5/13/2022 10:42:19 AM
|
Project Closed
|
5/13/2022 10:42:19 AM
|
Project Approved: 5/13/2022
|
11/12/2021 4:23:47 PM
|
Request for Review Comments returned by PCD Engineering Division
|
10/28/2021 5:24:18 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
10/28/2021 5:23:11 PM
|
Submission Triaged
|
10/28/2021 2:23:45 PM
|
Submission received from Applicant
|
10/21/2021 2:38:46 PM
|
Submission request sent to Applicant
|
10/20/2021 10:10:38 AM
|
Request for Review Comments returned by PCD Engineering Division
|
9/21/2021 9:16:52 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
9/21/2021 9:14:44 PM
|
Submission Triaged
|
9/13/2021 2:41:40 PM
|
Submission received from Applicant
|
9/13/2021 1:32:17 PM
|
Submission request sent to Applicant
|
7/19/2021 9:27:49 PM
|
Submission request sent to Applicant
|
7/13/2021 5:15:58 PM
|
Request for Review Comments returned by PCD Engineering Division
|
6/13/2021 7:55:48 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
6/13/2021 7:53:34 PM
|
Submission Triaged
|
6/11/2021 8:44:25 AM
|
Submission received from Applicant
|
6/10/2021 8:19:29 AM
|
Submission request sent to Applicant
|
5/6/2021 1:37:22 PM
|
Request for Review Comments returned by PCD Engineering Division
|
4/30/2021 8:45:22 AM
|
Request for Review Comments returned by EPC County Attorney's Office
|
4/30/2021 6:27:34 AM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Edi Anderson on behalf of EPC County Attorney's Office
|
4/30/2021 6:27:29 AM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
4/30/2021 6:25:02 AM
|
Submission Triaged
|
4/29/2021 1:10:17 PM
|
Submission received from Applicant
|
4/28/2021 7:46:25 AM
|
Request for Review Comments returned by PCD Administrative Notice
|
4/20/2021 12:43:01 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Elena Krebs on behalf of PCD Administrative Notice
|
4/18/2021 12:25:43 PM
|
Submission request sent to Applicant
|
4/15/2021 5:06:25 PM
|
Request for Review Comments returned by PCD Engineering Division
|
4/15/2021 8:07:04 AM
|
Request for Review Comments returned by PCD Project Manager
|
3/23/2021 5:19:44 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Nina Ruiz on behalf of PCD Project Manager
|
3/23/2021 5:19:33 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
3/23/2021 5:12:58 PM
|
Submission Triaged
|
3/22/2021 7:55:53 AM
|
Submission received from Applicant
|
3/19/2021 12:36:51 PM
|
Submission request sent to Applicant
|
3/19/2021 12:35:55 PM
|
Submission Triaged
|
3/18/2021 4:09:15 PM
|
Submission received from Applicant
|
1/6/2021 1:55:38 PM
|
Request for Review Comments returned by EPC County Attorney's Office
|
1/5/2021 3:25:33 PM
|
Submission request sent to Applicant
|
1/5/2021 8:01:52 AM
|
Request for Review Comments returned by PCD Engineering Division
|
12/29/2020 9:03:42 PM
|
Request for Review Comments returned by EPC Health Department
|
12/28/2020 4:20:49 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
12/28/2020 4:19:19 PM
|
Submission Triaged
|
12/28/2020 4:13:22 PM
|
Submission received from Applicant
|
12/25/2020 12:34:28 PM
|
Submission request sent to Applicant
|
12/22/2020 2:49:10 PM
|
Request for Review Comments returned by PCD Engineering Division
|
12/11/2020 3:38:59 PM
|
Request for Review Comments returned by Colorado Department of Public Health and Environment
|
12/4/2020 2:51:14 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Edi Anderson on behalf of EPC County Attorney's Office
|
12/4/2020 2:51:06 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
12/4/2020 2:42:48 PM
|
Submission Triaged
|
12/4/2020 11:07:32 AM
|
Submission received from Applicant
|
11/29/2020 4:12:55 PM
|
Request for Review Comments returned by PCD Project Manager
|
11/28/2020 1:35:25 PM
|
Submission request sent to Applicant
|
11/25/2020 5:41:55 PM
|
Request for Review Comments returned by PCD Engineering Division
|
11/23/2020 4:51:14 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Sean Hackett on behalf of Colorado Department of Public Health and Environment
|
11/19/2020 8:58:08 AM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
11/18/2020 9:08:03 AM
|
Request for Review Comments returned by EPC County Attorney's Office
|
11/5/2020 11:48:00 AM
|
Request for Review Comments returned by Colorado Department of Public Health and Environment
|
11/4/2020 9:37:09 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
11/4/2020 9:37:06 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Sean Hackett on behalf of Colorado Department of Public Health and Environment
|
11/4/2020 9:37:00 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by on behalf of EPC Health Department
|
