM
View Mineral Rights Certification 1/26/2021 1:39:55 PM
View Zoning Map 8/21/2020 5:26:03 PM
View Deviation Request 4/12/2021 6:19:32 PM
View Electric Provider Commitment Letter 8/3/2020 2:32:19 PM
View Fire Commitment Letter 8/3/2020 2:32:19 PM
View Natural Gas Commitment Letter 8/3/2020 2:32:24 PM
View Drainage Report - Preliminary 5/13/2021 1:18:23 PM
View Fire Protection Report 8/3/2020 2:32:20 PM
View Natural Features Report 8/3/2020 2:32:24 PM
View Noxious Weed Management Plan 1/26/2021 1:39:56 PM
View Soils & Geology Report 8/21/2020 5:20:30 PM
View Wildland Fire & Hazard Mitigation Plan 1/26/2021 1:39:58 PM
View Colorado Ground Water Determination of Water Rights (signed) 8/3/2020 2:32:17 PM
View Signed court decrees, including augmentation plans 8/3/2020 2:32:27 PM
View Water Quality Report 8/3/2020 2:32:29 PM
View Water Resources Report 8/3/2020 2:32:30 PM
View Water Supply Information Summary 4/8/2021 1:09:51 PM
View Well Permits (if water source is wells) 8/3/2020 2:32:31 PM
View Declaration of Covenants (MS Word version required) 1/26/2021 1:39:54 PM
View HOA articles of incorporation 8/3/2020 2:32:21 PM
View HOA bylaws (MS Word version required) 8/3/2020 2:32:22 PM
View Secretary of State Certification 8/3/2020 2:32:26 PM
View Confirmation Deed Public Trustees Foreclosure Sale November 2010 4/8/2021 1:09:53 PM
View Confirmation Deed Public Trustees Foreclosure Sale November 2010 5/13/2021 1:18:27 PM
View Deed of Trust First National Bank and Edward Edwards Nov 30 2007 5/13/2021 1:18:26 PM
View Deed of Trust First National Bank and Edward Edwards Nov 30 2007 4/8/2021 1:09:52 PM
View Quit Claim Deed First National Bank to Eagle Forest Development 5/27/2021 11:01:07 AM
View Traffic Memo 3/4/2021 12:44:31 PM
View Water Rights Memorandum 8/3/2020 2:32:35 PM



Events (129)

Date Comment
3/29/2022 9:23:07 AM Project Closed
3/29/2022 9:23:07 AM Project Approved: 3/29/2022
8/26/2021 3:51:32 PM Submission request sent to Applicant
8/18/2021 2:11:19 PM Project Ready for Approval requests. Review Comment period is complete.
6/18/2021 5:17:13 PM Submission Triaged
6/18/2021 4:49:57 PM Submission received from Applicant
6/9/2021 1:30:24 PM Submission request sent to Applicant
6/8/2021 9:22:58 AM Request for Review Comments returned by County Attorney - Water
5/27/2021 5:29:59 PM Request for Review Comments returned by PCD Engineering Division
5/13/2021 2:27:09 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Edi Anderson on behalf of County Attorney - Water
5/13/2021 2:24:15 PM Request for Review Comments returned by PCD Project Manager
5/13/2021 2:23:47 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Edi Anderson on behalf of County Attorney - Water
5/13/2021 2:23:45 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Ryan Howser on behalf of PCD Project Manager
5/13/2021 2:23:40 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
5/13/2021 2:21:56 PM Submission Triaged
5/13/2021 1:18:54 PM Submission received from Applicant
5/11/2021 7:22:06 AM Submission request sent to Applicant
5/7/2021 4:49:46 PM Submission request sent to Applicant
5/7/2021 4:22:26 PM Request for Review Comments returned by PCD Engineering Division
5/6/2021 9:44:37 AM Request for Review Comments returned by PCD Project Manager
5/6/2021 9:43:36 AM Request for Review Comments email resent for Project Eagle Forest PUDSP for review by Ryan Howser on behalf of PCD Project Manager
5/6/2021 9:42:55 AM Request for Review Comments returned by PCD Project Manager
5/3/2021 5:30:25 PM Request for Review Comments returned by Pikes Peak Regional Building Department
4/13/2021 1:42:40 PM Request for Review Comments returned by EPC Environmental Services
4/13/2021 8:38:18 AM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
4/13/2021 8:38:15 AM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Kathy Andrew on behalf of EPC Environmental Services
4/13/2021 8:38:13 AM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Edi Anderson on behalf of County Attorney - Water
4/13/2021 8:38:11 AM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Ryan Howser on behalf of PCD Project Manager
