Project Details

Search


File Number
PPR1853
Project Name
Falcon Landing
Description
PPR08022- Adding the incomplete engineering docs; however the site dev plan was approved - no changes are proposed
Parcels
4307202030 4307202030
Applicant
Dakota Springs Engineering
PA Koscielski ( dse.pak7@gmail.com )
(719) 377-0244
PA Koscielski ( dse.pak7@gmail.com )
(719) 377-0244
EA Number
EA18218
File Prefix
PPR - Plot Plan Review
Year
2018
Project Manager
Kari Parsons
Status
Closed
Created
7/30/2018 1:16:59 PM

View: Review Comments



Additional Documents (8)

Link Document Comment
View Approved Drainage Memo
View Approved FAE
View Grading & Erosion Control Plan Approved
View Accepted O & M
View Accepted SWMP
View SDP Approved added ADA Ramp
View Recorded Detention Maintenance Agreement
View Landscape Completion Agreement


Review Documents (25)

Link Document Date
View Application/Petition Form 9/27/2018 9:04:05 AM
View Legal Description (MS WORD Version required) 9/20/2018 11:21:04 AM
View Letter of Intent 1/30/2019 12:11:11 PM
View Title Commitment (Current within 30 days of submittal) 11/26/2018 10:11:06 AM
View Erosion and Stormwater Quality Control Permit (ESQCP) 9/27/2018 9:04:06 AM
View PDB/BMP Operations & Maintenance Manual 3/27/2019 9:21:23 AM
View Floor Plans (8.5" x 11") 2/13/2019 4:27:36 PM
View Grading & Erosion Control Plan (24 x 36) 2/13/2019 4:22:23 PM
View Landscape Plan drawings (24" x 36") 3/27/2019 9:21:15 AM
View Site Development Plan (24" x 36") 3/27/2019 9:21:21 AM
View Storm Water Management Plan (SWMP) 3/27/2019 9:21:19 AM
View Detention Maintenance Agreement (MS WORD version required - attachments included) 1/30/2019 3:40:04 PM
View Commitment letter from waste water service provider 9/21/2018 10:41:34 AM
View Commitment letter from water service provider 9/21/2018 10:41:33 AM
View Detention Maintenance Agreement (signed) 10/2/2018 11:52:38 AM
View Development Plan Comments [DSE Response] 3/14/2019 10:56:14 AM
View Drainage Letter 3/27/2019 9:21:03 AM
View Drainage Letter [DSE Response] 3/14/2019 10:58:31 AM
View Elevation Plans (24" x 36") 2/13/2019 4:22:21 PM
View Financial Assurance Comments [DSE Response] 3/7/2019 10:44:12 AM
View Financial Assurance Forms 3/27/2019 9:21:13 AM
View Fire Hydrant Service Plan Sheet 6 9/24/2018 11:30:23 AM
View Lighting Plan (24" x 36") 3/27/2019 9:21:17 AM
View O&M Manual [DSE Response] 3/14/2019 10:58:32 AM
View SWMP Comments [DSE Response] 3/7/2019 10:38:49 AM



Events (57)

