Project Details

Search


File Number
SF1825
Project Name
Mayberry Filing No 1 (Ellicott Town Center Final Plat Extension Review)
Description
Review associated engineering drawings and reaffirm water finding associated with an extension of a final plat (SF-06-012)
Parcels
3400000259 3400000259 3400000260 3400000260 3400000345 3400000345 3400000346 3400000346
Applicant
JPS Engineering, Inc.
John Schwab ( john@jpsengr.com )
(719) 477-9429
John Schwab ( john@jpsengr.com )
(719) 477-9429
File Prefix
SF - Final Plat
Year
2018
Project Manager
Nina Ruiz
Status
Closed
Created
6/18/2018 9:41:25 AM

View: Review Comments


Approved Documents (11)

Link Document
View Construction Drawings (Plans/ Profiles)
View Grading & Erosion Control Plan (24 x 36)
View Drainage Report - Final
View Deviation Requests
View FAE
View GEC Checklist
View O&M Manuals
View PBMP Form
View SDI Form
View SWMP
View SWMP Checklist


Additional Documents (9)

Link Document Comment
View Recorded Plat
View Recorded Maintenance Agreement
View Recorded Subdivision Improvement Agreement
View Recorded Affidavit of Modification
View SF 1825 Mayberry Filing 1A - Revised partial pavement approved
View Recorded Warranty Deed
View Certificate AD Valorem Property Taxes
View Land Title - Order # SC55072532.2.2
View Mayberry_Tract 'O' Borrow_GEC_Signed (1-27-22)


Review Documents (52)

Link Document Date
View Application/Petition Form 9/4/2018 10:30:11 AM
View Letter of Intent 1/25/2019 2:28:47 PM
View Title Commitment (Current within 30 days of submittal) 9/4/2018 10:30:13 AM
View Vicinity/Location Map 8/28/2018 4:08:28 PM
View Erosion and Stormwater Quality Control Permit (ESQCP) 10/28/2020 12:28:02 AM
View Construction Drawings (Plans/ Profiles) 10/28/2020 12:19:38 AM
View Final Plat Drawings (24" x 36") 11/25/2020 12:59:56 AM
View Grading & Erosion Control Plan (24 x 36) 10/28/2020 12:19:42 AM
View Electric Provider Commitment Letter 8/28/2018 4:08:22 PM
View Drainage Report - Final 10/28/2020 12:19:40 AM
View Subdivision Summary Sheet 8/28/2018 4:08:27 PM
View Wastewater Treatment Report 8/28/2018 4:08:28 PM
View Detention Maintenance Agreement (MS WORD version required - attachments included) 12/7/2020 4:40:24 PM
View Water Resources Report 8/28/2018 4:08:29 PM
View Water Supply Information Summary 12/17/2020 9:39:32 AM
View Closure Sheets 1/25/2019 2:28:49 PM
View Comment Response Letter 9/18/2019 2:07:20 PM
View Comment Response Letter 1/25/2019 2:28:48 PM
View Comment Response Letter 4/30/2020 1:23:10 PM
View Comment Response Letter 10/9/2020 4:36:05 PM
View Commitment letter from waste water service provider 8/28/2018 4:08:21 PM
View Commitment letter from water service provider 12/1/2020 9:31:28 AM
View Deviation Request Letter 10/28/2020 12:28:03 AM
View Deviation Requests 1/31/2020 5:47:37 PM
View Deviation Requests 10/28/2020 12:28:06 AM
View ESQCP 10/9/2020 4:36:05 PM
View ESQCP Application Form 1/31/2020 2:19:11 PM
View FAE 1/31/2020 2:17:48 PM
View FAE 10/28/2020 12:28:06 AM
View Financial Assurance Forms 10/28/2020 12:19:40 AM
View GEC Checklist 4/24/2020 5:08:20 PM
View Geotechnical Report 1/25/2019 2:33:21 PM
View LSC response to EPC Redlines 9/30/2019 1:49:29 PM
View LSC responses to CDOT traffic comments 9/30/2019 1:49:28 PM
View MS4 Forms 1/31/2020 5:47:39 PM
View Noise Study 1/25/2019 2:28:51 PM
View O&M Manual for Detention Ponds 9/18/2019 2:07:23 PM
View O&M Manuals 1/31/2020 2:17:49 PM
View PBMP Form 1/31/2020 2:17:48 PM
View PBMP Form 1/31/2020 2:06:56 PM
View PDB-BMP Agreement 10/29/2020 10:45:13 PM
View Response to CDOT Comments 9/30/2019 1:49:27 PM
View SDI Form 9/18/2019 2:07:27 PM
View SDI Worksheets 1/31/2020 5:47:39 PM
View SEO Water Review Message 12/1/2020 9:39:22 AM
View Subdivision Improvement Agreement 11/25/2020 12:59:57 AM
View SWMP 9/23/2020 8:02:54 PM
View SWMP Checklist 9/23/2020 8:02:56 PM
View Traffic Report Update 10/28/2020 12:28:04 AM
View Water & Wastewater Commitment Letters 11/25/2020 12:59:58 AM
View Water Resources & Wastewater Report 11/25/2020 12:59:57 AM
View Water Supply Information Summary 12/1/2020 9:31:29 AM



