2/10/2020 1:42:39 PM
|
Project Closed
|
2/10/2020 1:42:39 PM
|
Project Approved: 2/10/2020
|
1/8/2020 4:53:37 PM
|
Submission request sent to Applicant
|
1/2/2020 5:35:08 PM
|
Request for Review Comments returned by EPC Health Department
|
12/31/2019 2:31:54 PM
|
Submission request sent to Applicant
|
12/30/2019 5:45:35 PM
|
Request for Review Comments returned by PCD Engineering Division
|
12/27/2019 4:20:01 PM
|
Request for Review Comments returned by EPC County Attorney's Office
|
12/23/2019 6:38:42 AM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
12/23/2019 6:37:56 AM
|
Submission Triaged
|
12/19/2019 3:53:53 PM
|
Submission received from Applicant
|
12/19/2019 12:30:48 PM
|
Submission request sent to Applicant
|
12/19/2019 11:53:00 AM
|
Submission request sent to Applicant
|
12/17/2019 7:19:04 AM
|
Request for Review Comments returned by PCD Engineering Division
|
12/17/2019 6:37:18 AM
|
Submission Triaged
|
12/12/2019 8:19:20 PM
|
Submission received from Applicant
|
12/11/2019 12:45:09 PM
|
Submission request sent to Applicant
|
12/10/2019 10:41:41 AM
|
Submission Triaged
|
12/10/2019 9:47:58 AM
|
Submission received from Applicant
|
12/10/2019 9:42:39 AM
|
Submission request sent to Applicant
|
12/10/2019 5:27:21 AM
|
Request for Review Comments returned by PCD Project Manager
|
12/9/2019 5:10:48 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by Nina Ruiz on behalf of PCD Project Manager
|
12/9/2019 5:10:47 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
12/9/2019 5:09:25 PM
|
Submission Triaged
|
12/9/2019 3:19:53 PM
|
Submission received from Applicant
|
12/9/2019 10:49:57 AM
|
Request for Review Comments returned by PCD Engineering Division
|
12/9/2019 10:44:57 AM
|
Submission request sent to Applicant
|
12/9/2019 10:43:43 AM
|
Submission request sent to Applicant
|
12/5/2019 12:55:37 PM
|
Request for Review Comments returned by PCD Project Manager
|
11/26/2019 9:28:36 AM
|
Request for Review Comments returned by Colorado Geological Survey
|
11/25/2019 2:12:19 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
11/25/2019 2:12:18 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by Nina Ruiz on behalf of PCD Project Manager
|
11/25/2019 2:12:15 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
11/25/2019 2:11:26 PM
|
Submission Triaged
|
11/25/2019 11:54:39 AM
|
Submission received from Applicant
|
10/31/2019 9:28:44 AM
|
Request for Review Comments returned by Parks Advisory Board
|
10/31/2019 9:27:34 AM
|
Request for Review Comments returned by EPC Parks Department
|
10/30/2019 7:29:26 AM
|
Submission request sent to Applicant
|
10/30/2019 7:27:49 AM
|
Request for Review Comments returned by PCD Project Manager
|
10/30/2019 7:26:09 AM
|
Request for Review Comments email resent for Project Walker Reserve Minor Subdivision for review by Nina Ruiz on behalf of PCD Project Manager
|
10/30/2019 7:05:10 AM
|
Request for Review Comments returned by PCD Project Manager
|
10/29/2019 10:07:41 PM
|
Request for Review Comments returned by PCD Engineering Division
|
10/29/2019 11:05:59 AM
|
Request for Review Comments returned by Colorado Geological Survey
|
10/29/2019 10:10:11 AM
|
Request for Review Comments returned by Northern EPC Coalition of Community Organizations, Inc. (NEPCO)
|
10/29/2019 6:27:50 AM
|
Submission request sent to Applicant
|
10/28/2019 8:11:31 PM
|
Request for Review Comments returned by Black Forest Land Use Committee
|
10/28/2019 1:13:00 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
10/23/2019 3:23:34 PM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
10/23/2019 8:52:47 AM
|
Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
|
10/21/2019 12:36:42 PM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
10/21/2019 9:16:42 AM
|
Request for Review Comments returned by EPC Environmental Services
|
10/18/2019 12:21:05 PM
|
Submission Triaged
|
10/17/2019 3:40:52 PM
|
Submission received from Applicant
|
10/17/2019 2:10:22 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
10/16/2019 5:20:08 PM
|
Submission request sent to Applicant
|
10/16/2019 4:24:36 PM
|
Request for Review Comments returned by Lewis Palmer 38
|
10/16/2019 3:25:03 PM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
10/15/2019 3:30:00 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by Jamey Bumgarner on behalf of Tri-Lakes-Monument Fire Protection District
