Project Details

Search


File Number
SP206
Project Name
Paint Brush Hills Preliminary Plan 14
Description
Preliminary Plan for 224 single-family lots split zoned RS-20000 & RS-6000. A Regional Trail Corridor along Northern Boundary is included. A finding of water sufficiency , pre-site development grading and administrative plats are requested.
Location
northwest of Londonderry Drive within the Paintbrush Hills development
Parcels
5226101009 5226101009
Applicant
M & S Civil
Jason Alwine ( jason_alwine@matrixdesigngroup.com ) Jason Alwine ( jason_alwine@matrixdesigngroup.com )
EA Number
17-149
File Prefix
SP - Preliminary Plan
Year
2020
Project Manager
Kari Parsons
Status
Closed
Created
1/4/2018 11:09:45 AM

View: Review Comments


Approved Documents (10)

Link Document
View Grading & Erosion Control checklist
View Erosion and Stormwater Quality Control Permit (ESQCP)
View PBMP Applicability Form
View SWMP checklist
View Grading & Erosion Control Plan (24 x 36)
View Predevelopment (Early) Grading Request
View Storm Water Management Plan (SWMP)
View Drainage Report - Preliminary
View Traffic Impact Study
View Financial Assurance Forms


Additional Documents (11)

Link Document Comment
View Water History Filings 13B-D recorded
View Deviation Intersection Spacing Approved
View Deviation Aux Lane Approved with Conditions
View Mailing Packet: Notice, Map and Labels Mailed 4/14/2021--42 Notices
View Posting Photos Posted 4/19/2021
View PC Staff Report with Attachments
View BoCC Staff Report with Attachments
View PC Approval Letter
View BoCC Approval Letter
View BoCC Resolution 21-183
View PC Resolution


Review Documents (44)

Link Document Date
View Adjacent Property Owner Notification (Includes letter and certified mailing receipts) 8/26/2020 7:06:14 PM
View Application/Petition Form 9/2/2020 9:38:28 AM
View Grading & Erosion Control checklist 1/7/2021 9:32:08 PM
View Legal Description (MS WORD Version required) 8/14/2020 3:05:14 PM
View Letter of Intent 3/25/2021 4:24:37 PM
View Title Commitment (Current within 30 days of submittal) 8/19/2020 4:27:16 PM
View Vicinity/Location Map 8/11/2020 1:59:47 PM
View Applicant Comment Response Letter 3/9/2021 8:17:18 AM
View Colorado Geological Survey Receipt 7/20/2018 3:09:49 PM
View Erosion and Stormwater Quality Control Permit (ESQCP) 3/7/2021 9:42:44 AM
View Mineral Rights Certification 1/7/2021 6:31:41 PM
View PBMP Applicability Form 3/7/2021 10:07:26 AM
View PDB/BMP Operations & Maintenance Manual 6/29/2018 11:36:12 AM
View Stormwater Detention & Infiltration Design Data Worksheet (SDI Worksheet) 10/19/2020 5:10:21 PM
View SWMP checklist 1/7/2021 9:32:09 PM
View Grading & Erosion Control Plan (24 x 36) 3/7/2021 9:42:43 AM
View Predevelopment (Early) Grading Request 3/16/2021 2:40:44 PM
View Preliminary Plan Drawings (24" x 36") 3/16/2021 2:40:43 PM
View Storm Water Management Plan (SWMP) 1/7/2021 9:21:43 PM
View Electric Provider Commitment Letter 8/11/2020 12:22:07 PM
View Fire Commitment Letter 8/11/2020 10:01:06 AM
View Natural Gas Commitment Letter 8/14/2020 2:22:50 PM
View Drainage Report - Preliminary 3/17/2021 1:21:50 PM
View Fire Protection Report 1/6/2021 7:45:41 AM
View Natural Features Report 1/6/2021 7:45:44 AM
View Soils & Geology Report 1/6/2021 7:45:42 AM
View Traffic Impact Study 3/17/2021 1:25:36 PM
View Wastewater Disposal Report 1/12/2021 10:29:55 PM
View Water Resources Report 4/7/2021 11:08:18 AM
View Water Supply Information Summary 3/7/2021 8:47:23 AM
View Attorney Water Commitment Response 3/9/2021 8:25:31 AM
View Aux. Lane Deviation 1/14/2021 9:56:35 AM
View Commitment letter from waste water service provider 3/7/2021 8:47:20 AM
View Commitment letter from water service provider 3/7/2021 8:47:19 AM
View FDR Response Comments 1/7/2021 7:35:32 AM
View Financial Assurance Forms 3/16/2021 2:40:43 PM
View Impact Identification Statement 1/6/2021 7:45:43 AM
View Intersection Spacing Deviation 1/14/2021 9:56:34 AM
View Lot 70 Exhibit 3/9/2021 8:17:57 AM
View PM Water Review Response 3/9/2021 8:25:32 AM
View Prelim Plan Response to Comments 1/14/2021 10:00:34 AM
View Preliminary Plan Engineering Responses 3/9/2021 8:25:33 AM
View TIS Response to Comments 1/14/2021 9:56:34 AM
View Water Summary Response 3/9/2021 8:25:34 AM



