Project Review Comments
- File Number
- CDR268
- Project Name
- WHMD RWRF Stormwater Improvements CDR
- Description
- This project is a construction review drawing application for stormwater improvements to the existing Woodmen Hills Regional Water Reclamation Facility.
- Parcels
- 4230312001 4230312001
- Applicant
-
Kimley-Horn and Associates, Inc.
Grant Petik ( Grant.Petik@kimley-horn.com )
(719) 284-7276 Grant Petik ( Grant.Petik@kimley-horn.com )
(719) 284-7276 - EA Number
- EA2660
- File Number
- CDR268
- Project Manager
- Engineering Manager
- Status
- Active
- Created
- 5/13/2026 7:25:00 AM
View: Project Documents
| Agency | Review # | Comment | ||
|---|---|---|---|---|
| View |
County Attorney - Development Review
10/7/2026 11:09:02 AM |
4 |
Please see attached updated ROW License Agreement. Certain highlighted changes were accepted and additional edits are included in track changes. Please include Exhibit B to this agreement and fill in the Licensee information in the signature block (and the information of someone with authority to act on behalf of the Licensee). With respect to Exhibit B of the PCM Maintenance Agreement, please 1) add/label the location of the detention pond and 2) use a different color or shading to highlight where the access and maintenance easement is. The Exhibit/map should clearly depict where the easement is in relation to the detention pond(s). It should also abut a public road so the County has legal access. Reviewed by: Erika Keech, Sr. County Attorney, erikakeech2@elpasoco.com. |
10/7/2026 11:09:02 AM |
| View |
EPC DPW Development Services - Engineering
10/7/2026 10:20:06 AM |
4 | Construction Drawings comments | 10/7/2026 10:20:06 AM |
|
EPC DPW Development Services - Engineering
10/7/2026 10:18:06 AM |
4 |
Review 4. Engineering comments on the following documents: - Construction Drawings Please continue to to work with the County Attorney regarding any comments on the PCM Maintenance Agreement and ROW License Agreement. Reviewed by: Joe Sandstrom, EIT, CFM Associate Engineer Department of Public Works O: 719-520-6314 M: 719-505-0516 josephsandstrom@elpasoco.com |
10/7/2026 10:18:06 AM | |
| View |
EPC DPW Development Services - Engineering
9/24/2026 4:02:30 PM |
3 | Construction Drawings comments | 9/24/2026 4:02:30 PM |
|
EPC DPW Development Services - Engineering
9/24/2026 4:00:09 PM |
3 |
Review 3. Engineering comments on the following documents: - Construction Drawings Comments on legal documents will be returned by the County Attorney's office at a later date. Reviewed by: Joe Sandstrom, EIT, CFM Associate Engineer Department of Public Works O: 719-520-6314 M: 719-505-0516 josephsandstrom@elpasoco.com |
9/24/2026 4:00:09 PM | |
| View |
County Attorney - Development Review
9/23/2026 1:11:05 PM |
3 |
Please see attached consolidated edits to the maintenance agreement. For future submittals of this agreement, please fill in the highlighted name and title of individuals with authority to sign and include Exhibit B for review. Reviewed by: Erika Keech, Sr. County Attorney, erikakeech2@elpasoco.com. |
9/23/2026 1:11:05 PM |
| View |
EPC DPW Development Services - Engineering
8/27/2026 2:21:26 PM |
2 | CD comments | 8/27/2026 2:21:26 PM |
| View |
EPC DPW Development Services - Engineering
8/27/2026 2:21:02 PM |
2 | FDR comments | 8/27/2026 2:21:02 PM |
|
EPC DPW Stormwater
8/27/2026 1:40:37 PM |
2 |