11/4/2020 9:36:51 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Edi Anderson on behalf of EPC County Attorney's Office
|
11/4/2020 9:36:49 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Nina Ruiz on behalf of PCD Project Manager
|
11/4/2020 9:36:41 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
11/4/2020 9:30:27 PM
|
Submission Triaged
|
11/3/2020 4:24:53 PM
|
Submission received from Applicant
|
8/25/2020 7:16:35 AM
|
Submission request sent to Applicant
|
8/21/2020 6:21:44 PM
|
Request for Review Comments returned by PCD Engineering Division
|
8/16/2020 7:33:17 AM
|
Request for Review Comments returned by PCD Project Manager
|
7/23/2020 5:41:27 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Nina Ruiz on behalf of PCD Project Manager
|
7/23/2020 5:41:23 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
7/23/2020 5:38:05 PM
|
Submission Triaged
|
7/23/2020 2:28:00 PM
|
Submission received from Applicant
|
7/21/2020 9:09:39 PM
|
Submission request sent to Applicant
|
7/10/2020 7:35:12 AM
|
Submission request sent to Applicant
|
7/10/2020 7:33:38 AM
|
Request for Review Comments returned by PCD Project Manager
|
7/10/2020 7:31:08 AM
|
Request for Review Comments email resent for Project Saddlehorn (824 Acres), Final Plat for review by Nina Ruiz on behalf of PCD Project Manager
|
7/9/2020 8:14:02 AM
|
Request for Review Comments returned by PCD Engineering Division
|
7/8/2020 5:12:28 AM
|
Request for Review Comments returned by PCD Project Manager
|
6/30/2020 10:57:02 AM
|
Request for Review Comments returned by EPC County Attorney's Office
|
6/10/2020 8:47:59 AM
|
Request for Review Comments returned by Colorado Department of Public Health and Environment
|
6/9/2020 8:25:08 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Sean Hackett on behalf of Colorado Department of Public Health and Environment
|
6/9/2020 8:25:06 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by on behalf of EPC Health Department
|
6/9/2020 8:25:04 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Edi Anderson on behalf of EPC County Attorney's Office
|
6/9/2020 8:25:03 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Nina Ruiz on behalf of PCD Project Manager
|
6/9/2020 8:25:01 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
6/9/2020 8:20:41 PM
|
Submission Triaged
|
6/9/2020 11:11:17 AM
|
Submission received from Applicant
|
4/30/2020 3:13:16 PM
|
Submission request sent to Applicant
|
4/21/2020 4:45:13 PM
|
Request for Review Comments returned by EPC Health Department
|
4/15/2020 8:37:32 AM
|
Request for Review Comments returned by EPC County Attorney's Office
|
4/13/2020 10:34:32 PM
|
Request for Review Comments returned by PCD Engineering Division
|
4/11/2020 6:54:29 AM
|
Request for Review Comments email resent for Project Saddlehorn (824 Acres), Final Plat for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
4/10/2020 1:04:37 PM
|
Request for Review Comments returned by PCD Engineering Division
|
4/8/2020 1:44:57 PM
|
Request for Review Comments returned by PCD Project Manager
|
4/1/2020 12:20:15 PM
|
Request for Review Comments returned by Falcon Fire Protection District
|
4/1/2020 9:44:41 AM
|
Request for Review Comments returned by Colorado Department of Public Health and Environment
|
3/18/2020 5:05:30 PM
|
Request for Review Comments email resent for Project Saddlehorn (824 Acres), Final Plat for review by Sean Hackett on behalf of Colorado Department of Public Health and Environment
|
3/18/2020 2:00:40 PM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
3/17/2020 1:00:01 PM
|
Request for Review Comments returned by Colorado Department of Public Health and Environment
|
3/12/2020 12:24:19 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
3/12/2020 12:24:19 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Permits Manager Valerie Sword on behalf of Colorado Department of Transportation - Pueblo Office
|
3/12/2020 12:24:15 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Sean Hackett on behalf of Colorado Department of Public Health and Environment
|
3/12/2020 12:24:14 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
|
3/12/2020 12:24:10 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by on behalf of EPC Health Department
|
3/12/2020 12:24:10 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Edi Anderson on behalf of EPC County Attorney's Office
|
3/12/2020 12:24:09 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Nina Ruiz on behalf of PCD Project Manager
|
3/12/2020 12:24:06 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
3/12/2020 12:12:32 PM
|
Submission Triaged
|
3/11/2020 4:59:25 PM
|
Submission received from Applicant
|
2/3/2020 3:48:31 PM
|
Submission request sent to Applicant
|
1/29/2020 5:19:24 AM
|
