10/5/2021 7:42:57 PM
|
Project Closed
|
10/5/2021 7:42:56 PM
|
Project Cancelled: 10/5/2021
|
9/22/2021 8:41:59 PM
|
Request for Review Comments returned by PCD Project Manager
|
8/12/2021 11:53:39 AM
|
Request for Review Comments email sent for Project 4-WAY LIFT STATION for review by Nina Ruiz on behalf of PCD Project Manager
|
4/1/2020 12:28:25 PM
|
Request for Review Comments returned by Falcon Fire Protection District
|
2/21/2020 1:01:56 PM
|
Request for Review Comments returned by Colorado Department of Public Health and Environment
|
1/30/2020 4:05:54 PM
|
Request for Review Comments returned by EPC Health Department
|
12/26/2019 5:14:49 PM
|
Submission request sent to Applicant
|
12/26/2019 5:12:39 PM
|
Request for Review Comments returned by PCD Project Manager
|
12/26/2019 5:05:57 PM
|
Request for Review Comments email resent for Project 4-WAY LIFT STATION for review by Nina Ruiz on behalf of PCD Project Manager
|
12/19/2019 3:12:22 PM
|
Request for Review Comments returned by PCD Engineering Division
|
12/12/2019 1:30:02 PM
|
Request for Review Comments returned by PCD Project Manager
|
12/11/2019 9:56:16 AM
|
Request for Review Comments returned by RBD Floodplain
|
12/10/2019 4:51:56 PM
|
Request for Review Comments email sent for Project 4-WAY LIFT STATION for review by Keith Curtis on behalf of RBD Floodplain
|
12/10/2019 10:34:21 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
12/9/2019 5:07:17 PM
|
Project reopened for Review Comments
|
12/4/2019 1:31:40 PM
|
Request for Review Comments returned by Woodmen Hills Metro
|
11/26/2019 10:40:35 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
11/20/2019 8:25:36 AM
|
Request for Review Comments email sent for Project 4-WAY LIFT STATION for review by Jerry Jacobson on behalf of Woodmen Hills Metro
|
11/20/2019 8:25:35 AM
|
Request for Review Comments email sent for Project 4-WAY LIFT STATION for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
|
11/20/2019 8:25:34 AM
|
Request for Review Comments email sent for Project 4-WAY LIFT STATION for review by Chief Trent Harwig on behalf of Falcon Fire Protection District
|
11/20/2019 8:25:33 AM
|
Request for Review Comments email sent for Project 4-WAY LIFT STATION for review by RBD Enumerations & Floodplain on behalf of Pikes Peak Regional Building Department
|
11/20/2019 8:25:29 AM
|
Request for Review Comments email sent for Project 4-WAY LIFT STATION for review by on behalf of EPC Health Department
|
11/20/2019 8:25:28 AM
|
Request for Review Comments email sent for Project 4-WAY LIFT STATION for review by Nina Ruiz on behalf of PCD Project Manager
|
11/20/2019 8:25:27 AM
|
Request for Review Comments email sent for Project 4-WAY LIFT STATION for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
11/20/2019 8:23:36 AM
|
Submission Triaged
|
11/14/2019 1:53:04 PM
|
Submission received from Applicant
|
12/31/2018 2:46:04 PM
|
Request for Review Comments returned by Falcon Fire Protection District
|
12/19/2018 5:37:33 PM
|
Submission request sent to Applicant
|
12/19/2018 5:36:12 PM
|
Request for Review Comments returned by PCD Project Manager
|
12/14/2018 4:01:07 PM
|
Request for Review Comments returned by Woodmen Hills Metro
|
12/14/2018 10:15:39 AM
|
Request for Review Comments returned by EPC Health Department
|
12/13/2018 1:00:50 PM
|
Request for Review Comments returned by PCD Engineering Division
|
12/6/2018 4:17:05 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
12/3/2018 4:37:45 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
11/29/2018 1:13:51 PM
|
Request for Review Comments email sent for Project 4-WAY LIFT STATION for review by Jerry Jacobson on behalf of Woodmen Hills Metro
|
11/29/2018 1:13:48 PM
|
Request for Review Comments email sent for Project 4-WAY LIFT STATION for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
|
11/29/2018 1:13:44 PM
|
Request for Review Comments email sent for Project 4-WAY LIFT STATION for review by Chief Trent Harwig on behalf of Falcon Fire Protection District
|
11/29/2018 1:13:41 PM
|
Request for Review Comments email sent for Project 4-WAY LIFT STATION for review by RBD Enumerations & Floodplain on behalf of Pikes Peak Regional Building Department
|
11/29/2018 1:13:37 PM
|
Request for Review Comments email sent for Project 4-WAY LIFT STATION for review by Jill Parisi on behalf of Colorado Department of Public Health and Environment
|
11/29/2018 1:13:27 PM
|
Request for Review Comments email sent for Project 4-WAY LIFT STATION for review by on behalf of EPC Health Department
|
11/29/2018 1:13:23 PM
|
Request for Review Comments email sent for Project 4-WAY LIFT STATION for review by Nina Ruiz on behalf of PCD Project Manager
|
11/29/2018 1:13:20 PM
|
Request for Review Comments email sent for Project 4-WAY LIFT STATION for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
11/29/2018 1:12:33 PM
|
Fees paid: 11/29/2018 (Receipt: 1001116)
|
11/7/2018 4:16:36 PM
|
File # Assigned: PPR1851
|
11/7/2018 7:39:33 AM
|
Submission Triaged
|
11/6/2018 7:18:10 AM
|
Submission received from Applicant
|
11/5/2018 2:03:39 PM
|
Submission request sent to Applicant
|
11/5/2018 2:01:27 PM
|
Project Manager Assigned: Nina Ruiz
|
10/31/2018 1:11:56 PM
|
Submission Triaged
|
10/30/2018 5:32:02 PM
|
Submission received from Applicant
|
6/20/2018 9:46:57 AM
|
Project reopened for Approval requests
|
6/20/2018 9:45:52 AM
|
Payment Request sent: 6/20/2018
|
6/20/2018 9:45:52 AM
|
Project Ready for Approval, pending fees: 6/20/2018
|
6/20/2018 9:45:24 AM
|
Project Manager Assigned: Raimere Fitzpatrick
|
6/20/2018 9:44:49 AM
|
Project Manager Assigned: Kari Parsons
|
3/21/2018 3:41:08 PM
|
Submission request sent to Applicant
|
3/21/2018 1:14:48 PM
|
Project Manager Assigned: Raimere Fitzpatrick
|
3/21/2018 1:14:48 PM
|
EA Assigned: EA18114
|
3/21/2018 1:14:48 PM
|
Project Created
|