6/26/2020 6:45:16 AM
|
Project Closed
|
6/26/2020 6:45:16 AM
|
Project Approved: 6/26/2020
|
5/18/2020 1:28:25 PM
|
Submission Triaged
|
5/18/2020 11:46:07 AM
|
Submission received from Applicant
|
5/18/2020 9:05:30 AM
|
Submission request sent to Applicant
|
5/17/2020 7:42:03 AM
|
Submission request sent to Applicant
|
4/23/2020 9:17:24 AM
|
Request for Review Comments returned by EPC Health Department
|
4/14/2020 2:22:07 PM
|
Request for Review Comments returned by EPC County Attorney's Office
|
4/14/2020 5:52:13 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Edi Anderson on behalf of EPC County Attorney's Office
|
4/13/2020 1:45:29 PM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
4/8/2020 4:17:21 PM
|
Request for Review Comments returned by Woodmoor Water and Sanitation District
|
4/8/2020 12:29:03 PM
|
Request for Review Comments returned by Colorado Geological Survey
|
4/7/2020 3:17:04 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
4/7/2020 6:21:15 AM
|
Request for Review Comments returned by PCD Project Manager
|
4/2/2020 8:17:11 AM
|
Request for Review Comments returned by PCD Engineering Division
|
3/31/2020 2:42:19 PM
|
Request for Review Comments returned by EPC County Attorney's Office
|
3/31/2020 9:37:19 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
3/31/2020 8:38:37 AM
|
Request for Review Comments returned by EPC Parks Department
|
3/30/2020 2:50:11 PM
|
Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
|
3/30/2020 7:57:34 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
3/29/2020 11:18:07 AM
|
Request for Review Comments returned by Northern EPC Coalition of Community Organizations, Inc. (NEPCO)
|
3/26/2020 12:43:19 PM
|
Request for Review Comments returned by EPC Environmental Services
|
3/26/2020 12:09:01 PM
|
Request for Review Comments returned by Lewis Palmer 38
|
3/26/2020 11:14:25 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
|
3/26/2020 11:14:24 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by RBD Enumerations & Floodplain on behalf of Pikes Peak Regional Building Department
|
3/26/2020 11:14:23 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Paul Pirog on behalf of Northern EPC Coalition of Community Organizations, Inc. (NEPCO)
|
3/26/2020 11:14:22 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
3/26/2020 11:14:21 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
3/26/2020 11:14:20 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Melissa Van Der Poel on behalf of Colorado Division of Water Resources
|
3/26/2020 11:14:18 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Woodmoor Water District on behalf of Woodmoor Water and Sanitation District
|
3/26/2020 11:14:18 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Jamey Bumgarner on behalf of Tri-Lakes-Monument Fire Protection District
|
3/26/2020 11:14:16 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Vicki Wood on behalf of Lewis Palmer 38
|
3/26/2020 11:14:15 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by on behalf of EPC Parks Department
|
3/26/2020 11:14:11 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by on behalf of EPC Health Department
|
3/26/2020 11:14:11 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Kathy Andrew on behalf of EPC Environmental Services
|
3/26/2020 11:14:10 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Edi Anderson on behalf of EPC County Attorney's Office
|
3/26/2020 11:14:09 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Nina Ruiz on behalf of PCD Project Manager
|
3/26/2020 11:14:07 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
2/26/2020 7:28:01 AM
|
Submission Triaged
|
2/25/2020 1:24:35 PM
|
Submission received from Applicant
|
2/19/2020 11:58:16 AM
|
Request for Review Comments returned by EPC County Attorney's Office
|
2/8/2020 4:57:28 PM
|
Request for Review Comments returned by EPC Health Department
|
1/22/2020 10:56:47 AM
|
Request for Review Comments returned by PCD Project Manager
|
1/22/2020 10:55:52 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Nina Ruiz on behalf of PCD Project Manager
|
1/6/2020 1:43:42 PM
|
Request for Review Comments returned by PCD Project Manager
|
1/6/2020 1:43:41 PM
|
Submission request sent to Applicant
|
1/6/2020 1:39:34 PM
|
Request for Review Comments email resent for Project Northbay at Lake Woodmoor for review by Nina Ruiz on behalf of PCD Project Manager
|
1/6/2020 9:41:09 AM
|
Request for Review Comments returned by Colorado Geological Survey
|
12/30/2019 12:27:29 PM
|
Request for Review Comments returned by PCD Engineering Division
|
12/26/2019 9:32:27 AM
|
Request for Review Comments returned by PCD Project Manager
|
12/23/2019 2:49:55 PM
|
Request for Review Comments returned by Woodmoor Water and Sanitation District
|
12/19/2019 12:00:54 PM
|
Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
|
12/18/2019 3:04:06 PM
|
Request for Review Comments returned by Northern EPC Coalition of Community Organizations, Inc. (NEPCO)