Date Comment
10/21/2020 7:42:47 AM Project Closed
10/21/2020 7:42:47 AM Project Approved: 10/21/2020
7/28/2020 2:32:28 PM Submission request sent to Applicant
6/11/2020 10:09:18 AM Request for Review Comments returned by EPC Code Enforcement
5/28/2020 6:36:42 PM Project reopened for Review Comments
5/28/2020 7:04:08 AM Request for Review Comments email sent for Project Falcon Landing for review by Mindy Madden on behalf of EPC Code Enforcement
4/9/2019 2:05:24 PM Project Closed
4/9/2019 2:05:24 PM Project Approved: 4/9/2019
4/9/2019 2:00:32 PM Request for Review Comments returned by PCD Engineering Division
4/9/2019 10:31:10 AM Request for Review Comments returned by PCD Project Manager
3/28/2019 8:06:17 AM Request for Review Comments email sent for Project Falcon Landing for review by Kari Parsons on behalf of PCD Project Manager
3/28/2019 8:06:11 AM Request for Review Comments email sent for Project Falcon Landing for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
3/28/2019 8:05:24 AM Submission Triaged
3/27/2019 9:25:52 AM Submission received from Applicant
2/28/2019 2:23:24 PM Submission request sent to Applicant
2/28/2019 2:19:44 PM Request for Review Comments returned by PCD Project Manager
2/28/2019 11:15:47 AM Request for Review Comments returned by PCD Engineering Division
2/27/2019 2:04:49 PM Request for Review Comments returned by Pikes Peak Regional Building Department
2/25/2019 9:03:58 AM Request for Review Comments returned by 911 Authority - El Paso/Teller County
2/14/2019 7:20:31 AM Request for Review Comments email sent for Project Falcon Landing for review by RBD Enumerations & Floodplain on behalf of Pikes Peak Regional Building Department
2/14/2019 7:20:22 AM Request for Review Comments email sent for Project Falcon Landing for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
2/14/2019 7:20:18 AM Request for Review Comments email sent for Project Falcon Landing for review by Kari Parsons on behalf of PCD Project Manager
2/14/2019 7:20:05 AM Request for Review Comments email sent for Project Falcon Landing for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
2/14/2019 7:19:12 AM Submission Triaged
2/13/2019 4:31:59 PM Submission received from Applicant
12/31/2018 2:07:50 PM Request for Review Comments returned by Falcon Fire Protection District
12/27/2018 2:01:30 PM Request for Review Comments returned by US Postal Service
12/19/2018 4:25:12 PM Request for Review Comments returned by Woodmen Hills Metro
12/18/2018 2:43:03 PM Submission request sent to Applicant
12/18/2018 2:39:21 PM Request for Review Comments returned by PCD Project Manager
12/18/2018 10:11:54 AM Request for Review Comments returned by PCD Engineering Division
12/18/2018 8:52:17 AM Request for Review Comments returned by Pikes Peak Regional Building Department
12/7/2018 2:18:11 PM Request for Review Comments returned by 911 Authority - El Paso/Teller County
12/5/2018 3:33:35 PM Request for Review Comments returned by Woodmen Road Metro
12/5/2018 11:57:34 AM Request for Review Comments email sent for Project Falcon Landing for review by Autumn Mason on behalf of Woodmen Road Metro
12/5/2018 11:57:32 AM Request for Review Comments email sent for Project Falcon Landing for review by Jerry Jacobson on behalf of Woodmen Hills Metro
12/5/2018 11:57:30 AM Request for Review Comments email sent for Project Falcon Landing for review by Chief Trent Harwig on behalf of Falcon Fire Protection District
12/5/2018 11:57:28 AM Request for Review Comments email sent for Project Falcon Landing for review by Melissa Andrews on behalf of Falcon 49
12/5/2018 11:57:26 AM Request for Review Comments email sent for Project Falcon Landing for review by Joe Valdez on behalf of Black Hills Energy-Aquila
12/5/2018 11:57:23 AM Request for Review Comments email sent for Project Falcon Landing for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
12/5/2018 11:57:21 AM Request for Review Comments email sent for Project Falcon Landing for review by RBD Enumerations & Floodplain on behalf of Pikes Peak Regional Building Department
12/5/2018 11:57:19 AM Request for Review Comments email sent for Project Falcon Landing for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
12/5/2018 11:57:17 AM Request for Review Comments email sent for Project Falcon Landing for review by Elaine Kelly on behalf of US Postal Service
12/5/2018 11:57:15 AM Request for Review Comments email sent for Project Falcon Landing for review by Kari Parsons on behalf of PCD Project Manager
12/5/2018 11:57:13 AM Request for Review Comments email sent for Project Falcon Landing for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
12/5/2018 11:55:17 AM Fees paid: 12/5/2018 (Receipt: 1001124)
11/26/2018 2:34:15 PM Payment Request sent: 11/26/2018
11/26/2018 2:34:15 PM File # Assigned: PPR1853
11/26/2018 2:34:06 PM Submission Triaged
11/26/2018 10:11:26 AM Submission received from Applicant
11/21/2018 7:13:27 AM Submission request sent to Applicant
11/21/2018 7:13:17 AM Submission Triaged
11/19/2018 2:57:18 PM Submission received from Applicant
7/30/2018 1:29:31 PM Submission request sent to Applicant
7/30/2018 1:17:07 PM Project Manager Assigned: Kari Parsons
7/30/2018 1:17:07 PM EA Assigned: EA18218
7/30/2018 1:17:07 PM Project Created