Events (156)

Date Comment
5/13/2022 9:29:14 AM Project Closed
5/13/2022 9:29:14 AM Project Approved: 5/13/2022
12/17/2020 12:11:49 PM Submission Triaged
12/17/2020 9:41:05 AM Submission received from Applicant
12/17/2020 6:29:53 AM Submission request sent to Applicant
12/16/2020 3:40:00 PM Request for Review Comments returned by County Attorney - Development Review
12/7/2020 5:30:20 PM Submission Triaged
12/7/2020 4:41:44 PM Submission received from Applicant
12/7/2020 5:22:10 AM Submission request sent to Applicant
12/7/2020 5:21:27 AM Request for Review Comments returned by PCD Project Manager
12/6/2020 3:33:17 PM Request for Review Comments returned by PCD Engineering Division
12/2/2020 11:06:39 AM Request for Review Comments returned by EPC County Attorney's Office
12/1/2020 9:29:57 PM Submission Triaged
12/1/2020 9:39:38 AM Submission received from Applicant
12/1/2020 9:26:32 AM Request for Review Comments email resent for Project Ellicott Town Center Final Plat Extension Review for review by Edi Anderson on behalf of EPC County Attorney's Office
12/1/2020 5:22:49 AM Submission request sent to Applicant
11/30/2020 3:19:04 PM Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
11/30/2020 8:34:39 AM Request for Review Comments returned by EPC County Attorney's Office
11/25/2020 5:38:02 AM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Lori Seago on behalf of County Attorney - Development Review
11/25/2020 5:38:00 AM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Nina Ruiz on behalf of PCD Project Manager
11/25/2020 5:37:56 AM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
11/25/2020 5:35:12 AM Submission Triaged
11/25/2020 1:11:38 AM Submission received from Applicant
11/23/2020 10:58:08 AM Submission request sent to Applicant
11/20/2020 6:27:25 AM Submission request sent to Applicant
11/18/2020 10:16:07 PM Request for Review Comments returned by County Attorney - Development Review
11/6/2020 6:48:13 AM Request for Review Comments email resent for Project Ellicott Town Center Final Plat Extension Review for review by Lori Seago on behalf of County Attorney - Development Review
11/5/2020 8:20:08 PM Request for Review Comments returned by County Attorney - Development Review
11/4/2020 4:56:39 PM Request for Review Comments returned by PCD Engineering Division
11/4/2020 5:34:11 AM Request for Review Comments returned by PCD Project Manager
11/2/2020 5:23:35 PM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Lori Seago on behalf of County Attorney - Development Review
11/2/2020 5:22:37 PM Submission Triaged
10/29/2020 10:45:24 PM Submission received from Applicant
10/28/2020 12:36:10 PM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Edi Anderson on behalf of EPC County Attorney's Office
10/28/2020 6:25:31 AM Submission request sent to Applicant
10/28/2020 6:24:59 AM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
10/28/2020 6:20:31 AM Submission Triaged
10/28/2020 12:29:15 AM Submission received from Applicant
10/26/2020 8:44:22 PM Request for Review Comments returned by County Attorney - Development Review
10/20/2020 7:23:37 AM Submission request sent to Applicant
10/19/2020 3:02:24 PM Request for Review Comments returned by PCD Engineering Division
10/13/2020 5:48:10 AM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
10/13/2020 5:48:08 AM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Lori Seago on behalf of County Attorney - Development Review
10/13/2020 5:48:06 AM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Nina Ruiz on behalf of PCD Project Manager
10/13/2020 5:46:23 AM Submission Triaged
10/9/2020 4:36:23 PM Submission received from Applicant
9/28/2020 4:47:27 PM Submission request sent to Applicant
9/24/2020 3:44:39 PM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Permits Manager Valerie Sword on behalf of Colorado Department of Transportation - Pueblo Office
9/24/2020 3:44:27 PM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
9/24/2020 3:43:48 PM Submission Triaged
9/24/2020 11:17:20 AM Submission received from Applicant
6/2/2020 11:33:14 AM Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
6/1/2020 11:49:51 AM Request for Review Comments returned by County Attorney - Development Review
5/27/2020 10:03:16 PM Submission request sent to Applicant
5/26/2020 5:15:04 PM Request for Review Comments returned by PCD Engineering Division
5/26/2020 7:47:30 AM Request for Review Comments returned by PCD Project Manager
