Project Details

Search


File Number
PPR1817
Project Name
Mountain Splendor Contractor Equipment Yard Site Plan
Description
Site development plan for a contractor's equipment yard
Location
7205 Maine Lane
Parcels
5308000048 5308000048
Applicant
Mountain Splendor Services Inc
Tamara Baxter ( tbaxter@nescolorado.com )
(719) 471-0073
Tamara Baxter ( tbaxter@nescolorado.com )
(719) 471-0073
EA Number
EA-17-106
File Prefix
PPR - Plot Plan Review
Year
2018
Project Manager
Gabe Sevigny
Status
Closed
Created
3/2/2018 11:46:25 AM

View: Review Comments



Additional Documents (2)

Link Document Comment
View approved drainage report
View Approved Application Packet


Review Documents (21)

Link Document Date
View Application/Petition Form 4/12/2018 9:32:32 AM
View Legal Description (MS WORD Version required) 4/12/2018 9:32:35 AM
View Letter of Intent 9/4/2018 1:24:16 PM
View Title Commitment (Current within 30 days of submittal) 4/12/2018 9:32:38 AM
View Vicinity/Location Map 4/12/2018 9:32:39 AM
View Applicant Comment Response Letter 9/4/2018 1:24:20 PM
View Driveway Permit 4/12/2018 9:32:41 AM
View Erosion and Stormwater Quality Control Permit (ESQCP) 4/12/2018 9:32:38 AM
View Grading & Erosion Control Plan (24 x 36) 4/12/2018 9:32:34 AM
View Landscape Plan drawings (24" x 36") 9/4/2018 1:24:16 PM
View Sign Plan 9/4/2018 1:24:17 PM
View Site Development Plan (24" x 36") 9/4/2018 1:24:19 PM
View Drainage Report - Final 9/4/2018 1:24:14 PM
View Wastewater Disposal Report 9/4/2018 1:24:18 PM
View Well Permits (if water source is wells) 9/4/2018 1:24:18 PM
View ADA Route 9/4/2018 1:26:46 PM
View California Lane 9/4/2018 1:26:46 PM
View Drivway Permit Waiver 9/4/2018 1:26:47 PM
View Elevation Plans (24" x 36") 9/4/2018 1:24:12 PM
View Floor Plans (24" x 36") 9/4/2018 1:24:15 PM
View Lighting Plan (24" x 36") 4/12/2018 9:32:36 AM



Events (45)

