3/5/2020 8:50:26 AM
|
Project Closed
|
3/5/2020 8:50:25 AM
|
Project Approved: 3/5/2020
|
2/28/2020 1:09:49 PM
|
Submission Triaged
|
2/28/2020 11:27:25 AM
|
Submission received from Applicant
|
2/26/2020 10:41:58 AM
|
Submission request sent to Applicant
|
2/26/2020 10:39:28 AM
|
Request for Review Comments returned by PCD Project Manager
|
2/24/2020 10:53:57 AM
|
Request for Review Comments email sent for Project Peaceful Valley Interior Remodel for review by Petra Rangel on behalf of PCD Project Manager
|
2/24/2020 10:47:08 AM
|
Submission Triaged
|
2/21/2020 3:06:55 PM
|
Submission received from Applicant
|
2/19/2020 11:30:00 AM
|
Submission request sent to Applicant
|
2/18/2020 7:35:32 AM
|
Submission Triaged
|
2/17/2020 3:02:47 PM
|
Submission received from Applicant
|
2/13/2020 12:16:59 PM
|
Submission request sent to Applicant
|
2/13/2020 12:14:50 PM
|
Request for Review Comments returned by PCD Project Manager
|
2/13/2020 11:51:25 AM
|
Request for Review Comments email resent for Project Peaceful Valley Interior Remodel for review by Petra Rangel on behalf of PCD Project Manager
|
2/13/2020 10:44:46 AM
|
Request for Review Comments returned by PCD Project Manager
|
2/12/2020 3:00:06 PM
|
Request for Review Comments returned by PCD Engineering Division
|
2/11/2020 10:40:29 AM
|
Request for Review Comments email sent for Project Peaceful Valley Interior Remodel for review by Petra Rangel on behalf of PCD Project Manager
|
2/11/2020 10:40:27 AM
|
Request for Review Comments email sent for Project Peaceful Valley Interior Remodel for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
2/11/2020 7:24:15 AM
|
Submission Triaged
|
2/10/2020 1:55:34 PM
|
Submission received from Applicant
|
2/6/2020 8:59:39 AM
|
Submission request sent to Applicant
|
2/6/2020 8:56:05 AM
|
Submission Triaged
|
2/5/2020 5:15:35 PM
|
Submission received from Applicant
|
1/15/2020 10:33:43 AM
|
Submission request sent to Applicant
|
1/15/2020 10:32:29 AM
|
Submission Triaged
|
1/14/2020 3:42:59 PM
|
Submission received from Applicant
|
1/3/2020 11:56:41 AM
|
Request for Review Comments returned by EPC Health Department
|
12/13/2019 7:31:22 AM
|
Submission request sent to Applicant
|
12/12/2019 4:08:33 PM
|
Request for Review Comments returned by PCD Engineering Division
|
12/6/2019 2:35:38 PM
|
Request for Review Comments returned by PCD Project Manager
|
12/5/2019 8:17:08 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
11/26/2019 10:25:05 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
11/22/2019 7:35:25 AM
|
Request for Review Comments email sent for Project Peaceful Valley Interior Remodel for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
11/22/2019 7:35:22 AM
|
Request for Review Comments email sent for Project Peaceful Valley Interior Remodel for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
|
11/22/2019 7:35:18 AM
|
Request for Review Comments email sent for Project Peaceful Valley Interior Remodel for review by Petra Rangel on behalf of PCD Project Manager
|
11/22/2019 7:35:14 AM
|
Request for Review Comments email sent for Project Peaceful Valley Interior Remodel for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
11/22/2019 7:22:30 AM
|
Submission Triaged
|
11/21/2019 2:42:59 PM
|
Submission received from Applicant
|
10/31/2019 10:45:35 AM
|
Submission request sent to Applicant
|
10/31/2019 9:28:15 AM
|
Submission request sent to Applicant
|
10/31/2019 9:26:27 AM
|
Request for Review Comments returned by PCD Project Manager
|
10/30/2019 11:23:17 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
10/23/2019 4:23:03 PM
|
Request for Review Comments returned by PCD Engineering Division
|
10/21/2019 11:03:47 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
10/17/2019 1:34:13 PM
|
Request for Review Comments email sent for Project Peaceful Valley Interior Remodel for review by Kristy Martinez on behalf of Fountain
|
10/17/2019 1:34:12 PM
|
Request for Review Comments email sent for Project Peaceful Valley Interior Remodel for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
10/17/2019 1:34:11 PM
|
Request for Review Comments email sent for Project Peaceful Valley Interior Remodel for review by Dennis Neal on behalf of Widefield SD 3
|
10/17/2019 1:34:10 PM
|
Request for Review Comments email sent for Project Peaceful Valley Interior Remodel for review by Garrett Markus on behalf of Southeastern Colorado Water Conservancy
|
10/17/2019 1:34:09 PM
|
Request for Review Comments email sent for Project Peaceful Valley Interior Remodel for review by on behalf of Security Fire Protection District
|
10/17/2019 1:34:08 PM
|
Request for Review Comments email sent for Project Peaceful Valley Interior Remodel for review by P.E. Mgr. Gary Steen on behalf of Fountain Mutual Irrigation Company
|
10/17/2019 1:34:07 PM
|
Request for Review Comments email sent for Project Peaceful Valley Interior Remodel for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
|
10/17/2019 1:34:06 PM
|
Request for Review Comments email sent for Project Peaceful Valley Interior Remodel for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
10/17/2019 1:34:03 PM
|
Request for Review Comments email sent for Project Peaceful Valley Interior Remodel for review by on behalf of EPC Health Department
|
10/17/2019 1:34:02 PM
|
Request for Review Comments email sent for Project Peaceful Valley Interior Remodel for review by Petra Rangel on behalf of PCD Project Manager
|
10/17/2019 1:34:01 PM
|
Request for Review Comments email sent for Project Peaceful Valley Interior Remodel for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
10/17/2019 9:31:31 AM
|
Fees paid: 10/17/2019 (Receipt: 1001902)
|
10/16/2019 1:03:32 PM
|
Payment Request sent: 10/16/2019
|
10/16/2019 1:03:23 PM
|
Payment Request canceled: 10/16/2019
|
10/16/2019 1:03:18 PM
|
Payment Request sent: 10/16/2019
|
10/16/2019 1:03:10 PM
|
File # Assigned: PPR1948
|
10/16/2019 12:06:35 PM
|
Submission Triaged
|
10/16/2019 10:20:58 AM
|
Submission received from Applicant
|
10/15/2019 9:42:24 AM
|
Submission request sent to Applicant
|
10/15/2019 9:42:18 AM
|
Submission Triaged
|
10/11/2019 3:10:38 PM
|
Submission received from Applicant
|
10/1/2019 2:39:27 PM
|
Submission request sent to Applicant
|
10/1/2019 2:38:53 PM
|
Submission request canceled
|
6/24/2019 3:22:47 PM
|
Submission request sent to Applicant
|
6/24/2019 2:52:52 PM
|
Project Manager Assigned: Petra Rangel
|
6/24/2019 2:52:52 PM
|
Project Created
|