9/17/2019 2:31:21 PM
|
Project Closed
|
9/17/2019 2:31:21 PM
|
Project Cancelled: 9/17/2019
|
8/14/2019 11:05:37 AM
|
Project Manager Assigned: Lindsay Darden
|
7/23/2019 10:38:29 AM
|
Request for Review Comments returned by EPC Health Department
|
7/2/2019 6:36:18 AM
|
Request for Review Comments returned by Rock Creek Mesa Water Dist
|
6/27/2019 9:13:16 AM
|
Submission request sent to Applicant
|
6/27/2019 8:18:54 AM
|
Request for Review Comments returned by PCD Project Manager
|
6/26/2019 10:32:30 AM
|
Request for Review Comments returned by PCD Engineering Division
|
6/26/2019 7:14:51 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
6/24/2019 8:02:21 AM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
6/12/2019 4:41:47 PM
|
Request for Review Comments returned by EPC Code Enforcement
|
6/12/2019 10:53:30 AM
|
Request for Review Comments email sent for Project Gibson Administrative Relief for review by Hart Wright on behalf of Southwestern Hwy 115 Fire Protection District
|
6/12/2019 10:53:29 AM
|
Request for Review Comments email sent for Project Gibson Administrative Relief for review by Kathy Olson on behalf of Rock Creek Mesa Water Dist
|
6/12/2019 10:53:28 AM
|
Request for Review Comments email sent for Project Gibson Administrative Relief for review by UDS Admin Staff on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
6/12/2019 10:53:27 AM
|
Request for Review Comments email sent for Project Gibson Administrative Relief for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
6/12/2019 10:53:26 AM
|
Request for Review Comments email sent for Project Gibson Administrative Relief for review by on behalf of EPC Health Department
|
6/12/2019 10:53:25 AM
|
Request for Review Comments email sent for Project Gibson Administrative Relief for review by Mindy Madden on behalf of EPC Code Enforcement
|
6/12/2019 10:53:24 AM
|
Request for Review Comments email sent for Project Gibson Administrative Relief for review by Len Kendall on behalf of PCD Project Manager
|
6/12/2019 10:53:23 AM
|
Request for Review Comments email sent for Project Gibson Administrative Relief for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
6/12/2019 9:52:45 AM
|
Fees waived: 6/12/2019 by Mike Hrebenar (mikehrebenar@elpasoco.com)
|
6/3/2019 1:36:35 PM
|
Payment Request canceled: 6/3/2019
|
6/3/2019 1:36:15 PM
|
Payment Request sent: 6/3/2019
|
6/3/2019 1:32:49 PM
|
File # Assigned: ADR1910
|
6/3/2019 12:59:54 PM
|
Submission Triaged
|
6/3/2019 10:05:20 AM
|
Submission received from Applicant
|
5/23/2019 8:28:50 AM
|
Submission request sent to Applicant
|
5/23/2019 8:28:42 AM
|
Submission Triaged
|
5/22/2019 8:04:45 PM
|
Submission received from Applicant
|
5/17/2019 9:12:23 AM
|
Submission request sent to Applicant
|
5/17/2019 9:05:57 AM
|
Project Manager Assigned: Len Kendall
|
5/17/2019 9:05:57 AM
|
EA Assigned: EA18285
|
5/17/2019 9:05:56 AM
|
Project Created
|