|
10/15/2019 3:29:57 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by Tom Vierzbea on behalf of Northern EPC Coalition of Community Organizations, Inc. (NEPCO)
|
10/15/2019 3:29:53 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
|
10/15/2019 3:29:45 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by Vicki Wood on behalf of Lewis Palmer 38
|
10/15/2019 3:29:34 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by Pamela Davison on behalf of El Paso County Conservation Dist
|
10/15/2019 3:29:31 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by Terry Stokka on behalf of Black Forest Land Use Committee
|
10/15/2019 3:29:27 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by RBD Enumerations & Floodplain on behalf of Pikes Peak Regional Building Department
|
10/15/2019 3:29:19 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
10/15/2019 3:29:15 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
10/15/2019 3:29:08 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
10/15/2019 3:29:04 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by on behalf of Parks Advisory Board
|
10/15/2019 3:29:00 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by on behalf of EPC Parks Department
|
10/15/2019 3:28:45 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by on behalf of EPC Health Department
|
10/15/2019 3:28:41 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by Kathy Andrew on behalf of EPC Environmental Services
|
10/15/2019 3:28:38 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by Edi Anderson on behalf of EPC County Attorney's Office
|
10/15/2019 3:28:34 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by Nina Ruiz on behalf of PCD Project Manager
|
10/15/2019 3:28:27 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
9/10/2019 5:02:19 AM
|
Submission Triaged
|
9/4/2019 12:00:47 PM
|
Submission received from Applicant
|
9/3/2019 1:47:12 PM
|
Request for Review Comments returned by EPC Health Department
|
8/7/2019 9:07:00 AM
|
Request for Review Comments returned by EPC County Attorney's Office
|
7/26/2019 11:44:09 AM
|
Request for Review Comments returned by Parks Advisory Board
|
7/26/2019 11:40:47 AM
|
Request for Review Comments returned by EPC Parks Department
|
7/22/2019 12:09:47 PM
|
Submission request sent to Applicant
|
7/22/2019 11:44:49 AM
|
Request for Review Comments returned by PCD Project Manager
|
7/22/2019 11:40:38 AM
|
Request for Review Comments email resent for Project Walker Reserve Minor Subdivision for review by Nina Ruiz on behalf of PCD Project Manager
|
7/18/2019 3:38:09 PM
|
Request for Review Comments returned by PCD Engineering Division
|
7/16/2019 5:25:23 PM
|
Request for Review Comments returned by Lewis Palmer 38
|
7/15/2019 5:19:26 PM
|
Request for Review Comments returned by PCD Project Manager
|
7/15/2019 9:46:03 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
7/15/2019 5:15:57 AM
|
Submission request sent to Applicant
|
7/12/2019 1:42:06 PM
|
Request for Review Comments returned by Colorado Geological Survey
|
7/10/2019 10:32:45 AM
|
Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
|
7/8/2019 5:05:08 PM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
7/8/2019 3:20:45 PM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
7/8/2019 3:14:43 PM
|
Request for Review Comments returned by Northern EPC Coalition of Community Organizations, Inc. (NEPCO)
|
7/8/2019 1:50:48 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
7/3/2019 10:11:25 AM
|
Request for Review Comments returned by EPC Environmental Services
|
6/30/2019 11:10:13 AM
|
Request for Review Comments returned by Black Forest Land Use Committee
|
6/28/2019 12:40:27 PM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
6/27/2019 3:54:41 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by Jamey Bumgarner on behalf of Tri-Lakes-Monument Fire Protection District
|
6/27/2019 3:54:40 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by Tom Vierzbea on behalf of Northern EPC Coalition of Community Organizations, Inc. (NEPCO)
|
6/27/2019 3:54:39 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
|
6/27/2019 3:54:37 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by Vicki Wood on behalf of Lewis Palmer 38
|
6/27/2019 3:54:36 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by Pamela Davison on behalf of El Paso County Conservation Dist