4/13/2021 8:38:07 AM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
4/13/2021 8:31:09 AM Submission Triaged
4/12/2021 6:22:41 PM Submission received from Applicant
4/8/2021 3:25:43 PM Submission request sent to Applicant
4/8/2021 3:25:26 PM Submission Triaged
4/8/2021 1:10:28 PM Submission received from Applicant
3/23/2021 3:32:38 PM Submission request sent to Applicant
3/11/2021 2:43:05 PM Request for Review Comments returned by PCD Engineering Division
3/4/2021 1:31:11 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
3/4/2021 1:19:39 PM Submission Triaged
3/4/2021 12:45:00 PM Submission received from Applicant
3/4/2021 12:37:44 PM Submission request sent to Applicant
3/2/2021 12:18:53 PM Request for Review Comments returned by EPC Environmental Services
2/26/2021 4:57:41 PM Request for Review Comments returned by PCD Project Manager
2/26/2021 4:53:07 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Kathy Andrew on behalf of EPC Environmental Services
2/26/2021 4:42:12 PM Request for Review Comments email resent for Project Eagle Forest PUDSP for review by Ryan Howser on behalf of PCD Project Manager
2/26/2021 4:01:52 PM Request for Review Comments returned by PCD Engineering Division
2/26/2021 1:34:40 PM Request for Review Comments returned by County Attorney - Water
2/26/2021 7:31:28 AM Request for Review Comments returned by PCD Project Manager
2/19/2021 7:08:10 AM Submission Triaged
2/18/2021 5:50:34 PM Submission received from Applicant
2/17/2021 1:08:47 PM Submission request sent to Applicant
2/17/2021 1:08:01 PM Submission Triaged
1/29/2021 8:54:51 AM Request for Review Comments returned by 911 Authority - El Paso/Teller County
1/28/2021 10:51:12 AM Request for Review Comments returned by EPC Environmental Services
1/26/2021 4:58:38 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
1/26/2021 4:58:36 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Kathy Andrew on behalf of EPC Environmental Services
1/26/2021 4:58:34 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Edi Anderson on behalf of County Attorney - Water
1/26/2021 4:58:32 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Ryan Howser on behalf of PCD Project Manager
1/26/2021 4:58:28 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
1/26/2021 4:57:20 PM Submission Triaged
1/26/2021 4:50:23 PM Submission received from Applicant
1/26/2021 4:24:45 PM Submission request sent to Applicant
1/26/2021 4:23:45 PM Submission Triaged
1/26/2021 1:42:16 PM Submission received from Applicant
12/27/2020 2:03:15 PM Project Manager Assigned: Ryan Howser
10/7/2020 11:09:42 PM Submission request sent to Applicant
10/7/2020 11:07:15 PM Request for Review Comments returned by PCD Project Manager
10/7/2020 5:37:50 PM Request for Review Comments returned by EPC Health Department
10/7/2020 5:22:56 PM Request for Review Comments returned by PCD Engineering Division
10/7/2020 4:35:24 PM Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
10/7/2020 10:23:18 AM Request for Review Comments returned by Colorado Division of Water Resources
10/6/2020 8:29:44 AM Request for Review Comments returned by County Attorney - Development Review
10/1/2020 5:46:17 PM Request for Review Comments returned by Colorado Geological Survey
10/1/2020 2:19:31 PM Request for Review Comments returned by Colorado Department of Public Health and Environment
9/30/2020 2:49:02 PM Request for Review Comments returned by Pikes Peak Regional Building Department
9/30/2020 9:07:44 AM Request for Review Comments returned by Parks Advisory Board
9/30/2020 9:04:51 AM Request for Review Comments returned by EPC Parks Department
9/28/2020 12:56:51 PM Request for Review Comments returned by EPC Stormwater Review
9/24/2020 1:12:51 PM Request for Review Comments returned by EPC Environmental Services
9/22/2020 7:51:31 AM Request for Review Comments returned by 911 Authority - El Paso/Teller County
9/21/2020 2:52:57 PM Request for Review Comments returned by Colorado Parks and Wildlife
9/16/2020 8:11:25 AM Request for Review Comments returned by Colorado State Forest Service
9/15/2020 3:37:09 PM Request for Review Comments returned by Mountain View Electric Association, Inc.
