Project Review Comments

Back to List


File Number
ASB2614
Project Name
Red Rock Valley Estates Water District Water Transmission Lines
Description
Install water transmission lines along existing utility corridors between the Keeton Water Treatment Plant and the Tallent Well, one potable water line for redundancy and one raw water line for more production, no development is proposed, no grading is proposed - The disturbed area is going to be more than one acre, so I’m expecting the County will want a SWMP, ESQCP, and such.
Parcels
7602400009 7602400009 7611002025 7611002025
Applicant
Terra Nova Engineering, Inc.
L Doucette ( luanne.rubey@tnesinc.com )
(719) 499-6422
L Doucette ( luanne.rubey@tnesinc.com )
(719) 499-6422
File Number
ASB2614
Project Manager
Zachary Jannusch
Status
Closed
Created
5/27/2026 3:37:31 PM

View: Project Documents



Review Comments (8)

Link Agency Review # Comment
EPC DPW Asset Management
7/20/2026 7:40:52 AM
2 This CAD file passes inspection.

Thank you very much,
Matt Goolsby
Senior Geospatial Analyst
719.352.5937
MatthewGoolsby@elpasoco.com
7/20/2026 7:40:52 AM
EPC DPW Development Services - Engineering
7/16/2026 9:09:19 AM
2 Review 2.

Engineering comments are resolved.

Reviewed by:
Joe Sandstrom, EIT, CFM
Associate Engineer
Department of Public Works
O: 719-520-6314
M: 719-505-0516
josephsandstrom@elpasoco.com
7/16/2026 9:09:19 AM
EPC DPW Development Services - Inspections
7/13/2026 3:58:05 PM
1 No Comments for Inspections 7/13/2026 3:58:05 PM
View EPC DPW Stormwater
7/8/2026 2:54:53 PM
1 Public Improvement Certification Letter comments 7/8/2026 2:54:53 PM
View EPC DPW Stormwater
7/8/2026 2:54:35 PM
1 As-built comments 7/8/2026 2:54:35 PM
EPC DPW Development Services - Engineering
7/8/2026 1:22:42 PM
1 Review 1.

Engineering comments on the following documents (to be uploaded by the project manager):
- As-built Drawings
- Public Improvement Certification Letter

Reviewed by:
Joe Sandstrom, EIT, CFM
Associate Engineer
Department of Public Works
O: 719-520-6314
M: 719-505-0516
josephsandstrom@elpasoco.com
7/8/2026 1:22:42 PM
EPC DPW Stormwater
7/8/2026 2:52:54 PM
1 EPC DPW Stormwater has no comments. Once other reviewer’s comments have also been resolved, this ASB review process will be deemed complete. At that time, this ASB file will be marked as Approved/Closed on EDARP and no further action is required by the Applicant. Please finalize all other PA/FA Punchlist items.

Reviewed by:
Zachary Jannusch
Associate Engineer - Stormwater
719.500.3170
ZacharyJannusch@elpasoco.com
7/8/2026 2:52:54 PM
EPC DPW Asset Management
6/29/2026 10:27:23 AM
1 Hello Terra Nova Engineering, in order to support the intake of your data into El Paso County’s GIS and Asset Management Systems, we kindly ask that you submit CAD files for your work in Colorado State Plane Central zone coordinates and includes horizontal control points (decimal lat/long coordinates to 6 decimal places will suffice). If you have questions about this request or how to get your data into the requested format, please let me know and I can assist you.

Thanks in advance,

Matt Goolsby
Senior Geospatial Analyst
719.352.5937
MatthewGoolsby@elpasoco.com
6/29/2026 10:27:23 AM