Project Review Comments
- File Number
- COM2612
- Project Name
- Walmart 4335 Falcon, CO - OPD Expansion
- Description
- Building expansion to accommodate online pick up and delivery operations & installation of EV chargers
- Location
- 11550 Meridian Market View, Falcon, CO 80831
- Parcels
- 5312101005 5312101005
- Applicant
-
Galloway & Company, Inc. Denver Office
Anna Betkowski ( AnnaBetkowski@GallowayUS.com )
(720) 705-6824 Anna Betkowski ( AnnaBetkowski@GallowayUS.com )
(720) 705-6824 - File Number
- COM2612
- Project Manager
- Ryan Howser
- Status
- Active
- Created
- 5/29/2026 11:00:31 AM
View: Project Documents
| Agency | Review # | Comment | ||
|---|---|---|---|---|
| View |
PCD Project Manager
7/9/2026 2:16:04 PM |
1 |
Review 1: PCD Planning Division has comments on the following documents: - Site Development Plan (attached) |
7/9/2026 2:16:04 PM |
|
EPC DPW Development Services - Engineering
7/9/2026 1:51:46 PM |
1 |
Engineering Review Ver.1 See comments on the following documents SDP_V1 Please provide a Letter of Intent that details the traffic generation and the ability to meet a TIS exception under Engineering Criteria Manual Section B.1.2.D. If not able to meet, then a Traffic Memo is required. In the Letter of Intent please discuss if chargers will be operable 24/7 when store is closed. No Engineering Comments on new building addition itself. No change to impervious % or runoff. A drainage report and CDs will not be required Road Impact fees will be based on new building addition and EV station. Building $5,498 /1000sqft 4886sqft = $26,863.22 EV Charging Stations $2,283 per station 70% reduction factor for EV station vs fuel pump. 4 EV Stations x $2283 x 30% = $2,739.6 TOTAL EPC ROAD IMPACT FEE = $29,602.82 Edward Schoenheit, Engineer E.P.C. Dept. of Public Works 2880 International Circle Colorado Springs, CO. 80910 Office: 719.520.6813 Cell: 719.502.9659 edwardschoenheit@elpasoco.com https://publicworks.elpasoco.com/department-public-works/county-engineer/ |
7/9/2026 1:51:46 PM | |
|
EPC DPW Stormwater
7/8/2026 11:02:51 AM |
1 |
Review 1: EPC DPW Stormwater has no comments. The proposed COM will not disturb over an acre. If the area of disturbance exceeds 1 acre at any time, all work must be stopped and an ESQCP must be obtained in order to resume construction. EPC Project Manager: no re-review necessary. Reviewed by: Mikayla Hartford, P.E. Senior Engineer - Stormwater 719.339.5053 MikaylaHartford@elpasoco.com |
7/8/2026 11:02:51 AM |