Project Review Comments

Back to List


File Number
COM2612
Project Name
Walmart 4335 Falcon, CO - OPD Expansion
Description
Building expansion to accommodate online pick up and delivery operations & installation of EV chargers
Location
11550 Meridian Market View, Falcon, CO 80831
Parcels
5312101005 5312101005
Applicant
Galloway & Company, Inc. Denver Office
Anna Betkowski ( AnnaBetkowski@GallowayUS.com )
(720) 705-6824
Anna Betkowski ( AnnaBetkowski@GallowayUS.com )
(720) 705-6824
File Number
COM2612
Project Manager
Ryan Howser
Status
Active
Created
5/29/2026 11:00:31 AM

View: Project Documents



Review Comments (3)

Link Agency Review # Comment
View PCD Project Manager
7/9/2026 2:16:04 PM
1 Review 1: PCD Planning Division has comments on the following documents:
- Site Development Plan (attached)
7/9/2026 2:16:04 PM
EPC DPW Development Services - Engineering
7/9/2026 1:51:46 PM
1 Engineering Review Ver.1

See comments on the following documents
SDP_V1

Please provide a Letter of Intent that details the traffic generation and the ability to meet a TIS exception under Engineering Criteria Manual Section B.1.2.D. If not able to meet, then a Traffic Memo is required.
In the Letter of Intent please discuss if chargers will be operable 24/7 when store is closed.

No Engineering Comments on new building addition itself.
No change to impervious % or runoff.
A drainage report and CDs will not be required

Road Impact fees will be based on new building addition and EV station.
Building
$5,498 /1000sqft
4886sqft = $26,863.22

EV Charging Stations
$2,283 per station
70% reduction factor for EV station vs fuel pump.
4 EV Stations x $2283 x 30% = $2,739.6
TOTAL EPC ROAD IMPACT FEE = $29,602.82


Edward Schoenheit, Engineer
E.P.C. Dept. of Public Works
2880 International Circle
Colorado Springs, CO. 80910
Office: 719.520.6813
Cell: 719.502.9659
edwardschoenheit@elpasoco.com
https://publicworks.elpasoco.com/department-public-works/county-engineer/
7/9/2026 1:51:46 PM
EPC DPW Stormwater
7/8/2026 11:02:51 AM
1 Review 1: EPC DPW Stormwater has no comments. The proposed COM will not disturb over an acre. If the area of disturbance exceeds 1 acre at any time, all work must be stopped and an ESQCP must be obtained in order to resume construction.

EPC Project Manager: no re-review necessary.

Reviewed by:
Mikayla Hartford, P.E.
Senior Engineer - Stormwater
719.339.5053
MikaylaHartford@elpasoco.com
7/8/2026 11:02:51 AM