|
12/18/2019 2:35:39 PM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
12/18/2019 1:12:05 PM
|
Request for Review Comments returned by Lewis Palmer 38
|
12/18/2019 10:31:20 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
12/11/2019 10:34:17 AM
|
Request for Review Comments returned by EPC Parks Department
|
12/11/2019 10:30:17 AM
|
Request for Review Comments returned by EPC Parks Department
|
12/3/2019 10:52:44 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
12/3/2019 10:52:10 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
12/2/2019 10:59:58 AM
|
Request for Review Comments returned by EPC Environmental Services
|
12/2/2019 10:59:18 AM
|
Request for Review Comments returned by EPC Environmental Services
|
12/2/2019 8:21:56 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
12/2/2019 8:21:27 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
11/25/2019 5:07:32 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Administrator/Mgr on behalf of Woodmoor Improvement Association
|
11/25/2019 5:07:31 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
|
11/25/2019 5:07:30 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
11/25/2019 5:07:29 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Jennifer Jones on behalf of Monument
|
11/25/2019 5:07:28 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by John Bender on behalf of Tri Lakes Land Use Committee
|
11/25/2019 5:07:27 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by RBD Enumerations & Floodplain on behalf of Pikes Peak Regional Building Department
|
11/25/2019 5:07:26 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Tom Vierzba on behalf of Northern EPC Coalition of Community Organizations, Inc. (NEPCO)
|
11/25/2019 5:07:25 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Dave Munger on behalf of Council of Neighborhood Organizations (CONO)
|
11/25/2019 5:07:24 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
11/25/2019 5:07:23 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Larry Long on behalf of Colorado State Forest Service
|
11/25/2019 5:07:22 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Dan Prenzlow on behalf of Colorado Parks and Wildlife
|
11/25/2019 5:07:21 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
11/25/2019 5:07:21 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Melissa Van Der Poel on behalf of Colorado Division of Water Resources
|
11/25/2019 5:07:19 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Woodmoor Water District on behalf of Woodmoor Water and Sanitation District
|
11/25/2019 5:07:18 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Jamey Bumgarner on behalf of Tri-Lakes-Monument Fire Protection District
|
11/25/2019 5:07:17 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Vicki Wood on behalf of Lewis Palmer 38
|
11/25/2019 5:07:16 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Commander John Padgett on behalf of EPC Sheriff's Department
|
11/25/2019 5:07:15 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by on behalf of EPC Parks Department
|
11/25/2019 5:07:14 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Administrator/Mgr on behalf of Woodmoor Improvement Association
|
11/25/2019 5:07:13 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
|
11/25/2019 5:07:13 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by on behalf of EPC Health Department
|
11/25/2019 5:07:12 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
11/25/2019 5:07:12 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Kathy Andrew on behalf of EPC Environmental Services
|
11/25/2019 5:07:11 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Edi Anderson on behalf of EPC County Attorney's Office
|
11/25/2019 5:07:11 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Jennifer Jones on behalf of Monument
|
11/25/2019 5:07:10 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Nina Ruiz on behalf of PCD Project Manager
|
11/25/2019 5:07:10 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by John Bender on behalf of Tri Lakes Land Use Committee
|
11/25/2019 5:07:09 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by RBD Enumerations & Floodplain on behalf of Pikes Peak Regional Building Department
|
11/25/2019 5:07:08 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
11/25/2019 5:07:08 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Tom Vierzba on behalf of Northern EPC Coalition of Community Organizations, Inc. (NEPCO)
|
11/25/2019 5:07:07 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Dave Munger on behalf of Council of Neighborhood Organizations (CONO)
|
11/25/2019 5:07:06 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
11/25/2019 5:07:05 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Larry Long on behalf of Colorado State Forest Service
|
11/25/2019 5:07:04 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Dan Prenzlow on behalf of Colorado Parks and Wildlife
|