9/14/2020 7:26:57 AM Request for Review Comments returned by Academy SD 20 Building Fund
9/10/2020 3:45:39 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Sean Hackett on behalf of Colorado Department of Public Health and Environment
9/10/2020 3:44:03 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Sean Hackett on behalf of Colorado Department of Public Health and Environment
9/10/2020 3:16:16 PM Request for Review Comments returned by County Attorney - Water
9/10/2020 2:47:10 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
9/10/2020 2:47:09 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Joe Valdez on behalf of Black Hills Energy-Aquila
9/10/2020 2:47:08 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Cheryl Pixley on behalf of Black Forest Trails Association
9/10/2020 2:47:06 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Terry Stokka on behalf of Black Forest Land Use Committee
9/10/2020 2:47:06 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by P.J. Langmaid on behalf of Black Forest Fire Protection District
9/10/2020 2:47:05 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Plannig Consultant Donald Smith on behalf of Academy SD 20 Building Fund
9/10/2020 2:47:04 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
9/10/2020 2:47:03 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
9/10/2020 2:47:02 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Mr. Andy Schlosberg on behalf of Colorado State Forest Service
9/10/2020 2:47:01 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Energy and Land Use Specialist Karen Voltura on behalf of Colorado Parks and Wildlife
9/10/2020 2:47:00 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Colorado Geological Survey on behalf of Colorado Geological Survey
9/10/2020 2:46:59 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Joanna Williams on behalf of Colorado Division of Water Resources
9/10/2020 2:46:58 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Permits Manager Valerie Sword on behalf of Colorado Department of Transportation - Pueblo Office
9/10/2020 2:46:57 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Sean Hackett on behalf of Colorado Department of Public Health and Environment
9/10/2020 2:46:56 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by on behalf of Parks Advisory Board
9/10/2020 2:46:55 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
9/10/2020 2:46:54 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Commander John Padgett on behalf of EPC Sheriff's Department
9/10/2020 2:46:53 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
9/10/2020 2:46:52 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by on behalf of EPC Parks Department
9/10/2020 2:46:50 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by on behalf of EPC Health Department
9/10/2020 2:46:47 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Kathy Andrew on behalf of EPC Environmental Services
9/10/2020 2:46:46 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Edi Anderson on behalf of County Attorney - Water
9/10/2020 2:46:45 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Lori Seago on behalf of County Attorney - Development Review
9/10/2020 2:46:44 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Lindsay Darden on behalf of PCD Project Manager
9/10/2020 2:46:43 PM Request for Review Comments email sent for Project Eagle Forest PUDSP for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
9/8/2020 11:29:46 AM Fees paid: 9/8/2020 (Receipt: 1003208)
8/24/2020 6:01:30 AM Payment Request sent: 8/24/2020
8/24/2020 6:01:30 AM File # Assigned: PUDSP206
8/24/2020 6:01:26 AM Submission Triaged
8/21/2020 5:26:12 PM Submission received from Applicant
8/6/2020 11:07:53 AM Submission request sent to Applicant
8/4/2020 4:53:51 PM Submission request sent to Applicant
8/4/2020 6:32:41 AM Project Manager Assigned: Lindsay Darden
8/4/2020 6:29:56 AM Submission request sent to Applicant
8/4/2020 6:29:24 AM Submission Triaged
8/3/2020 2:33:18 PM Submission received from Applicant
7/14/2020 4:28:19 PM Submission request sent to Applicant
3/4/2020 7:29:21 AM Submission request sent to Applicant
2/3/2020 9:22:39 AM Submission request sent to Applicant
2/3/2020 8:59:10 AM Submission request sent to Applicant
2/3/2020 7:48:30 AM Project Manager Assigned: Gabe Sevigny
2/3/2020 7:48:30 AM EA Assigned: EA19208
2/3/2020 7:48:30 AM Project Created