File Number
PPR1824
Project Name
Rice Ranch Site Development Plan
Description
Site Development to legalize uses
Location
8150 Rice Lane
Parcels
6525000009 6525000009 6525000011 6525000011 6525000021 6525000021
Applicant
Ridgeline Land Surveying
Jim Lenz ( Jlenz@ridgeline-survey.com )
(719) 238-2917
Jim Lenz ( Jlenz@ridgeline-survey.com )
(719) 238-2917
EA Number
EA-17-089
File Prefix
PPR - Plot Plan Review
Year
2018
Project Manager
Nina Ruiz
Status
Closed
Created
2/20/2018 2:20:17 PM

View: Review Comments



Additional Documents (1)

Link Document Comment
View Recorded Maintenance Agreement and Easement


Review Documents (3)

Link Document Date
View Comment Letter 10/8/2018 6:11:02 PM
View Comment Letter 11/26/2018 6:02:25 PM
View Drainage Report 5/9/2019 6:26:52 AM



Events (101)

Date Comment
8/19/2019 4:03:19 PM Project Closed
8/19/2019 4:03:19 PM Project Approved: 8/19/2019
8/19/2019 4:02:57 PM Request for Review Comments returned by PCD Project Manager
8/15/2019 4:08:06 PM Request for Review Comments returned by PCD Engineering Division
8/13/2019 12:50:59 PM Request for Review Comments returned by EPC Code Enforcement
8/13/2019 7:58:11 AM Request for Review Comments email sent for Project Rice Ranch Site Development Plan for review by Nina Ruiz on behalf of PCD Project Manager
8/13/2019 7:58:09 AM Request for Review Comments email sent for Project Rice Ranch Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
7/29/2019 1:06:31 PM Submission Triaged
7/26/2019 8:48:04 AM Submission received from Applicant
7/1/2019 7:11:22 AM Request for Review Comments returned by PCD Project Manager
7/1/2019 5:25:12 AM Submission request sent to Applicant
6/28/2019 2:17:48 PM Request for Review Comments returned by PCD Engineering Division
6/22/2019 6:43:09 AM Request for Review Comments email sent for Project Rice Ranch Site Development Plan for review by Mindy Madden on behalf of EPC Code Enforcement
6/22/2019 6:43:06 AM Request for Review Comments email sent for Project Rice Ranch Site Development Plan for review by Nina Ruiz on behalf of PCD Project Manager
6/22/2019 6:43:02 AM Request for Review Comments email sent for Project Rice Ranch Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
6/22/2019 6:41:52 AM Submission Triaged
6/20/2019 4:33:18 PM Submission received from Applicant
6/12/2019 3:33:09 PM Request for Review Comments returned by EPC County Attorney's Office
6/5/2019 8:50:53 AM Request for Review Comments returned by EPC Code Enforcement
6/3/2019 8:33:21 AM Submission request sent to Applicant
5/30/2019 1:24:56 PM Request for Review Comments returned by PCD Engineering Division
5/28/2019 10:16:52 AM Request for Review Comments returned by PCD Project Manager
5/28/2019 10:16:27 AM Submission request sent to Applicant
5/28/2019 7:41:26 AM Request for Review Comments email sent for Project Rice Ranch Site Development Plan for review by Edi Anderson on behalf of EPC County Attorney's Office
5/28/2019 7:23:19 AM Submission Triaged
5/22/2019 5:44:53 PM Submission received from Applicant
5/22/2019 12:42:06 PM Submission request sent to Applicant
5/17/2019 3:27:00 PM Request for Review Comments returned by EPC County Attorney's Office
5/14/2019 5:45:54 AM Request for Review Comments email sent for Project Rice Ranch Site Development Plan for review by Edi Anderson on behalf of EPC County Attorney's Office
5/14/2019 5:45:49 AM Request for Review Comments email sent for Project Rice Ranch Site Development Plan for review by Mindy Madden on behalf of EPC Code Enforcement
5/14/2019 5:45:45 AM Request for Review Comments email sent for Project Rice Ranch Site Development Plan for review by Nina Ruiz on behalf of PCD Project Manager
5/14/2019 5:45:37 AM Request for Review Comments email sent for Project Rice Ranch Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
5/14/2019 5:42:08 AM Submission Triaged
5/13/2019 5:36:29 PM Submission received from Applicant
5/10/2019 11:55:07 AM Submission request sent to Applicant
5/10/2019 11:54:38 AM Submission Triaged
5/9/2019 6:27:38 AM Submission received from Applicant
4/1/2019 1:53:51 PM Submission request sent to Applicant
2/18/2019 5:37:22 PM Request for Review Comments returned by PCD Engineering Division
2/14/2019 12:37:14 PM Request for Review Comments returned by PCD Project Manager
2/12/2019 4:10:52 PM Request for Review Comments returned by EPC Code Enforcement
2/11/2019 6:18:37 AM Request for Review Comments email sent for Project Rice Ranch Site Development Plan for review by Mindy Madden on behalf of EPC Code Enforcement
1/31/2019 11:54:57 AM Request for Review Comments email sent for Project Rice Ranch Site Development Plan for review by Nina Ruiz on behalf of PCD Project Manager
1/31/2019 11:54:50 AM Request for Review Comments email sent for Project Rice Ranch Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
1/31/2019 11:53:43 AM Submission Triaged
1/31/2019 11:12:48 AM Submission received from Applicant
12/11/2018 1:42:23 PM Request for Review Comments returned by Colorado Springs Airport Advisory Commission
12/11/2018 12:14:25 PM Submission request sent to Applicant
12/11/2018 12:13:48 PM Request for Review Comments returned by PCD Project Manager
12/5/2018 3:26:04 PM Request for Review Comments returned by PCD Engineering Division
11/29/2018 7:45:45 AM Request for Review Comments returned by EPC Code Enforcement