Review 2: EPC DPW Stormwater comments have been resolved on the following document(s): - Drainage Letter - ESQCP - FAE - GEC Plan - GEC Checklist - Letter of Intent - SWMP - SWMP Checklist EPC DPW Stormwater has no further comments. EPC Project Manager: no re-review necessary. Reviewed by: Glenn Reese, P.E. Principal Engineer - Stormwater 719.675.2654 GlennReese@elpasoco.com |
8/27/2026 1:40:37 PM | |
|
EPC DPW Development Services - Engineering
8/27/2026 2:39:09 PM |
2 |
Review 2. Engineering comments on the following documents: - Construction Drawings - Drainage Letter Applicant Notes: - A license agreement is required for the private pipe located with the County Right of Way. Please include for engineering and county attorney review with the next submittal. Reviewed by: Joe Sandstrom, EIT, CFM Associate Engineer Department of Public Works O: 719-520-6314 M: 719-505-0516 josephsandstrom@elpasoco.com |
8/27/2026 2:39:09 PM | |
| View |
County Attorney - Development Review
8/25/2026 1:34:54 PM |
2 |
See attached edits to PCM Maintenance Agreement, uploaded 8/7/26. This appears to be the same version of the document, Senior County Attorney, Ms. Seago, previously circulated. I accepted the track changes. Please finalize the Exhibits and insert the appropriate signatories before signing/resubmitting. Reviewed by: Erika Keech, Sr. County Attorney. |
8/25/2026 1:34:54 PM |
| View |
EPC DPW Development Services - Engineering
7/15/2026 7:44:01 AM |
1 | Drainage Letter comments | 7/15/2026 7:44:01 AM |
| View |
EPC DPW Development Services - Engineering
7/14/2026 5:22:28 PM |
1 | Letter of Intent comments | 7/14/2026 5:22:28 PM |
| View |
EPC DPW Development Services - Engineering
7/14/2026 5:21:42 PM |
1 | CD comments | 7/14/2026 5:21:42 PM |
| View |
EPC DPW Development Services - Engineering
7/14/2026 5:21:05 PM |
1 | FAE comments | 7/14/2026 5:21:05 PM |
| View |
EPC DPW Stormwater
7/14/2026 2:20:06 PM |
1 | SWMP Checklist | 7/14/2026 2:20:06 PM |
| View |
EPC DPW Stormwater
7/14/2026 2:19:51 PM |
1 | SWMP | 7/14/2026 2:19:51 PM |
| View |
EPC DPW Stormwater
7/14/2026 2:19:35 PM |
1 | GEC Checklist | 7/14/2026 2:19:35 PM |
| View |
EPC DPW Stormwater
7/14/2026 2:19:21 PM |
1 | GEC Plan | 7/14/2026 2:19:21 PM |
| View |
EPC DPW Stormwater
7/14/2026 2:19:07 PM |
1 | ESQCP | 7/14/2026 2:19:07 PM |
|
EPC DPW Stormwater
7/14/2026 2:18:06 PM |
1 |
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded document(s): - Drainage Letter....(to be uploaded with Development Services comments) - ESQCP - FAE.....................(to be uploaded with Development Services comments) - GEC Plan - GEC Checklist - Letter of Intent.....(to be uploaded with Development Services comments) - SWMP - SWMP Checklist Please provide the following document(s) upon resubmittal (the planner will need to send an upload request): - PCM Applicability Form Reviewed by: Glenn Reese, P.E. Principal Engineer - Stormwater 719.675.2654 GlennReese@elpasoco.com |
7/14/2026 2:18:06 PM | |
|
EPC DPW Development Services - Engineering
7/14/2026 5:17:50 PM |
1 |
Review 1. Engineering comments in blue on the following documents: - Construction Drawings - FAE - Drainage Letter A license agreement is required with the next submittal for the private pipe located with the County Right of Way. Reviewed by: Joe Sandstrom, EIT, CFM Associate Engineer Department of Public Works O: 719-520-6314 M: 719-505-0516 josephsandstrom@elpasoco.com |
7/14/2026 5:17:50 PM | |
| View |
County Attorney - Development Review
7/10/2026 12:18:04 PM |
1 |
See edits and comments to attached DMA. Reviewed by: Erika Keech, Sr. County Attorney, erikakeech2@elpasoco.com. |
7/10/2026 12:18:04 PM |
EDARP