Events (171)

Date Comment
5/11/2021 10:35:38 AM Project Closed
5/11/2021 10:35:38 AM Project Approved: 5/11/2021
4/28/2021 9:48:07 AM Project reopened for Approval requests
4/27/2021 7:28:34 AM Project Closed
4/27/2021 7:28:34 AM Project Approved: 4/27/2021
4/7/2021 5:28:16 PM Request for Review Comments returned by EPC County Attorney's Office
4/7/2021 11:20:59 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Edi Anderson on behalf of EPC County Attorney's Office
4/7/2021 11:20:16 AM Submission Triaged
4/7/2021 11:08:31 AM Submission received from Applicant
4/6/2021 7:17:08 AM Submission request sent to Applicant
4/3/2021 1:52:25 PM Request for Review Comments returned by EPC County Attorney's Office
4/1/2021 3:17:54 PM Request for Review Comments returned by PCD Engineering Division
4/1/2021 12:08:22 PM Submission request canceled
4/1/2021 10:00:55 AM Request for Review Comments returned by PCD Project Manager
4/1/2021 9:59:37 AM Request for Review Comments email resent for Project Paint Brush Hills Preliminary Plan 14 for review by Kari Parsons on behalf of PCD Project Manager
4/1/2021 9:56:23 AM Submission request sent to Applicant
4/1/2021 9:55:48 AM Request for Review Comments returned by PCD Project Manager
3/31/2021 2:04:50 PM Request for Review Comments returned by EPC Health Department
3/31/2021 7:48:44 AM Request for Review Comments email resent for Project Paint Brush Hills Preliminary Plan 14 for review by Kari Parsons on behalf of PCD Project Manager
3/31/2021 7:44:08 AM Request for Review Comments returned by PCD Project Manager
3/25/2021 5:03:54 PM Submission Triaged
3/25/2021 4:25:30 PM Submission received from Applicant
3/25/2021 12:59:38 PM Submission request sent to Applicant
3/24/2021 8:22:00 AM Request for Review Comments returned by Colorado Division of Water Resources
3/23/2021 4:23:05 PM Request for Review Comments returned by Pikes Peak Regional Building Department
3/23/2021 9:38:13 AM Request for Review Comments returned by EPC Stormwater Review
3/18/2021 10:33:08 AM Request for Review Comments returned by EPC Parks Department
3/17/2021 5:37:36 PM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Kari Parsons on behalf of PCD Project Manager
3/17/2021 5:37:32 PM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
3/17/2021 1:45:10 PM Request for Review Comments returned by PCD Project Manager
3/17/2021 1:44:14 PM Request for Review Comments email resent for Project Paint Brush Hills Preliminary Plan 14 for review by Kari Parsons on behalf of PCD Project Manager
3/17/2021 1:33:34 PM Submission Triaged
3/17/2021 1:26:04 PM Submission received from Applicant
3/16/2021 7:03:29 AM Submission request sent to Applicant
3/15/2021 11:04:23 AM Request for Review Comments returned by PCD Engineering Division
3/9/2021 9:41:05 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Leon Gomes on behalf of Paint Brush Hills Metro
3/9/2021 9:41:03 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by RBD Enumerations & Floodplain on behalf of Pikes Peak Regional Building Department
3/9/2021 9:40:58 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Joanna Williams on behalf of Colorado Division of Water Resources
3/9/2021 9:40:54 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
3/9/2021 9:40:52 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by on behalf of EPC Parks Department
3/9/2021 9:40:42 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by on behalf of EPC Health Department
3/9/2021 9:40:34 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Edi Anderson on behalf of EPC County Attorney's Office
3/9/2021 9:40:32 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Kari Parsons on behalf of PCD Project Manager
3/9/2021 9:40:28 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
3/9/2021 9:37:36 AM Submission Triaged
3/9/2021 8:25:57 AM Submission received from Applicant
3/9/2021 7:04:11 AM Submission request sent to Applicant
3/9/2021 7:02:30 AM Submission Triaged
