10/31/2019 4:49:15 PM
|
Project Closed
|
10/31/2019 4:49:15 PM
|
Project Approved: 10/31/2019
|
10/17/2019 7:58:30 AM
|
Project Manager Assigned: Gabe Sevigny
|
10/16/2019 11:59:37 AM
|
Request for Review Comments returned by PCD Project Manager
|
9/29/2019 7:44:34 PM
|
Request for Review Comments email sent for Project 645 Cimarron Admin Relief for review by Lindsay Darden on behalf of PCD Project Manager
|
9/29/2019 7:44:12 PM
|
Submission Triaged
|
9/25/2019 4:10:48 PM
|
Submission received from Applicant
|
9/23/2019 2:47:39 PM
|
Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
|
9/23/2019 12:03:10 PM
|
Submission request sent to Applicant
|
9/23/2019 12:00:27 PM
|
Request for Review Comments returned by PCD Project Manager
|
9/23/2019 11:52:42 AM
|
Request for Review Comments email resent for Project 645 Cimarron Admin Relief for review by Lindsay Darden on behalf of PCD Project Manager
|
9/23/2019 11:48:04 AM
|
Request for Review Comments returned by PCD Project Manager
|
9/19/2019 10:07:17 AM
|
Request for Review Comments returned by PCD Engineering Division
|
9/9/2019 3:06:26 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
9/6/2019 8:46:56 AM
|
Request for Review Comments email sent for Project 645 Cimarron Admin Relief for review by Jamey Bumgarner on behalf of Tri-Lakes-Monument Fire Protection District
|
9/6/2019 8:46:55 AM
|
Request for Review Comments email sent for Project 645 Cimarron Admin Relief for review by John Bender on behalf of Tri Lakes Land Use Committee
|
9/6/2019 8:46:54 AM
|
Request for Review Comments email sent for Project 645 Cimarron Admin Relief for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
|
9/6/2019 8:46:53 AM
|
Request for Review Comments email sent for Project 645 Cimarron Admin Relief for review by Jennifer Jones on behalf of Monument
|
9/6/2019 8:46:52 AM
|
Request for Review Comments email sent for Project 645 Cimarron Admin Relief for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
9/6/2019 8:46:51 AM
|
Request for Review Comments email sent for Project 645 Cimarron Admin Relief for review by Lindsay Darden on behalf of PCD Project Manager
|
9/6/2019 8:46:50 AM
|
Request for Review Comments email sent for Project 645 Cimarron Admin Relief for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
9/4/2019 7:30:35 PM
|
Fees paid: 9/4/2019 (Receipt: 1001740)
|
9/4/2019 3:43:21 PM
|
Payment Request sent: 9/4/2019
|
9/4/2019 3:43:04 PM
|
File # Assigned: ADR1917
|
9/3/2019 2:09:18 PM
|
Submission Triaged
|
9/3/2019 1:53:28 PM
|
Submission received from Applicant
|
9/3/2019 1:21:32 PM
|
Submission request sent to Applicant
|
9/3/2019 1:21:27 PM
|
Submission Triaged
|
9/3/2019 12:59:28 PM
|
Submission received from Applicant
|
9/3/2019 9:53:10 AM
|
Submission request sent to Applicant
|
9/3/2019 9:53:00 AM
|
Submission Triaged
|
9/3/2019 9:52:21 AM
|
Project Manager Assigned: Lindsay Darden
|
9/3/2019 8:14:04 AM
|
Submission received from Applicant
|
8/12/2019 12:46:58 PM
|
Submission request sent to Applicant
|
8/12/2019 12:44:45 PM
|
Project Manager Assigned: Nina Ruiz
|
8/12/2019 12:44:45 PM
|
Project Created
|