1/7/2020 8:32:15 AM
|
Project Closed
|
1/7/2020 8:32:15 AM
|
Project Approved: 1/6/2020
|
1/2/2020 1:40:56 PM
|
Request for Review Comments returned by PCD Project Manager
|
1/2/2020 1:40:35 PM
|
Request for Review Comments email sent for Project Emerald Vista Lot Line Adjustment for review by Ryan Howser on behalf of PCD Project Manager
|
1/2/2020 1:40:09 PM
|
Submission Triaged
|
1/2/2020 1:01:42 PM
|
Submission received from Applicant
|
1/2/2020 8:52:20 AM
|
Submission request sent to Applicant
|
1/2/2020 8:49:07 AM
|
Request for Review Comments returned by PCD Project Manager
|
1/2/2020 8:45:44 AM
|
Request for Review Comments email sent for Project Emerald Vista Lot Line Adjustment for review by Ryan Howser on behalf of PCD Project Manager
|
1/2/2020 8:36:09 AM
|
Submission Triaged
|
1/2/2020 7:50:04 AM
|
Submission received from Applicant
|
1/2/2020 7:25:07 AM
|
Submission request sent to Applicant
|
12/27/2019 3:01:46 PM
|
Submission Triaged
|
12/27/2019 1:51:41 PM
|
Submission received from Applicant
|
12/20/2019 3:09:01 PM
|
Submission request sent to Applicant
|
12/20/2019 3:07:37 PM
|
Request for Review Comments returned by PCD Project Manager
|
12/20/2019 3:02:59 PM
|
Request for Review Comments email sent for Project Emerald Vista Lot Line Adjustment for review by Ryan Howser on behalf of PCD Project Manager
|
12/20/2019 2:57:17 PM
|
Submission Triaged
|
12/20/2019 9:18:44 AM
|
Submission received from Applicant
|
12/19/2019 8:01:43 AM
|
Submission request sent to Applicant
|
12/3/2019 3:29:35 PM
|
Request for Review Comments returned by Upper Black Squirrel Creek GWMD
|
11/25/2019 11:44:46 AM
|
Request for Review Comments returned by PCD Project Manager
|
11/20/2019 2:32:08 PM
|
Request for Review Comments email sent for Project Emerald Vista Lot Line Adjustment for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
|
11/20/2019 2:32:06 PM
|
Request for Review Comments email sent for Project Emerald Vista Lot Line Adjustment for review by Ryan Howser on behalf of PCD Project Manager
|
11/20/2019 2:29:26 PM
|
Submission Triaged
|
11/20/2019 8:59:08 AM
|
Submission received from Applicant
|
11/20/2019 7:47:50 AM
|
Submission request sent to Applicant
|
11/18/2019 7:56:39 AM
|
Submission request sent to Applicant
|
11/15/2019 1:47:28 PM
|
Request for Review Comments returned by PCD Project Manager
|
11/15/2019 8:53:18 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
11/14/2019 11:02:58 AM
|
Request for Review Comments returned by PCD Engineering Division
|
11/12/2019 12:18:25 PM
|
Request for Review Comments returned by Upper Black Squirrel Creek GWMD
|
10/31/2019 11:03:42 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
10/31/2019 8:13:45 AM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
10/25/2019 2:58:58 PM
|
Request for Review Comments email sent for Project Emerald Vista Lot Line Adjustment for review by Autumn Mason on behalf of Woodmen Road Metro
|
10/25/2019 2:58:57 PM
|
Request for Review Comments email sent for Project Emerald Vista Lot Line Adjustment for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
|
10/25/2019 2:58:56 PM
|
Request for Review Comments email sent for Project Emerald Vista Lot Line Adjustment for review by Mr. David Pelser on behalf of Meridian Ranch/Meridian Service Metro Dist.
|
10/25/2019 2:58:55 PM
|
Request for Review Comments email sent for Project Emerald Vista Lot Line Adjustment for review by Chief Trent Harwig on behalf of Falcon Fire Protection District
|
10/25/2019 2:58:54 PM
|
Request for Review Comments email sent for Project Emerald Vista Lot Line Adjustment for review by Pamela Davison on behalf of El Paso County Conservation Dist
|
10/25/2019 2:58:53 PM
|
Request for Review Comments email sent for Project Emerald Vista Lot Line Adjustment for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
10/25/2019 2:58:51 PM
|
Request for Review Comments email sent for Project Emerald Vista Lot Line Adjustment for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
|
10/25/2019 2:58:50 PM
|
Request for Review Comments email sent for Project Emerald Vista Lot Line Adjustment for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
10/25/2019 2:58:49 PM
|
Request for Review Comments email sent for Project Emerald Vista Lot Line Adjustment for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
|
10/25/2019 2:58:48 PM
|
Request for Review Comments email sent for Project Emerald Vista Lot Line Adjustment for review by Ryan Howser on behalf of PCD Project Manager
|
10/25/2019 2:58:47 PM
|
Request for Review Comments email sent for Project Emerald Vista Lot Line Adjustment for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
10/24/2019 11:46:14 AM
|
Fees paid: 10/24/2019 (Receipt: 1001934)
|
10/24/2019 11:40:08 AM
|
Payment Request sent: 10/24/2019
|
10/24/2019 11:37:58 AM
|
File # Assigned: VR193
|
10/23/2019 4:35:55 PM
|
Submission Triaged
|
10/23/2019 4:35:39 PM
|
Project Manager Assigned: Ryan Howser
|
10/22/2019 1:44:04 PM
|
Submission received from Applicant
|
7/2/2019 2:21:20 PM
|
Submission request sent to Applicant
|
7/2/2019 2:15:56 PM
|
Project Manager Assigned: Len Kendall
|
7/2/2019 2:15:56 PM
|
EA Assigned: EA19116
|
7/2/2019 2:15:56 PM
|
Project Created
|