3/8/2021 12:04:24 PM Submission received from Applicant
2/17/2021 7:26:40 AM Submission request sent to Applicant
2/17/2021 7:25:15 AM Submission request sent to Applicant
2/17/2021 7:06:14 AM Request for Review Comments returned by PCD Engineering Division
2/15/2021 10:38:41 AM Request for Review Comments returned by Colorado Geological Survey
2/11/2021 5:13:40 PM Request for Review Comments returned by Pikes Peak Regional Building Department
2/8/2021 7:21:08 AM Request for Review Comments returned by EPC Parks Department
2/4/2021 5:31:14 PM Request for Review Comments returned by EPC Stormwater Review
1/29/2021 2:54:55 PM Request for Review Comments returned by PCD Project Manager
1/29/2021 8:12:10 AM Request for Review Comments returned by 911 Authority - El Paso/Teller County
1/29/2021 7:55:56 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by RBD Enumerations & Floodplain on behalf of Pikes Peak Regional Building Department
1/29/2021 7:55:51 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
1/29/2021 7:49:43 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Colorado Geological Survey on behalf of Colorado Geological Survey
1/28/2021 9:12:41 AM Request for Review Comments returned by EPC County Attorney's Office
1/27/2021 4:54:46 PM Project Manager Assigned: Kari Parsons
1/19/2021 10:19:06 AM Request for Review Comments returned by 911 Authority - El Paso/Teller County
1/15/2021 10:07:28 AM Request for Review Comments returned by EPC Environmental Services
1/14/2021 11:10:09 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
1/14/2021 11:10:07 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Elaine Kelly on behalf of US Postal Service
1/14/2021 11:10:03 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
1/14/2021 11:10:01 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by on behalf of EPC Parks Department
1/14/2021 11:09:59 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Kathy Andrew on behalf of EPC Environmental Services
1/14/2021 11:09:56 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Edi Anderson on behalf of EPC County Attorney's Office
1/14/2021 11:09:52 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Ryan Howser on behalf of PCD Project Manager
1/14/2021 11:09:48 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
1/14/2021 11:00:32 AM Submission Triaged
1/14/2021 10:00:42 AM Submission received from Applicant
12/27/2020 2:04:46 PM Project Manager Assigned: Ryan Howser
12/15/2020 7:53:43 AM Request for Review Comments returned by US Postal Service
11/25/2020 3:56:27 PM Request for Review Comments returned by Colorado Division of Water Resources
11/23/2020 12:11:26 AM Submission request sent to Applicant
11/23/2020 12:11:21 AM Request for Review Comments returned by PCD Project Manager
11/23/2020 12:10:16 AM Request for Review Comments email resent for Project Paint Brush Hills Preliminary Plan 14 for review by Lindsay Darden on behalf of PCD Project Manager
11/18/2020 12:09:36 PM Request for Review Comments returned by Colorado Geological Survey
11/16/2020 8:02:52 AM Request for Review Comments returned by Parks Advisory Board
11/15/2020 11:26:02 PM Request for Review Comments returned by PCD Project Manager
11/15/2020 11:10:36 PM Request for Review Comments email resent for Project Paint Brush Hills Preliminary Plan 14 for review by Lindsay Darden on behalf of PCD Project Manager
11/14/2020 5:51:38 PM Request for Review Comments returned by EPC Health Department
11/12/2020 1:35:18 PM Request for Review Comments returned by EPC Stormwater Review
11/12/2020 11:12:11 AM Request for Review Comments returned by Pikes Peak Regional Building Department
11/10/2020 3:29:31 PM Request for Review Comments returned by Falcon Fire Protection District
11/9/2020 7:15:09 AM Request for Review Comments returned by El Paso County Conservation Dist
11/9/2020 5:10:56 AM Request for Review Comments returned by PCD Project Manager