11/25/2019 5:07:03 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
11/25/2019 5:07:02 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Melissa Van Der Poel on behalf of Colorado Division of Water Resources
|
11/25/2019 5:07:01 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Woodmoor Water District on behalf of Woodmoor Water and Sanitation District
|
11/25/2019 5:07:00 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Jamey Bumgarner on behalf of Tri-Lakes-Monument Fire Protection District
|
11/25/2019 5:06:59 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Vicki Wood on behalf of Lewis Palmer 38
|
11/25/2019 5:06:58 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Commander John Padgett on behalf of EPC Sheriff's Department
|
11/25/2019 5:06:57 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by on behalf of EPC Parks Department
|
11/25/2019 5:06:55 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by on behalf of EPC Health Department
|
11/25/2019 5:06:54 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Kathy Andrew on behalf of EPC Environmental Services
|
11/25/2019 5:06:53 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Edi Anderson on behalf of EPC County Attorney's Office
|
11/25/2019 5:06:52 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Nina Ruiz on behalf of PCD Project Manager
|
11/25/2019 5:06:50 AM
|
Request for Review Comments email sent for Project Northbay at Lake Woodmoor for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
11/25/2019 4:53:04 AM
|
Submission Triaged
|
11/22/2019 1:09:57 PM
|
Submission received from Applicant
|
11/5/2018 10:44:02 AM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
10/23/2018 9:35:03 AM
|
Request for Review Comments email resent for Project Northbay at Lake Woodmoor for review by Melissa Van Der Poel on behalf of Colorado Division of Water Resources
|
10/22/2018 1:14:04 PM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
10/17/2018 10:21:13 AM
|
Submission request sent to Applicant
|
10/17/2018 10:20:11 AM
|
Request for Review Comments returned by PCD Project Manager
|
10/16/2018 4:01:08 PM
|
Request for Review Comments returned by PCD Engineering Division
|
10/10/2018 4:45:44 PM
|
Request for Review Comments email resent for Project North Bay at Lake Woodmoor for review by Nina Ruiz on behalf of PCD Project Manager
|
10/1/2018 9:47:49 AM
|
Request for Review Comments returned by PCD Project Manager
|
9/26/2018 3:32:14 PM
|
Request for Review Comments returned by EPC County Attorney's Office
|
9/25/2018 5:12:19 PM
|
Request for Review Comments email sent for Project North Bay at Lake Woodmoor for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
9/25/2018 5:12:18 PM
|
Request for Review Comments email sent for Project North Bay at Lake Woodmoor for review by Edi Anderson on behalf of EPC County Attorney's Office
|
9/25/2018 5:12:17 PM
|
Request for Review Comments email sent for Project North Bay at Lake Woodmoor for review by Nina Ruiz on behalf of PCD Project Manager
|
9/25/2018 5:12:14 PM
|
Request for Review Comments email sent for Project North Bay at Lake Woodmoor for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
9/25/2018 5:09:53 PM
|
Submission Triaged
|
9/24/2018 5:52:23 PM
|
Submission received from Applicant
|
6/1/2018 9:55:00 AM
|
Project Manager Assigned: Nina Ruiz
|
4/20/2018 10:57:17 AM
|
Submission request sent to Applicant
|
4/2/2018 9:09:02 PM
|
Request for Review Comments email sent for Project North Bay at Lake Woodmoor for review by Edi Anderson on behalf of EPC County Attorney's Office
|
1/8/2018 3:47:48 PM
|
Request for Review Comments returned by PCD Engineering Division
|
1/8/2018 3:36:24 PM
|
Request for Review Comments email resent for Project North Bay at Lake Woodmoor for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
1/4/2018 4:46:43 PM
|
Request for Review Comments returned by PCD Project Manager
|
1/2/2018 1:55:30 PM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
12/21/2017 1:34:26 PM
|
Request for Review Comments returned by PCD Engineering Division
|
12/12/2017 4:15:27 PM
|
Request for Review Comments email sent for Project North Bay at Lake Woodmoor for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
12/12/2017 4:15:26 PM
|
Request for Review Comments email sent for Project North Bay at Lake Woodmoor for review by Raimere Fitzpatrick on behalf of PCD Project Manager
|
12/12/2017 4:15:25 PM
|
Request for Review Comments email sent for Project North Bay at Lake Woodmoor for review by Gilbert LaForce on behalf of PCD Engineering Division
|
12/11/2017 7:12:32 AM
|
Submission Triaged
|
12/7/2017 3:17:54 PM
|
Submission received from Applicant
|
11/9/2017 3:39:05 PM
|
Submission request sent to Applicant
|
11/9/2017 3:32:43 PM
|
Fees paid: 11/9/2017 (Receipt: 1000299)
|
11/9/2017 2:56:47 PM
|
Project Manager Assigned: Raimere Fitzpatrick
|
11/9/2017 2:56:47 PM
|
File # Assigned: PUDSP-16-004
|
11/9/2017 2:56:47 PM
|
Project Created
|