6/25/2020 10:58:30 AM
|
Project Closed
|
6/25/2020 10:58:30 AM
|
Project Approved: 6/25/2020
|
6/19/2020 9:20:55 AM
|
Project Ready for Approval requests. Review Comment period is complete.
|
6/19/2020 7:55:53 AM
|
Request for Review Comments returned by PCD Project Manager
|
6/4/2020 1:23:18 PM
|
Request for Review Comments email sent for Project Boy Scout Recreation Camp for review by Rad Dickson on behalf of PCD Project Manager
|
6/4/2020 1:21:57 PM
|
Submission Triaged
|
6/3/2020 6:01:57 PM
|
Submission received from Applicant
|
5/27/2020 3:10:55 PM
|
Submission request sent to Applicant
|
5/27/2020 3:10:41 PM
|
Request for Review Comments returned by PCD Project Manager
|
5/27/2020 3:09:23 PM
|
Request for Review Comments email sent for Project Boy Scout Recreation Camp for review by District Conservationist Deric Clemons on behalf of El Paso County Conservation Dist
|
5/27/2020 3:09:22 PM
|
Request for Review Comments email sent for Project Boy Scout Recreation Camp for review by Jennifer DeWoody on behalf of US Forest Service, Pikes Peak Ranger District
|
5/27/2020 3:09:21 PM
|
Request for Review Comments email sent for Project Boy Scout Recreation Camp for review by Rad Dickson on behalf of PCD Project Manager
|
5/20/2020 10:32:12 AM
|
Request for Review Comments returned by EPC Health Department
|
5/19/2020 10:01:31 AM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
5/18/2020 9:17:47 AM
|
Request for Review Comments returned by PCD Project Manager
|
5/14/2020 9:08:34 PM
|
Request for Review Comments returned by PCD Engineering Division
|
5/13/2020 9:09:20 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
5/8/2020 12:31:05 PM
|
Request for Review Comments returned by EPC Environmental Services
|
5/7/2020 7:17:24 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
5/6/2020 7:26:15 PM
|
Request for Review Comments email sent for Project Boy Scout Recreation Camp for review by UDS Admin Staff on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
5/6/2020 7:26:15 PM
|
Request for Review Comments email sent for Project Boy Scout Recreation Camp for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
5/6/2020 7:26:13 PM
|
Request for Review Comments email sent for Project Boy Scout Recreation Camp for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
5/6/2020 7:26:11 PM
|
Request for Review Comments email sent for Project Boy Scout Recreation Camp for review by on behalf of EPC Health Department
|
5/6/2020 7:26:08 PM
|
Request for Review Comments email sent for Project Boy Scout Recreation Camp for review by Kathy Andrew on behalf of EPC Environmental Services
|
5/6/2020 7:26:07 PM
|
Request for Review Comments email sent for Project Boy Scout Recreation Camp for review by Rad Dickson on behalf of PCD Project Manager
|
5/6/2020 7:26:06 PM
|
Request for Review Comments email sent for Project Boy Scout Recreation Camp for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
5/6/2020 7:24:24 PM
|
Submission Triaged
|
5/5/2020 11:45:05 AM
|
Submission received from Applicant
|
5/2/2020 11:45:54 AM
|
Request for Review Comments returned by EPC Health Department
|
4/27/2020 4:07:40 PM
|
Submission request sent to Applicant
|
4/27/2020 4:07:09 PM
|
Request for Review Comments returned by PCD Project Manager
|
4/23/2020 9:35:23 PM
|
Request for Review Comments returned by PCD Engineering Division
|
4/20/2020 7:39:48 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
4/17/2020 2:41:01 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
4/16/2020 8:30:44 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
4/6/2020 8:25:29 PM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
3/31/2020 3:32:05 PM
|
Request for Review Comments email sent for Project Boy Scout Recreation Camp for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
3/31/2020 11:53:55 AM
|
Request for Review Comments returned by EPC Environmental Services
|
3/30/2020 11:21:23 AM
|
Request for Review Comments email sent for Project Boy Scout Recreation Camp for review by District Conservationist Deric Clemons on behalf of El Paso County Conservation Dist
|
3/30/2020 11:21:22 AM
|
Request for Review Comments email sent for Project Boy Scout Recreation Camp for review by UDS Admin Staff on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
3/30/2020 11:21:22 AM
|
Request for Review Comments email sent for Project Boy Scout Recreation Camp for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
3/30/2020 11:21:21 AM
|
Request for Review Comments email sent for Project Boy Scout Recreation Camp for review by Jennifer DeWoody on behalf of US Forest Service, Pikes Peak Ranger District
|
3/30/2020 11:21:20 AM
|
Request for Review Comments email sent for Project Boy Scout Recreation Camp for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
3/30/2020 11:21:17 AM
|
Request for Review Comments email sent for Project Boy Scout Recreation Camp for review by on behalf of EPC Health Department
|
3/30/2020 11:21:16 AM
|
Request for Review Comments email sent for Project Boy Scout Recreation Camp for review by Kathy Andrew on behalf of EPC Environmental Services
|
3/30/2020 11:21:16 AM
|
Request for Review Comments email sent for Project Boy Scout Recreation Camp for review by Mindy Madden on behalf of EPC Code Enforcement
|
3/30/2020 11:21:15 AM
|
Request for Review Comments email sent for Project Boy Scout Recreation Camp for review by Rad Dickson on behalf of PCD Project Manager
|
3/30/2020 11:21:14 AM
|
Request for Review Comments email sent for Project Boy Scout Recreation Camp for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
3/27/2020 1:24:28 PM
|
Submission Triaged
|
3/27/2020 1:04:41 PM
|
Fees paid: 3/27/2020 (Receipt: 1002569)
|
3/27/2020 11:44:35 AM
|
Payment Request sent: 3/27/2020
|
3/27/2020 11:44:25 AM
|
Payment Request canceled: 3/27/2020
|
3/26/2020 11:08:02 AM
|
Submission received from Applicant
|
3/26/2020 10:57:51 AM
|
Submission request sent to Applicant
|
3/26/2020 10:56:49 AM
|
Submission request sent to Applicant
|
3/25/2020 4:29:34 PM
|
Payment Request sent: 3/25/2020
|
3/25/2020 4:29:34 PM
|
File # Assigned: AL209
|
3/25/2020 4:29:31 PM
|
Submission Triaged
|
3/25/2020 2:36:11 PM
|
Submission received from Applicant
|
2/19/2020 9:56:21 AM
|
Submission request sent to Applicant
|
2/19/2020 9:56:08 AM
|
Submission Triaged
|
2/19/2020 9:36:07 AM
|
Submission received from Applicant
|
1/27/2020 9:27:44 AM
|
Submission request sent to Applicant
|
1/23/2020 3:36:43 PM
|
Project Manager Assigned: Rad Dickson
|
1/23/2020 3:36:43 PM
|
Project Created
|