11/28/2018 4:54:07 AM Request for Review Comments email sent for Project Rice Ranch Site Development Plan for review by Kristine Andrews on behalf of Colorado Springs Airport Advisory Commission
11/28/2018 4:54:06 AM Request for Review Comments email sent for Project Rice Ranch Site Development Plan for review by Mindy Madden on behalf of EPC Code Enforcement
11/28/2018 4:54:05 AM Request for Review Comments email sent for Project Rice Ranch Site Development Plan for review by Nina Ruiz on behalf of PCD Project Manager
11/28/2018 4:54:03 AM Request for Review Comments email sent for Project Rice Ranch Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
11/28/2018 4:53:26 AM Submission Triaged
11/26/2018 6:03:24 PM Submission received from Applicant
11/20/2018 2:11:42 PM Request for Review Comments returned by PCD Project Manager
11/20/2018 10:16:59 AM Request for Review Comments email resent for Project Rice Ranch Site Development Plan for review by Nina Ruiz on behalf of PCD Project Manager
11/7/2018 4:47:52 PM Submission request sent to Applicant
11/7/2018 4:47:17 PM Request for Review Comments returned by PCD Project Manager
11/7/2018 4:46:07 PM Request for Review Comments email resent for Project Rice Ranch Site Development Plan for review by Nina Ruiz on behalf of PCD Project Manager
11/7/2018 11:31:41 AM Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
11/6/2018 7:43:15 AM Request for Review Comments returned by EPC Code Enforcement
11/5/2018 2:51:30 PM Request for Review Comments returned by PCD Engineering Division
11/5/2018 9:17:11 AM Request for Review Comments returned by Colorado Springs Airport Advisory Commission
10/31/2018 4:11:21 PM Request for Review Comments returned by PCD Project Manager
10/23/2018 2:19:51 PM Request for Review Comments email sent for Project Rice Ranch Site Development Plan for review by Mindy Madden on behalf of EPC Code Enforcement
10/23/2018 2:19:31 PM Request for Review Comments email sent for Project Rice Ranch Site Development Plan for review by Kristine Andrews on behalf of Colorado Springs Airport Advisory Commission
10/23/2018 2:19:30 PM Request for Review Comments email sent for Project Rice Ranch Site Development Plan for review by Nina Ruiz on behalf of PCD Project Manager
10/23/2018 2:19:28 PM Request for Review Comments email sent for Project Rice Ranch Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
10/23/2018 2:17:33 PM Submission Triaged
10/23/2018 7:56:27 AM Submission received from Applicant
6/26/2018 1:27:47 PM Submission request sent to Applicant
6/26/2018 1:26:14 PM Request for Review Comments returned by PCD Project Manager
6/26/2018 1:25:40 PM Request for Review Comments email resent for Project Rice Ranch Site Development Plan for review by Nina Ruiz on behalf of PCD Project Manager
6/20/2018 4:28:22 PM Request for Review Comments returned by PCD Engineering Division
6/18/2018 2:33:11 PM Request for Review Comments returned by PCD Project Manager
6/16/2018 3:10:21 PM Request for Review Comments returned by EPC Health Department
6/14/2018 3:44:38 PM Request for Review Comments returned by Colorado Springs Airport Advisory Commission
6/14/2018 9:28:15 AM Request for Review Comments returned by Pikes Peak Regional Building Department
6/13/2018 5:12:25 PM Request for Review Comments returned by EPC Code Enforcement
5/31/2018 10:40:05 AM Request for Review Comments email sent for Project Rice Ranch Site Development Plan for review by on behalf of Security Fire Protection District
5/31/2018 10:40:04 AM Request for Review Comments email sent for Project Rice Ranch Site Development Plan for review by Kristy Martinez on behalf of Fountain
5/31/2018 10:40:03 AM Request for Review Comments email sent for Project Rice Ranch Site Development Plan for review by Kristine Andrews on behalf of Colorado Springs Airport Advisory Commission
5/31/2018 10:40:02 AM Request for Review Comments email sent for Project Rice Ranch Site Development Plan for review by RBD Enumerations & Floodplain on behalf of Pikes Peak Regional Building Department
5/31/2018 10:40:01 AM Request for Review Comments email sent for Project Rice Ranch Site Development Plan for review by Permits Manager Valerie Sword on behalf of Colorado Department of Transportation - Pueblo Office
5/31/2018 10:39:58 AM Request for Review Comments email sent for Project Rice Ranch Site Development Plan for review by on behalf of EPC Health Department
5/31/2018 10:39:57 AM Request for Review Comments email sent for Project Rice Ranch Site Development Plan for review by Mindy Madden on behalf of EPC Code Enforcement
5/31/2018 10:39:57 AM Request for Review Comments email sent for Project Rice Ranch Site Development Plan for review by Nina Ruiz on behalf of PCD Project Manager
5/31/2018 10:39:56 AM Request for Review Comments email sent for Project Rice Ranch Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
5/31/2018 10:38:46 AM Fees paid: 5/31/2018 (Receipt: 1000703)
5/29/2018 10:52:20 AM Payment Request sent: 5/29/2018
5/29/2018 10:52:14 AM File # Assigned: PPR1824
5/23/2018 10:49:07 AM Submission Triaged
5/22/2018 7:29:12 AM Submission received from Applicant
3/6/2018 10:44:52 AM Submission request sent to Applicant
2/20/2018 2:23:34 PM Submission request sent to Applicant
2/20/2018 2:20:26 PM Project Manager Assigned: Nina Ruiz
2/20/2018 2:20:26 PM EA Assigned: EA-17-089
2/20/2018 2:20:26 PM Project Created