5/4/2020 3:25:10 PM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Permits Manager Valerie Sword on behalf of Colorado Department of Transportation - Pueblo Office
5/4/2020 3:25:09 PM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Lori Seago on behalf of County Attorney - Development Review
5/4/2020 3:25:08 PM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Nina Ruiz on behalf of PCD Project Manager
5/4/2020 3:25:05 PM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
5/4/2020 3:19:58 PM Submission Triaged
4/30/2020 5:07:00 PM Submission received from Applicant
3/16/2020 4:15:43 PM Request for Review Comments returned by Colorado Division of Water Resources
3/11/2020 7:42:32 AM Submission request sent to Applicant
3/4/2020 6:31:32 PM Request for Review Comments returned by PCD Engineering Division
2/26/2020 1:51:47 PM Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
2/25/2020 10:09:34 AM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
2/24/2020 9:50:55 AM Request for Review Comments returned by Pikes Peak Regional Building Department
2/14/2020 11:53:39 AM Request for Review Comments returned by EPC County Attorney's Office
2/12/2020 3:10:43 PM Request for Review Comments returned by PCD Project Manager
2/12/2020 3:10:09 PM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Joanna Williams on behalf of Colorado Division of Water Resources
2/12/2020 3:04:03 PM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Edi Anderson on behalf of EPC County Attorney's Office
2/12/2020 3:03:21 PM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
2/6/2020 1:14:34 PM Request for Review Comments returned by EPC County Attorney's Office
2/4/2020 12:43:40 PM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by RBD Enumerations & Floodplain on behalf of Pikes Peak Regional Building Department
2/4/2020 12:43:39 PM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Permits Manager Valerie Sword on behalf of Colorado Department of Transportation - Pueblo Office
2/4/2020 12:43:36 PM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Edi Anderson on behalf of EPC County Attorney's Office
2/4/2020 12:43:33 PM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Nina Ruiz on behalf of PCD Project Manager
2/4/2020 12:43:25 PM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
2/4/2020 12:42:14 PM Submission Triaged
1/31/2020 5:50:07 PM Submission received from Applicant
1/23/2020 4:49:21 PM Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
12/4/2019 6:50:04 PM Request for Review Comments returned by EPC Health Department
10/21/2019 8:42:41 AM Submission request sent to Applicant
10/20/2019 5:20:53 PM Request for Review Comments returned by PCD Engineering Division
10/15/2019 11:40:06 AM Request for Review Comments returned by PCD Project Manager
10/11/2019 12:11:42 PM Request for Review Comments returned by EPC County Attorney's Office
10/10/2019 9:26:38 AM Request for Review Comments returned by Pikes Peak Regional Building Department
10/9/2019 10:01:12 AM Request for Review Comments returned by Parks Advisory Board
10/2/2019 2:21:26 PM Submission Triaged
9/30/2019 2:48:38 PM Submission received from Applicant
9/30/2019 1:23:31 PM Submission request sent to Applicant
9/19/2019 12:03:48 PM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by RBD Enumerations & Floodplain on behalf of Pikes Peak Regional Building Department
9/19/2019 12:03:47 PM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Permits Manager Valerie Sword on behalf of Colorado Department of Transportation - Pueblo Office
9/19/2019 12:03:46 PM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by on behalf of Parks Advisory Board
9/19/2019 12:03:42 PM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by on behalf of EPC Health Department
9/19/2019 12:03:40 PM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Edi Anderson on behalf of EPC County Attorney's Office
9/19/2019 12:03:39 PM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Nina Ruiz on behalf of PCD Project Manager
9/19/2019 12:03:37 PM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
9/19/2019 12:02:47 PM Submission Triaged
9/18/2019 2:07:49 PM Submission received from Applicant
9/18/2019 1:39:36 PM Submission request sent to Applicant
9/18/2019 1:38:57 PM Submission Triaged
9/16/2019 5:05:38 PM Submission received from Applicant
6/20/2019 2:19:07 PM Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
2/27/2019 7:47:25 AM Submission request sent to Applicant