|
6/27/2019 3:54:35 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by Cheryl Pixley on behalf of Black Forest Trails Association
|
6/27/2019 3:54:34 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by Terry Stokka on behalf of Black Forest Land Use Committee
|
6/27/2019 3:54:33 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by RBD Enumerations & Floodplain on behalf of Pikes Peak Regional Building Department
|
6/27/2019 3:54:31 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
6/27/2019 3:54:30 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
6/27/2019 3:54:29 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
6/27/2019 3:54:28 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by on behalf of Parks Advisory Board
|
6/27/2019 3:54:27 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by on behalf of EPC Parks Department
|
6/27/2019 3:54:23 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by on behalf of EPC Health Department
|
6/27/2019 3:54:22 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by Kathy Andrew on behalf of EPC Environmental Services
|
6/27/2019 3:54:21 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by Nina Ruiz on behalf of PCD Project Manager
|
6/27/2019 3:54:20 PM
|
Request for Review Comments email sent for Project Walker Reserve Minor Subdivision for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
6/27/2019 3:52:52 PM
|
Submission Triaged
|
6/27/2019 2:41:37 PM
|
Submission received from Applicant
|
6/12/2019 3:25:09 PM
|
Request for Review Comments returned by Lewis Palmer 38
|
6/9/2019 12:48:32 PM
|
Request for Review Comments returned by EPC Health Department
|
5/22/2019 7:35:34 AM
|
Submission request sent to Applicant
|
5/22/2019 7:33:37 AM
|
Request for Review Comments returned by PCD Project Manager
|
5/22/2019 7:31:47 AM
|
Request for Review Comments email resent for Project Walker Reserve Minor Subdivision for review by Nina Ruiz on behalf of PCD Project Manager
|
5/20/2019 5:53:48 PM
|
Request for Review Comments returned by PCD Engineering Division
|
5/20/2019 1:59:51 PM
|
Request for Review Comments returned by Northern EPC Coalition of Community Organizations, Inc. (NEPCO)
|
5/17/2019 9:53:06 AM
|
Request for Review Comments returned by PCD Project Manager
|
5/16/2019 1:45:20 PM
|
Request for Review Comments returned by Colorado Geological Survey
|
5/14/2019 11:56:28 PM
|
Request for Review Comments returned by Black Forest Trails Association
|
5/13/2019 8:48:48 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
5/7/2019 2:13:34 PM
|
Request for Review Comments returned by EPC Parks Department
|
5/7/2019 1:41:50 PM
|
Request for Review Comments returned by Parks Advisory Board
|
5/3/2019 10:50:35 AM
|
Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
|
5/2/2019 9:20:54 AM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
4/29/2019 9:04:23 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
4/25/2019 4:44:52 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
4/25/2019 3:12:26 PM
|
Request for Review Comments returned by EPC Environmental Services
|
4/25/2019 11:46:31 AM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
4/23/2019 8:15:41 PM
|
Request for Review Comments returned by Black Forest Land Use Committee
|
4/23/2019 10:28:53 AM
|
Request for Review Comments email sent for Project Walker Minor Subdivision for review by Jamey Bumgarner on behalf of Tri-Lakes-Monument Fire Protection District
|
4/23/2019 10:28:48 AM
|
Request for Review Comments email sent for Project Walker Minor Subdivision for review by Tom Vierzbea on behalf of Northern EPC Coalition of Community Organizations, Inc. (NEPCO)
|
4/23/2019 10:28:43 AM
|
Request for Review Comments email sent for Project Walker Minor Subdivision for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
|
4/23/2019 10:28:37 AM
|
Request for Review Comments email sent for Project Walker Minor Subdivision for review by Vicki Wood on behalf of Lewis Palmer 38
|
4/23/2019 10:28:33 AM
|
Request for Review Comments email sent for Project Walker Minor Subdivision for review by Pamela Davison on behalf of El Paso County Conservation Dist
|
4/23/2019 10:28:29 AM
|
Request for Review Comments email sent for Project Walker Minor Subdivision for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