Submission request sent to Applicant
|
1/29/2020 5:07:36 AM
|
Submission request sent to Applicant
|
1/15/2020 10:53:50 AM
|
Request for Review Comments returned by EPC County Attorney's Office
|
1/10/2020 12:30:00 PM
|
Request for Review Comments returned by PCD Engineering Division
|
1/9/2020 6:59:20 AM
|
Request for Review Comments returned by PCD Project Manager
|
1/8/2020 3:11:04 PM
|
Request for Review Comments email resent for Project Saddlehorn (824 Acres), Final Plat for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
1/7/2020 11:22:05 AM
|
Request for Review Comments returned by PCD Engineering Division
|
12/19/2019 6:23:41 AM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Nina Ruiz on behalf of PCD Project Manager
|
12/19/2019 6:23:39 AM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
12/19/2019 6:22:27 AM
|
Submission Triaged
|
12/18/2019 1:39:29 PM
|
Submission received from Applicant
|
12/18/2019 12:59:39 PM
|
Submission request sent to Applicant
|
12/6/2019 7:06:22 PM
|
Request for Review Comments returned by EPC Health Department
|
10/30/2019 7:24:21 AM
|
Submission request sent to Applicant
|
10/29/2019 12:22:30 PM
|
Request for Review Comments returned by PCD Engineering Division
|
10/15/2019 1:51:06 PM
|
Request for Review Comments returned by PCD Project Manager
|
10/10/2019 1:06:36 PM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
10/9/2019 8:47:46 AM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
10/8/2019 11:09:19 AM
|
Request for Review Comments returned by EPC Environmental Services
|
10/4/2019 11:12:14 AM
|
Request for Review Comments returned by Colorado Geological Survey
|
9/26/2019 12:28:30 PM
|
Request for Review Comments returned by Schriever AFB
|
9/24/2019 11:01:39 AM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
9/22/2019 11:57:34 AM
|
Request for Review Comments returned by Parks Advisory Board
|
9/19/2019 2:03:17 PM
|
Request for Review Comments returned by Central CO Conservation District
|
9/19/2019 12:28:05 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Darren Horstmeier on behalf of Schriever AFB
|
9/19/2019 12:28:01 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Chief Trent Harwig on behalf of Falcon Fire Protection District
|
9/19/2019 12:27:58 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Pamela Davison on behalf of El Paso County Conservation Dist
|
9/19/2019 12:27:54 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by UDS Admin Staff on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
9/19/2019 12:27:51 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Pamela Davidson on behalf of Central CO Conservation District
|
9/19/2019 12:27:47 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
9/19/2019 12:27:40 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
9/19/2019 12:27:36 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by on behalf of Parks Advisory Board
|
9/19/2019 12:27:22 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by on behalf of EPC Health Department
|
9/19/2019 12:27:18 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Kathy Andrew on behalf of EPC Environmental Services
|
9/19/2019 12:27:14 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Nina Ruiz on behalf of PCD Project Manager
|
9/19/2019 12:27:03 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
9/19/2019 12:22:21 PM
|
Submission Triaged
|
9/19/2019 12:15:47 PM
|
Submission received from Applicant
|
9/19/2019 12:10:37 PM
|
Submission request sent to Applicant
|
9/19/2019 12:10:19 PM
|
Submission Triaged
|
9/19/2019 12:06:56 PM
|
Submission received from Applicant
|
8/15/2019 8:26:53 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
8/7/2019 4:35:21 PM
|
Submission request sent to Applicant
|
8/7/2019 12:39:59 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
8/1/2019 7:55:38 AM
|
Submission request sent to Applicant
|
7/30/2019 10:40:51 AM
|
Request for Review Comments returned by EPC Parks Department
|
7/25/2019 12:36:06 PM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
7/25/2019 12:19:19 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
|
7/25/2019 12:19:15 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by RBD Enumerations & Floodplain on behalf of Pikes Peak Regional Building Department
|
7/25/2019 12:19:08 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
7/25/2019 12:19:04 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by on behalf of EPC Parks Department
|
7/25/2019 12:19:00 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Nina Ruiz on behalf of PCD Project Manager
|
7/25/2019 12:18:50 PM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
7/25/2019 12:16:43 PM
|
Submission Triaged
|
7/24/2019 4:21:48 PM
