7/23/2021 8:08:04 AM
|
Project Closed
|
7/23/2021 8:08:04 AM
|
Project Approved: 7/23/2021
|
7/7/2021 5:09:31 PM
|
Request for Review Comments returned by PCD Project Manager
|
7/7/2021 5:08:54 PM
|
Request for Review Comments email sent for Project Christian Construction, Inc. RHOC for review by Ryan Howser on behalf of PCD Project Manager
|
7/7/2021 4:45:29 PM
|
Submission Triaged
|
7/7/2021 4:29:24 PM
|
Submission received from Applicant
|
6/29/2021 5:05:52 PM
|
Submission request sent to Applicant
|
1/27/2021 3:50:44 PM
|
Submission request sent to Applicant
|
1/19/2021 2:48:08 PM
|
Project reopened for Review Comments
|
1/19/2021 2:47:52 PM
|
Project Manager Assigned: Ryan Howser
|
10/2/2020 6:47:11 AM
|
Project Closed
|
10/2/2020 6:47:11 AM
|
Project Cancelled: 10/2/2020
|
3/25/2020 10:09:10 AM
|
Request for Review Comments returned by EPC Code Enforcement
|
2/26/2020 2:38:20 PM
|
Submission request sent to Applicant
|
2/6/2020 8:56:00 AM
|
Request for Review Comments returned by PCD Project Manager
|
2/5/2020 4:05:07 PM
|
Request for Review Comments returned by Upper Black Squirrel Creek GWMD
|
1/30/2020 12:03:25 PM
|
Request for Review Comments returned by EPC Health Department
|
1/28/2020 5:30:20 PM
|
Request for Review Comments returned by PCD Engineering Division
|
1/22/2020 12:37:45 PM
|
Request for Review Comments email sent for Project Christian Construction, Inc. RHOC for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
|
1/22/2020 12:37:43 PM
|
Request for Review Comments email sent for Project Christian Construction, Inc. RHOC for review by Mindy Madden on behalf of EPC Code Enforcement
|
1/22/2020 12:37:39 PM
|
Request for Review Comments email sent for Project Christian Construction, Inc. RHOC for review by Rad Dickson on behalf of PCD Project Manager
|
1/22/2020 12:37:34 PM
|
Request for Review Comments email sent for Project Christian Construction, Inc. RHOC for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
1/22/2020 10:56:35 AM
|
Submission Triaged
|
1/22/2020 10:26:15 AM
|
Submission received from Applicant
|
12/18/2019 7:55:18 AM
|
Submission request sent to Applicant
|
12/17/2019 3:21:12 PM
|
Request for Review Comments returned by PCD Project Manager
|
12/17/2019 3:19:22 PM
|
Request for Review Comments email resent for Project Christian Construction, Inc. RHOC for review by Rad Dickson on behalf of PCD Project Manager
|
12/17/2019 3:08:57 PM
|
Request for Review Comments returned by PCD Project Manager
|
12/12/2019 5:06:24 PM
|
Request for Review Comments returned by PCD Engineering Division
|
12/6/2019 7:57:24 PM
|
Request for Review Comments returned by EPC Code Enforcement
|
12/3/2019 4:07:47 PM
|
Request for Review Comments email resent for Project Christian Construction, Inc. RHOC for review by Rad Dickson on behalf of PCD Project Manager
|
12/3/2019 4:06:01 PM
|
Request for Review Comments email sent for Project Christian Construction, Inc. RHOC for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
12/3/2019 4:05:08 PM
|
Request for Review Comments email sent for Project Christian Construction, Inc. RHOC for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
12/3/2019 3:32:05 PM
|
Request for Review Comments returned by Upper Black Squirrel Creek GWMD
|
12/3/2019 8:24:05 AM
|
Request for Review Comments email sent for Project Christian Construction, Inc. RHOC for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
12/2/2019 11:15:12 AM
|
Request for Review Comments returned by PCD Project Manager
|
11/25/2019 1:42:40 PM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
11/21/2019 4:45:09 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
11/15/2019 4:17:03 PM
|
Request for Review Comments email sent for Project Christian Construction, Inc. RHOC for review by Patrick Palacol on behalf of Peyton Fire Protection District
|
11/15/2019 4:17:02 PM
|
Request for Review Comments email sent for Project Christian Construction, Inc. RHOC for review by Maint Dir Greg Land on behalf of Peyton 23
|
11/15/2019 4:17:01 PM
|
Request for Review Comments email sent for Project Christian Construction, Inc. RHOC for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
|
11/15/2019 4:17:00 PM
|
Request for Review Comments email sent for Project Christian Construction, Inc. RHOC for review by Pamela Davison on behalf of El Paso County Conservation Dist
|
11/15/2019 4:16:59 PM
|
Request for Review Comments email sent for Project Christian Construction, Inc. RHOC for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
|
11/15/2019 4:16:58 PM
|
Request for Review Comments email sent for Project Christian Construction, Inc. RHOC for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
|
11/15/2019 4:16:56 PM
|
Request for Review Comments email sent for Project Christian Construction, Inc. RHOC for review by on behalf of EPC Health Department
|
11/15/2019 4:16:55 PM
|
Request for Review Comments email sent for Project Christian Construction, Inc. RHOC for review by Mindy Madden on behalf of EPC Code Enforcement
|
11/15/2019 4:16:53 PM
|
Request for Review Comments email sent for Project Christian Construction, Inc. RHOC for review by Rad Dickson on behalf of PCD Project Manager
|
11/15/2019 4:16:52 PM
|
Request for Review Comments email sent for Project Christian Construction, Inc. RHOC for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
11/14/2019 11:24:32 AM
|
Fees paid: 11/14/2019 (Receipt: 1002024)
|
11/12/2019 3:51:38 PM
|
Payment Request sent: 11/12/2019
|
11/12/2019 3:50:36 PM
|
File # Assigned: AL1930
|
11/12/2019 7:55:14 AM
|
Submission Triaged
|
11/11/2019 12:51:46 PM
|
Submission received from Applicant
|
11/6/2019 1:24:29 PM
|
Submission request sent to Applicant
|
11/6/2019 1:20:36 PM
|
Submission Triaged
|
11/6/2019 1:18:55 PM
|
Project Manager Assigned: Rad Dickson
|
11/6/2019 10:55:17 AM
|
Submission received from Applicant
|
10/23/2019 3:42:16 PM
|
Submission request sent to Applicant
|
10/23/2019 3:38:54 PM
|
Submission Triaged
|
10/21/2019 3:26:18 PM
|
Submission received from Applicant
|
9/30/2019 9:08:46 AM
|
Submission request sent to Applicant
|
1/15/2019 10:23:24 AM
|
Submission request sent to Applicant
|
1/15/2019 10:01:56 AM
|
Project Manager Assigned: Len Kendall
|
1/15/2019 10:01:56 AM
|
Project Created
|