2/27/2019 7:46:09 AM Request for Review Comments returned by PCD Project Manager
2/25/2019 9:53:40 AM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Permits Manager Valerie Sword on behalf of Colorado Department of Transportation - Pueblo Office
2/22/2019 3:34:13 PM Request for Review Comments returned by PCD Engineering Division
2/21/2019 1:42:26 PM Request for Review Comments returned by Colorado Division of Water Resources
2/12/2019 9:26:44 AM Request for Review Comments returned by Pikes Peak Regional Building Department
1/28/2019 3:58:26 PM Submission Triaged
1/25/2019 2:33:55 PM Submission received from Applicant
1/25/2019 1:39:09 PM Request for Review Comments returned by EPC Parks Department
1/23/2019 5:28:33 PM Submission request sent to Applicant
1/23/2019 1:33:40 PM Request for Review Comments returned by EPC County Attorney's Office
1/22/2019 4:33:54 PM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by RBD Enumerations & Floodplain on behalf of Pikes Peak Regional Building Department
1/22/2019 4:33:52 PM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Neelha Mudigonda on behalf of Colorado Division of Water Resources
1/22/2019 4:33:50 PM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by on behalf of EPC Parks Department
1/22/2019 4:33:46 PM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Edi Anderson on behalf of EPC County Attorney's Office
1/22/2019 4:33:44 PM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Nina Ruiz on behalf of PCD Project Manager
1/22/2019 4:33:38 PM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
1/22/2019 4:33:02 PM Submission Triaged
1/21/2019 3:51:52 PM Submission received from Applicant
11/19/2018 3:22:21 PM Request for Review Comments returned by Parks Advisory Board
11/15/2018 5:59:03 AM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Ross Williams on behalf of Parks Advisory Board
11/8/2018 11:29:14 AM Request for Review Comments returned by Colorado Division of Water Resources
10/24/2018 3:32:06 PM Request for Review Comments returned by EPC Parks Department
10/10/2018 10:54:03 AM Request for Review Comments returned by EPC Health Department
10/9/2018 9:44:02 AM Submission request sent to Applicant
10/9/2018 9:42:21 AM Request for Review Comments returned by PCD Project Manager
10/9/2018 9:35:40 AM Request for Review Comments email resent for Project Ellicott Town Center Final Plat Extension Review for review by Nina Ruiz on behalf of PCD Project Manager
10/5/2018 10:31:33 AM Request for Review Comments returned by PCD Engineering Division
10/3/2018 1:01:49 PM Request for Review Comments returned by EPC County Attorney's Office
10/1/2018 12:51:26 PM Request for Review Comments returned by PCD Project Manager
10/1/2018 9:26:52 AM Request for Review Comments returned by Pikes Peak Regional Building Department
9/11/2018 5:54:49 AM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by RBD Enumerations & Floodplain on behalf of Pikes Peak Regional Building Department
9/11/2018 5:54:48 AM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Joanna Williams on behalf of Colorado Division of Water Resources
9/11/2018 5:54:47 AM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by on behalf of EPC Parks Department
9/11/2018 5:54:45 AM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by on behalf of EPC Health Department
9/11/2018 5:54:44 AM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Edi Anderson on behalf of EPC County Attorney's Office
9/11/2018 5:54:43 AM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Nina Ruiz on behalf of PCD Project Manager
9/11/2018 5:54:42 AM Request for Review Comments email sent for Project Ellicott Town Center Final Plat Extension Review for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
9/10/2018 9:35:36 AM Fees paid: 9/10/2018 (Receipt: 1000951)
9/5/2018 5:27:17 PM Payment Request sent: 9/5/2018
9/5/2018 5:27:06 PM File # Assigned: SF1825
9/5/2018 9:53:38 AM Submission Triaged
9/4/2018 10:30:58 AM Submission received from Applicant
8/29/2018 11:19:03 AM Submission request sent to Applicant
8/29/2018 11:18:14 AM Submission request canceled
8/29/2018 10:54:09 AM Submission request sent to Applicant
8/29/2018 10:53:46 AM Submission Triaged
8/28/2018 4:08:58 PM Submission received from Applicant
6/18/2018 9:47:14 AM Submission request sent to Applicant
6/18/2018 9:41:46 AM Project Manager Assigned: Nina Ruiz
6/18/2018 9:41:46 AM Project Created