|
Submission received from Applicant
|
7/9/2019 9:21:20 AM
|
Submission request sent to Applicant
|
6/24/2019 4:45:01 PM
|
Request for Review Comments returned by EPC Health Department
|
6/17/2019 5:12:00 PM
|
Submission request sent to Applicant
|
6/17/2019 5:02:54 PM
|
Submission request sent to Applicant
|
6/17/2019 4:15:27 PM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
6/14/2019 6:08:19 PM
|
Request for Review Comments returned by PCD Engineering Division
|
6/13/2019 4:41:22 PM
|
Request for Review Comments returned by Parks Advisory Board
|
6/6/2019 4:45:42 PM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
6/5/2019 12:54:23 PM
|
Request for Review Comments returned by EPC Parks Department
|
6/4/2019 4:59:16 PM
|
Request for Review Comments returned by Colorado Geological Survey
|
6/3/2019 10:08:58 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
6/1/2019 11:44:08 AM
|
Request for Review Comments returned by PCD Project Manager
|
6/1/2019 9:52:15 AM
|
Request for Review Comments email sent for Project Saddlehorn (824 Acres), Final Plat for review by UDS Admin Staff on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
5/31/2019 2:27:17 PM
|
Request for Review Comments returned by Falcon Fire Protection District
|
5/30/2019 8:42:23 AM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
5/29/2019 9:34:29 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
5/29/2019 4:30:58 AM
|
Request for Review Comments email resent for Project 824 Acres, Final Plat for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
5/23/2019 2:28:00 PM
|
Request for Review Comments returned by EPC Environmental Services
|
5/16/2019 10:03:15 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
5/16/2019 10:02:38 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
5/15/2019 3:22:55 PM
|
Request for Review Comments returned by Central CO Conservation District
|
5/15/2019 3:21:06 PM
|
Request for Review Comments returned by Central CO Conservation District
|
5/15/2019 10:58:20 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
5/15/2019 10:57:35 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
5/15/2019 8:06:40 AM
|
Request for Review Comments returned by Schriever AFB
|
5/15/2019 8:05:24 AM
|
Request for Review Comments returned by Schriever AFB
|
5/14/2019 4:19:36 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Darren Horstmeier on behalf of Schriever AFB
|
5/14/2019 4:19:34 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
|
5/14/2019 4:19:31 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Dave Elliott on behalf of Meadow Lake Airport Association
|
5/14/2019 4:19:29 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Melissa Andrews on behalf of Falcon School District 49
|
5/14/2019 4:19:27 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Chief Trent Harwig on behalf of Falcon Fire Protection District
|
5/14/2019 4:19:25 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Pamela Davison on behalf of El Paso County Conservation Dist
|
5/14/2019 4:19:22 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Darren Horstmeier on behalf of Schriever AFB
|
5/14/2019 4:19:22 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Pamela Davidson on behalf of Central CO Conservation District
|
5/14/2019 4:19:20 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
5/14/2019 4:19:20 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
|
5/14/2019 4:19:18 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by RBD Enumerations & Floodplain on behalf of Pikes Peak Regional Building Department
|
5/14/2019 4:19:18 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Dave Elliott on behalf of Meadow Lake Airport Association
|
5/14/2019 4:19:16 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Melissa Andrews on behalf of Falcon School District 49
|
5/14/2019 4:19:16 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Larry Small on behalf of Fountain Creek Watershed Flood Control & Greenway Dist
|
5/14/2019 4:19:14 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
5/14/2019 4:19:14 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Chief Trent Harwig on behalf of Falcon Fire Protection District
|
5/14/2019 4:19:12 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Pamela Davison on behalf of El Paso County Conservation Dist
|
5/14/2019 4:19:12 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Christopher Grosso on behalf of US Army Corps of Engineers-Pueblo
|
5/14/2019 4:19:10 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Pamela Davidson on behalf of Central CO Conservation District
|
5/14/2019 4:19:10 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by John Bauer on behalf of Federal Aviation Administration (FAA)