Date Comment
9/28/2018 12:00:00 AM Project Closed
9/27/2018 4:11:06 PM Project Approved: 9/27/2018
9/26/2018 12:44:59 PM Project Ready for Approval requests. Review Comment period is complete.
9/26/2018 12:44:03 PM Request for Review Comments returned by PCD Project Manager
9/24/2018 7:55:07 AM Request for Review Comments returned by Pikes Peak Regional Building Department
9/13/2018 5:08:40 PM Request for Review Comments returned by PCD Engineering Division
9/10/2018 10:58:06 AM Request for Review Comments returned by Colorado Springs Planning & Community Development
9/4/2018 1:50:53 PM Request for Review Comments email sent for Project Mountain Splendor Contractor Equipment Yard Site Plan for review by Garrett Markus on behalf of Southeastern Colorado Water Conservancy
9/4/2018 1:50:52 PM Request for Review Comments email sent for Project Mountain Splendor Contractor Equipment Yard Site Plan for review by Carl Schueler on behalf of Colorado Springs Planning & Community Development
9/4/2018 1:50:49 PM Request for Review Comments email sent for Project Mountain Splendor Contractor Equipment Yard Site Plan for review by RBD Enumerations & Floodplain on behalf of Pikes Peak Regional Building Department
9/4/2018 1:50:46 PM Request for Review Comments email sent for Project Mountain Splendor Contractor Equipment Yard Site Plan for review by on behalf of EPC Health Department
9/4/2018 1:50:44 PM Request for Review Comments email sent for Project Mountain Splendor Contractor Equipment Yard Site Plan for review by Gabe Sevigny on behalf of PCD Project Manager
9/4/2018 1:50:43 PM Request for Review Comments email sent for Project Mountain Splendor Contractor Equipment Yard Site Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
9/4/2018 1:33:47 PM Submission Triaged
9/4/2018 1:27:16 PM Submission received from Applicant
8/24/2018 8:57:00 AM Submission request sent to Applicant
5/18/2018 3:30:28 PM Request for Review Comments returned by Falcon Fire Protection District
5/7/2018 11:47:24 AM Submission request sent to Applicant
5/7/2018 11:43:59 AM Request for Review Comments returned by PCD Project Manager
5/7/2018 10:25:17 AM Request for Review Comments returned by PCD Engineering Division
5/4/2018 10:41:55 AM Request for Review Comments returned by Pikes Peak Regional Building Department
5/1/2018 12:00:33 PM Request for Review Comments returned by El Paso County Conservation Dist
4/30/2018 8:51:49 AM Request for Review Comments returned by EPC Health Department
4/25/2018 7:52:15 AM Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
4/17/2018 2:16:59 PM Request for Review Comments returned by Mountain View Electric Association, Inc.
4/13/2018 1:49:21 PM Request for Review Comments email sent for Project Mountain Splendor Contractor Equipment Yard Site Plan for review by Garrett Markus on behalf of Southeastern Colorado Water Conservancy
4/13/2018 1:49:20 PM Request for Review Comments email sent for Project Mountain Splendor Contractor Equipment Yard Site Plan for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
4/13/2018 1:49:19 PM Request for Review Comments email sent for Project Mountain Splendor Contractor Equipment Yard Site Plan for review by Chief Trent Harwig on behalf of Falcon Fire Protection District
4/13/2018 1:49:18 PM Request for Review Comments email sent for Project Mountain Splendor Contractor Equipment Yard Site Plan for review by Pamela Davidson on behalf of El Paso County Conservation Dist
4/13/2018 1:49:17 PM Request for Review Comments email sent for Project Mountain Splendor Contractor Equipment Yard Site Plan for review by UDS Admin Staff on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
4/13/2018 1:49:16 PM Request for Review Comments email sent for Project Mountain Splendor Contractor Equipment Yard Site Plan for review by Carl Schueler on behalf of Colorado Springs Planning & Community Development
4/13/2018 1:49:15 PM Request for Review Comments email sent for Project Mountain Splendor Contractor Equipment Yard Site Plan for review by RBD Enumerations & Floodplain on behalf of Pikes Peak Regional Building Department
4/13/2018 1:49:13 PM Request for Review Comments email sent for Project Mountain Splendor Contractor Equipment Yard Site Plan for review by on behalf of EPC Health Department
4/13/2018 1:49:12 PM Request for Review Comments email sent for Project Mountain Splendor Contractor Equipment Yard Site Plan for review by Gabe Sevigny on behalf of PCD Project Manager
4/13/2018 1:49:11 PM Request for Review Comments email sent for Project Mountain Splendor Contractor Equipment Yard Site Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
4/13/2018 1:47:30 PM Fees paid: 4/13/2018 (Receipt: 1000614)
4/12/2018 3:32:02 PM Payment Request sent: 4/12/2018
4/12/2018 3:31:39 PM File # Assigned: PPR1817
4/12/2018 3:26:44 PM Submission Triaged
4/12/2018 9:33:10 AM Submission received from Applicant
3/7/2018 2:57:20 PM Submission request sent to Applicant
3/2/2018 3:21:44 PM Submission request sent to Applicant
3/2/2018 11:46:35 AM Project Manager Assigned: Gabe Sevigny
3/2/2018 11:46:35 AM EA Assigned: EA-17-106
3/2/2018 11:46:35 AM Project Created