11/6/2020 12:10:35 PM Request for Review Comments returned by PCD Engineering Division
11/4/2020 2:26:07 PM Request for Review Comments returned by Upper Black Squirrel Creek GWMD
11/3/2020 1:59:34 PM Request for Review Comments returned by Mountain View Electric Association, Inc.
10/30/2020 2:37:32 PM Request for Review Comments returned by EPC Parks Department
10/29/2020 12:27:13 PM Request for Review Comments returned by Colorado Parks and Wildlife
10/29/2020 8:26:35 AM Request for Review Comments returned by 911 Authority - El Paso/Teller County
10/27/2020 10:56:22 AM Request for Review Comments returned by EPC Environmental Services
10/22/2020 9:25:57 AM Request for Review Comments returned by EPC County Attorney's Office
10/22/2020 7:48:09 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Leon Gomes on behalf of Paint Brush Hills Metro
10/22/2020 7:48:07 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
10/22/2020 7:48:05 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Christoph Zurcher on behalf of Mountain Metro Transit (City of COS)
10/22/2020 7:48:03 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Chief Trent Harwig on behalf of Falcon Fire Protection District
10/22/2020 7:48:01 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Melissa Andrews on behalf of Falcon 49
10/22/2020 7:47:57 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Pamela Davison on behalf of El Paso County Conservation Dist
10/22/2020 7:47:55 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Sebastian Schwender on behalf of Black Hills Energy-Aquila
10/22/2020 7:47:53 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
10/22/2020 7:47:50 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by RBD Enumerations & Floodplain on behalf of Pikes Peak Regional Building Department
10/22/2020 7:47:48 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
10/22/2020 7:47:46 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Elaine Kelly on behalf of US Postal Service
10/22/2020 7:47:44 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Jeffrey Hovermale on behalf of US Forest Service, Pikes Peak Ranger District
10/22/2020 7:47:42 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Larry Long on behalf of Colorado State Forest Service
10/22/2020 7:47:40 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Dan Prenzlow on behalf of Colorado Parks and Wildlife
10/22/2020 7:47:34 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Colorado Geological Survey on behalf of Colorado Geological Survey
10/22/2020 7:47:31 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Joanna Williams on behalf of Colorado Division of Water Resources
10/22/2020 7:47:28 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by on behalf of Parks Advisory Board
10/22/2020 7:47:24 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
10/22/2020 7:47:22 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Commander John Padgett on behalf of EPC Sheriff's Department
10/22/2020 7:47:19 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
10/22/2020 7:47:17 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by on behalf of EPC Parks Department
10/22/2020 7:47:15 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by on behalf of EPC Health Department
10/22/2020 7:47:09 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Kathy Andrew on behalf of EPC Environmental Services
10/22/2020 7:47:07 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Edi Anderson on behalf of EPC County Attorney's Office
10/22/2020 7:47:05 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Lindsay Darden on behalf of PCD Project Manager
10/22/2020 7:47:01 AM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
10/21/2020 4:44:29 PM Fees paid: 10/21/2020 (Receipt: 1003441)
10/21/2020 3:30:45 PM Payment Request sent: 10/21/2020
10/21/2020 3:30:34 PM File # Assigned: SP206
10/21/2020 3:24:34 PM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Leon Gomes on behalf of Paint Brush Hills Metro