4/23/2019 10:28:18 AM
|
Request for Review Comments email sent for Project Walker Minor Subdivision for review by Cheryl Pixley on behalf of Black Forest Trails Association
|
4/23/2019 10:28:11 AM
|
Request for Review Comments email sent for Project Walker Minor Subdivision for review by Terry Stokka on behalf of Black Forest Land Use Committee
|
4/23/2019 10:28:06 AM
|
Request for Review Comments email sent for Project Walker Minor Subdivision for review by RBD Enumerations & Floodplain on behalf of Pikes Peak Regional Building Department
|
4/23/2019 10:28:02 AM
|
Request for Review Comments email sent for Project Walker Minor Subdivision for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
4/23/2019 10:27:57 AM
|
Request for Review Comments email sent for Project Walker Minor Subdivision for review by Jeffrey Hovermale on behalf of US Forest Service, Pikes Peak Ranger District
|
4/23/2019 10:27:50 AM
|
Request for Review Comments email sent for Project Walker Minor Subdivision for review by Christopher Grosso on behalf of US Army Corps of Engineers-Pueblo
|
4/23/2019 10:27:45 AM
|
Request for Review Comments email sent for Project Walker Minor Subdivision for review by Larry Long on behalf of Colorado State Forest Service
|
4/23/2019 10:27:40 AM
|
Request for Review Comments email sent for Project Walker Minor Subdivision for review by Energy and Land Use Specialist Karen Voltura on behalf of Colorado Parks and Wildlife
|
4/23/2019 10:27:33 AM
|
Request for Review Comments email sent for Project Walker Minor Subdivision for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
4/23/2019 10:27:28 AM
|
Request for Review Comments email sent for Project Walker Minor Subdivision for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
4/23/2019 10:27:22 AM
|
Request for Review Comments email sent for Project Walker Minor Subdivision for review by John Hunyadi on behalf of Colorado Dam Safety Division
|
4/23/2019 10:27:17 AM
|
Request for Review Comments email sent for Project Walker Minor Subdivision for review by on behalf of Parks Advisory Board
|
4/23/2019 10:27:12 AM
|
Request for Review Comments email sent for Project Walker Minor Subdivision for review by Commander John Padgett on behalf of EPC Sheriff's Department
|
4/23/2019 10:27:07 AM
|
Request for Review Comments email sent for Project Walker Minor Subdivision for review by on behalf of EPC Parks Department
|
4/23/2019 10:26:44 AM
|
Request for Review Comments email sent for Project Walker Minor Subdivision for review by on behalf of EPC Health Department
|
4/23/2019 10:26:39 AM
|
Request for Review Comments email sent for Project Walker Minor Subdivision for review by Kathy Andrew on behalf of EPC Environmental Services
|
4/23/2019 10:26:34 AM
|
Request for Review Comments email sent for Project Walker Minor Subdivision for review by Edi Anderson on behalf of EPC County Attorney's Office
|
4/23/2019 10:26:22 AM
|
Request for Review Comments email sent for Project Walker Minor Subdivision for review by Nina Ruiz on behalf of PCD Project Manager
|
4/23/2019 10:26:17 AM
|
Request for Review Comments email sent for Project Walker Minor Subdivision for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
4/23/2019 10:24:22 AM
|
Fees paid: 4/23/2019 (Receipt: 1001370)
|
4/22/2019 3:23:56 PM
|
Payment Request sent: 4/22/2019
|
4/22/2019 3:23:51 PM
|
File # Assigned: MS194
|
4/22/2019 10:43:31 AM
|
Submission Triaged
|
4/22/2019 9:14:02 AM
|
Submission received from Applicant
|
4/22/2019 7:49:50 AM
|
Submission request sent to Applicant
|
4/22/2019 7:49:36 AM
|
Submission Triaged
|
4/18/2019 11:24:53 AM
|
Submission received from Applicant
|
4/18/2019 10:48:09 AM
|
Submission request sent to Applicant
|
4/18/2019 10:46:53 AM
|
Submission Triaged
|
4/18/2019 8:40:35 AM
|
Submission received from Applicant
|
4/16/2019 9:38:19 AM
|
Submission request sent to Applicant
|
4/16/2019 9:37:45 AM
|
Submission Triaged
|
4/15/2019 4:18:43 PM
|
Submission received from Applicant
|
3/26/2019 12:13:26 PM
|
Submission request sent to Applicant
|
3/26/2019 12:12:53 PM
|
Submission Triaged
|
3/25/2019 2:48:51 PM
|
Submission received from Applicant
|
12/6/2018 11:27:30 AM
|
Submission request sent to Applicant
|
12/6/2018 11:19:10 AM
|
Project Manager Assigned: Nina Ruiz
|
12/6/2018 11:19:10 AM
|
Project Created
|