9/18/2020 11:46:55 AM
|
Project Closed
|
9/18/2020 11:46:55 AM
|
Project Approved: 9/18/2020
|
6/17/2020 8:07:38 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
6/9/2020 9:10:04 AM
|
Request for Review Comments returned by PCD Project Manager
|
6/2/2020 11:29:23 AM
|
Request for Review Comments email sent for Project 8884 Towner, No Build for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
6/2/2020 11:29:22 AM
|
Request for Review Comments email sent for Project 8884 Towner, No Build for review by Ryan Howser on behalf of PCD Project Manager
|
6/2/2020 11:19:22 AM
|
Submission Triaged
|
6/2/2020 10:29:20 AM
|
Submission received from Applicant
|
5/27/2020 2:48:53 PM
|
Submission request sent to Applicant
|
5/27/2020 2:48:38 PM
|
Submission Triaged
|
5/27/2020 10:21:32 AM
|
Submission received from Applicant
|
5/21/2020 11:45:26 AM
|
Submission request sent to Applicant
|
5/21/2020 11:44:30 AM
|
Request for Review Comments returned by PCD Project Manager
|
5/20/2020 4:22:51 PM
|
Request for Review Comments returned by PCD Engineering Division
|
5/19/2020 11:35:00 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
5/6/2020 10:32:09 AM
|
Request for Review Comments email sent for Project 8884 Towner, No Build for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
5/6/2020 10:32:08 AM
|
Request for Review Comments email sent for Project 8884 Towner, No Build for review by Ryan Howser on behalf of PCD Project Manager
|
5/6/2020 10:32:05 AM
|
Request for Review Comments email sent for Project 8884 Towner, No Build for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
5/6/2020 10:27:55 AM
|
Submission Triaged
|
5/5/2020 4:24:44 PM
|
Submission received from Applicant
|
4/23/2020 1:04:13 PM
|
Request for Review Comments returned by EPC Health Department
|
4/17/2020 9:10:12 AM
|
Submission request sent to Applicant
|
4/16/2020 9:50:01 AM
|
Request for Review Comments returned by PCD Project Manager
|
4/15/2020 2:27:47 PM
|
Request for Review Comments returned by PCD Engineering Division
|
4/14/2020 3:55:05 PM
|
Request for Review Comments email sent for Project 8884 Towner, No Build for review by Ryan Howser on behalf of PCD Project Manager
|
4/14/2020 3:54:27 PM
|
Request for Review Comments email sent for Project 8884 Towner, No Build for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
4/13/2020 11:38:54 AM
|
Request for Review Comments returned by Falcon Fire Protection District
|
4/13/2020 8:58:22 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
4/2/2020 1:09:17 PM
|
Request for Review Comments returned by Upper Black Squirrel Creek GWMD
|
3/30/2020 2:56:29 PM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
3/26/2020 1:15:04 PM
|
Request for Review Comments returned by EPC Environmental Services
|
3/26/2020 9:40:55 AM
|
Request for Review Comments returned by Colorado Geological Survey
|
3/25/2020 3:08:43 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
3/24/2020 11:58:42 AM
|
Request for Review Comments email sent for Project 8884 Towner, No Build for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
|
3/24/2020 11:58:41 AM
|
Request for Review Comments email sent for Project 8884 Towner, No Build for review by Fire Chief Trent Harwig on behalf of Falcon Fire Protection District
|
3/24/2020 11:58:40 AM
|
Request for Review Comments email sent for Project 8884 Towner, No Build for review by District Conservationist Deric Clemons on behalf of El Paso County Conservation Dist
|
3/24/2020 11:58:38 AM
|
Request for Review Comments email sent for Project 8884 Towner, No Build for review by UDS Admin Staff on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
3/24/2020 11:58:37 AM
|
Request for Review Comments email sent for Project 8884 Towner, No Build for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
|
3/24/2020 11:58:36 AM
|
Request for Review Comments email sent for Project 8884 Towner, No Build for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
3/24/2020 11:58:35 AM
|
Request for Review Comments email sent for Project 8884 Towner, No Build for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
3/24/2020 11:58:34 AM
|
Request for Review Comments email sent for Project 8884 Towner, No Build for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
|
3/24/2020 11:58:32 AM
|
Request for Review Comments email sent for Project 8884 Towner, No Build for review by on behalf of EPC Health Department
|
3/24/2020 11:58:31 AM
|
Request for Review Comments email sent for Project 8884 Towner, No Build for review by Kathy Andrew on behalf of EPC Environmental Services
|
3/24/2020 11:58:30 AM
|
Request for Review Comments email sent for Project 8884 Towner, No Build for review by Ryan Howser on behalf of PCD Project Manager
|
3/24/2020 11:58:29 AM
|
Request for Review Comments email sent for Project 8884 Towner, No Build for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
3/24/2020 9:15:11 AM
|
Project Manager Assigned: Ryan Howser
|
3/24/2020 9:10:55 AM
|
Fees paid: 3/24/2020 (Receipt: 1002542)
|
3/24/2020 9:04:46 AM
|
Payment Request sent: 3/24/2020
|
3/24/2020 9:04:46 AM
|
File # Assigned: VR201
|
3/24/2020 9:04:44 AM
|
Submission Triaged
|
3/24/2020 9:02:50 AM
|
Submission received from Applicant
|
1/28/2020 8:49:43 AM
|
Submission request sent to Applicant
|
1/28/2020 8:49:19 AM
|
Submission Triaged
|
1/24/2020 11:27:02 AM
|
Submission received from Applicant
|
1/23/2020 10:42:52 AM
|
Submission request sent to Applicant
|
1/23/2020 10:41:43 AM
|
Submission request canceled
|
1/23/2020 10:41:09 AM
|
Submission request sent to Applicant
|
1/23/2020 10:41:01 AM
|
Submission Triaged
|
1/22/2020 3:39:49 PM
|
Submission received from Applicant
|
8/15/2019 2:30:57 PM
|
Submission request sent to Applicant
|
8/15/2019 2:28:42 PM
|
Project Manager Assigned: Nina Ruiz
|
8/15/2019 2:21:31 PM
|
EA Assigned: EA19110
|
8/15/2019 2:21:31 PM
|
Project Created
|