10/21/2020 3:24:32 PM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
10/21/2020 3:24:30 PM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Christoph Zurcher on behalf of Mountain Metro Transit (City of COS)
10/21/2020 3:24:27 PM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Chief Trent Harwig on behalf of Falcon Fire Protection District
10/21/2020 3:24:25 PM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Melissa Andrews on behalf of Falcon 49
10/21/2020 3:24:21 PM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Pamela Davison on behalf of El Paso County Conservation Dist
10/21/2020 3:24:19 PM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Sebastian Schwender on behalf of Black Hills Energy-Aquila
10/21/2020 3:24:17 PM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
10/21/2020 3:24:15 PM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by RBD Enumerations & Floodplain on behalf of Pikes Peak Regional Building Department
10/21/2020 3:24:13 PM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
10/21/2020 3:24:11 PM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Elaine Kelly on behalf of US Postal Service
10/21/2020 3:24:09 PM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Jeffrey Hovermale on behalf of US Forest Service, Pikes Peak Ranger District
10/21/2020 3:24:06 PM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Larry Long on behalf of Colorado State Forest Service
10/21/2020 3:24:03 PM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Dan Prenzlow on behalf of Colorado Parks and Wildlife
10/21/2020 3:23:57 PM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Colorado Geological Survey on behalf of Colorado Geological Survey
10/21/2020 3:23:55 PM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Joanna Williams on behalf of Colorado Division of Water Resources
10/21/2020 3:23:53 PM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by on behalf of Parks Advisory Board
10/21/2020 3:23:50 PM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
10/21/2020 3:23:48 PM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Commander John Padgett on behalf of EPC Sheriff's Department
10/21/2020 3:23:45 PM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
10/21/2020 3:23:43 PM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by on behalf of EPC Parks Department
10/21/2020 3:23:41 PM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by on behalf of EPC Health Department
10/21/2020 3:23:36 PM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Kathy Andrew on behalf of EPC Environmental Services
10/21/2020 3:23:34 PM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Edi Anderson on behalf of EPC County Attorney's Office
10/21/2020 3:23:32 PM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Lindsay Darden on behalf of PCD Project Manager
10/21/2020 3:23:28 PM Request for Review Comments email sent for Project Paint Brush Hills Preliminary Plan 14 for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
10/21/2020 3:16:37 PM Submission Triaged
10/19/2020 5:10:39 PM Submission received from Applicant
8/31/2020 3:54:18 PM Submission request sent to Applicant
8/31/2020 3:51:45 PM Submission request sent to Applicant
8/31/2020 3:51:20 PM Submission Triaged
8/31/2020 10:54:24 AM Submission received from Applicant
7/15/2020 8:23:38 AM Submission request sent to Applicant
7/10/2020 2:04:27 PM Project reopened for Review Comments
4/16/2020 3:14:59 PM Project Manager Assigned: Lindsay Darden
5/7/2019 12:00:00 AM Project Closed
5/7/2019 12:00:00 AM Project Expired one year after 05/07/2018 Submission Request 05/07/2019
5/7/2018 5:11:24 PM Submission request sent to Applicant
5/7/2018 4:54:31 PM Submission request sent to Applicant
1/4/2018 11:54:55 AM Submission request sent to Applicant
1/4/2018 11:10:07 AM Project Manager Assigned: Kari Parsons
1/4/2018 11:10:07 AM EA Assigned: 17-149
1/4/2018 11:10:07 AM Project Created