Project Review Comments

Back to List


File Number
VR267
Project Name
3615 Summertime Ct
Description
Adjust lot line between Lots 34 and 35. No new lots will be created. No water review needed
Parcels
7116101027 7116101027
Applicant
Matt Hornung
Surveyor Consultant Kevin O'Leary ( kevin@lwalandsurveying.com )
(719) 636-5179
Surveyor Consultant Kevin O'Leary ( kevin@lwalandsurveying.com )
(719) 636-5179
File Number
VR267
Project Manager
Lacey Dean
Status
Active
Created
6/29/2026 1:44:02 PM

View: Project Documents | Submit/View Public Comment



Review Comments (13)

Link Agency Review # Comment
PCD Administrative Notice
9/18/2026 8:42:39 AM
1 On 09/18/2026, PCD mailed "Notice of Application" letters to surrounding property owners within a 500-foot range (23 addresses). Copies of the notice, mailing labels, and selected range have been uploaded to the EDARP file. Cost of postage to be billed to the applicant = $17.94. JM 9/18/2026 8:42:39 AM
View PCD Project Manager
9/16/2026 11:08:40 AM
1 V1_Letter of Intent_comments 9/16/2026 11:08:40 AM
View PCD Project Manager
9/16/2026 11:08:01 AM
1 V1_Final Plat Drawings_comments 9/16/2026 11:08:01 AM
View PCD Project Manager
9/16/2026 11:06:48 AM
1 V1_Application-Petition Form_comments 9/16/2026 11:06:48 AM
PCD Project Manager
9/16/2026 11:04:54 AM
1 Review 1: EPC Planning Division has comments in green text boxes on the following documents:

- Application Form
- Letter of Intent
- Plat Drawings

Reviewed by:
Lacey Dean, Associate Planner
laceydean2@elpasoco.com
9/16/2026 11:04:54 AM
EPC DPW Stormwater
9/15/2026 11:49:22 AM
1 Review 1: This lot line adjustment does not involve any soil disturbance that would trigger a EPC Stormwater Permit or water quality treatment. Thus EPC DPW Stormwater does not have any comments on the submitted documents. Thanks.

Reviewed by:
Glenn Reese, P.E.
Principal Engineer - Stormwater
719.675.2654
GlennReese@elpasoco.com
9/15/2026 11:49:22 AM
EPC DPW Development Services - Engineering
9/15/2026 11:43:33 AM
1 Engineering comments on the following documents (to be uploaded by the project manager at a later date):
- Letter of Intent
- Final Plat Drawing

Reviewed by:
Joe Sandstrom, EIT, CFM
Associate Engineer
Department of Public Works
O: 719-520-6314
M: 719-505-0516
josephsandstrom@elpasoco.com
9/15/2026 11:43:33 AM
County Attorney - Water
9/10/2026 1:05:54 PM
1 The project description states that no water review is needed; therefore, this office has no comment 9/10/2026 1:05:54 PM
Mountain View Electric Association, Inc.
9/8/2026 4:37:45 PM
1 No Comment - this is located outside of MVEA's service territory. 9/8/2026 4:37:45 PM
EPC Parks Department
9/3/2026 9:59:09 AM
1 Thank you for the opportunity to review the Vacate and Replat!

Upon reviewing the project and site location, El Paso County Parks staff has found that there are no immediate impacts to El Paso County parks, trails, open space, or other El Paso County Parks related items. Additionally, no parks fees will be required since no new lots are being created with this project.

El Paso County Parks staff will not have comments regarding this project.

Thank you!

Ashlyn Mathy
Parks Planner
Park Planning Division
El Paso County Parks Department
ashlynmathy@elpasoco.com
9/3/2026 9:59:09 AM
View EPC Environmental Services
9/1/2026 1:46:30 PM
1 9/1/2026 1:46:30 PM
E911 Authority - El Paso/Teller County
9/1/2026 8:04:46 AM
1 No action for E911 on this submittal.
Thank you.
Justin
9/1/2026 8:04:46 AM
Town of Monument Planning
8/27/2026 9:37:02 AM
1 No Comments 8/27/2026 9:37:02 AM