|
5/14/2019 4:19:07 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
5/14/2019 4:19:07 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Larry Long on behalf of Colorado State Forest Service
|
5/14/2019 4:19:05 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by RBD Enumerations & Floodplain on behalf of Pikes Peak Regional Building Department
|
5/14/2019 4:19:04 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Energy and Land Use Specialist Karen Voltura on behalf of Colorado Parks and Wildlife
|
5/14/2019 4:19:02 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
5/14/2019 4:19:02 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Larry Small on behalf of Fountain Creek Watershed Flood Control & Greenway Dist
|
5/14/2019 4:19:00 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
5/14/2019 4:19:00 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
5/14/2019 4:18:58 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Christopher Grosso on behalf of US Army Corps of Engineers-Pueblo
|
5/14/2019 4:18:56 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Permits Manager Valerie Sword on behalf of Colorado Department of Transportation - Pueblo Office
|
5/14/2019 4:18:56 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by John Bauer on behalf of Federal Aviation Administration (FAA)
|
5/14/2019 4:18:53 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Larry Long on behalf of Colorado State Forest Service
|
5/14/2019 4:18:53 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by on behalf of Parks Advisory Board
|
5/14/2019 4:18:51 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Commander John Padgett on behalf of EPC Sheriff's Department
|
5/14/2019 4:18:51 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Energy and Land Use Specialist Karen Voltura on behalf of Colorado Parks and Wildlife
|
5/14/2019 4:18:49 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
5/14/2019 4:18:49 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
|
5/14/2019 4:18:47 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by on behalf of EPC Parks Department
|
5/14/2019 4:18:47 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
5/14/2019 4:18:43 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Permits Manager Valerie Sword on behalf of Colorado Department of Transportation - Pueblo Office
|
5/14/2019 4:18:41 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by on behalf of EPC Health Department
|
5/14/2019 4:18:41 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by on behalf of Parks Advisory Board
|
5/14/2019 4:18:39 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Commander John Padgett on behalf of EPC Sheriff's Department
|
5/14/2019 4:18:39 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Kathy Andrew on behalf of EPC Environmental Services
|
5/14/2019 4:18:37 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
|
5/14/2019 4:18:37 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Edi Anderson on behalf of EPC County Attorney's Office
|
5/14/2019 4:18:35 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Nina Ruiz on behalf of PCD Project Manager
|
5/14/2019 4:18:35 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by on behalf of EPC Parks Department
|
5/14/2019 4:18:33 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
5/14/2019 4:18:28 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by on behalf of EPC Health Department
|
5/14/2019 4:18:25 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Kathy Andrew on behalf of EPC Environmental Services
|
5/14/2019 4:18:23 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Edi Anderson on behalf of EPC County Attorney's Office
|
5/14/2019 4:18:21 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Nina Ruiz on behalf of PCD Project Manager
|
5/14/2019 4:18:19 PM
|
Request for Review Comments email sent for Project 824 Acres, Final Plat for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
5/14/2019 4:15:31 PM
|
Fees paid: 5/14/2019 (Receipt: 1001449)
|
5/7/2019 3:22:32 PM
|
Payment Request sent: 5/7/2019
|
5/7/2019 3:22:16 PM
|
File # Assigned: SF1912
|
5/6/2019 3:06:38 PM
|
Submission Triaged
|
5/6/2019 1:40:17 PM
|
Submission received from Applicant
|
5/6/2019 11:52:11 AM
|
Submission request sent to Applicant
|
5/6/2019 11:51:31 AM
|
Submission Triaged
|
4/30/2019 5:26:21 PM
|
Submission received from Applicant
|
1/28/2019 9:53:49 AM
|
Submission request sent to Applicant
|
11/28/2018 5:31:57 AM
|
Submission request sent to Applicant
|
11/28/2018 5:26:53 AM
|
Project Manager Assigned: Nina Ruiz
|
11/28/2018 5:26:53 AM
|
EA Assigned: EA18215
|
11/28/2018 5:26:53 AM
|
Project Created
|