Project Review Comments
- File Number
- P2614
- Project Name
- Peyton Highway 310 Map Amendment
- Parcels
- 3300000217 3300000217
- Applicant
-
Cookie Investments LLC
Brynhildr Halsten ( brynhildr.halsten@hrgreen.com ) Brynhildr Halsten ( brynhildr.halsten@hrgreen.com ) - EA Number
- EA2656
- File Number
- P2614
- Project Manager
- Kylie Bagley
- Status
- Active
- Created
- 5/5/2026 9:29:52 AM
View: Project Documents | Submit/View Public Comment
| Agency | Review # | Comment | ||
|---|---|---|---|---|
| View |
PCD Project Manager
11/23/2026 10:43:25 AM |
1 | Traffic Impact Study redlines | 11/23/2026 10:43:25 AM |
| View |
PCD Project Manager
11/23/2026 10:42:56 AM |
1 | Zoning Map redlines | 11/23/2026 10:42:56 AM |
| View |
PCD Project Manager
11/23/2026 10:42:38 AM |
1 | Mineral Rights Certification redlines | 11/23/2026 10:42:38 AM |
| View |
PCD Project Manager
11/23/2026 10:42:20 AM |
1 | Letter of Intent redlines | 11/23/2026 10:42:20 AM |
|
PCD Project Manager
11/23/2026 10:40:03 AM |
1 |
The Planning Department has comments on the following document: -Letter of Intent -Mineral Rights Certification -Zoning Map Kylie Bagley, Principal Planner |
11/23/2026 10:40:03 AM | |
|
EPC DPW Stormwater
11/23/2026 7:37:25 AM |
1 |
EPC DPW Stormwater has no comments. Reviewed by: Zachary Jannusch Associate Engineer - Stormwater 719.500.3170 ZacharyJannusch@elpasoco.com |
11/23/2026 7:37:25 AM | |
|
Pikes Peak Regional Building Department
11/20/2026 3:00:21 PM |
1 |
The proposed project to rezone the vacant land and support future applications for single family subdivision. Enumerations has to comment on the rezone aspect of this project. Once a Preliminary or Development Plan is submitted, we will have further comments. Becky Allen Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org |
11/20/2026 3:00:21 PM | |
|
EPC DPW Development Services - Engineering
11/20/2026 1:29:31 PM |
1 |
Review 1: EPC Engineering comments have been provided on the following documents (to be uploaded by project manager): - Letter of Intent - Traffic Impact Study Reviewed by: Charlene Durham, PE charlenedurham@elpasoco.com |
11/20/2026 1:29:31 PM | |
|
Mountain View Electric Association, Inc.
11/19/2026 3:12:37 PM |
1 | MVEA has no comment. | 11/19/2026 3:12:37 PM | |
|
Ellicott Fire Protection District
11/18/2026 10:26:44 AM |
1 |
The letter of intent does not adequately explain how the Wildfire and Resiliency & Hazard Mitigation sections of the El Paso County Master Plan will be met in regards to the Colorado Wildfire Resiliency Code and fire protection or is the planner assigned to this project reviewing this submission for these elements? Ellicott Fire Protection District requests that further information on how wildfire mitigation, resiliency and hazard mitigation will be accomplished. Ellicott Fire Protection District efpdplanreview@gmail.com (719) 669-9037 |
11/18/2026 10:26:44 AM | |
|
EPC Parks Department
11/5/2026 2:33:24 PM |
1 |
The El Paso County Parks Department has reviewed the proposed rezone and has no objections to the request. The 2022 Parks Master Plan identifies the Judge Orr Secondary Regional Trail along the southern boundary of the property. While the County is not requesting a 25-foot trail easement or trail fees at the rezone stage, regional park fees and trail-related impacts will be evaluated during the review of any subsequent platting actions. Thank you. Ashlyn Mathy Parks Planner Park Planning Division El Paso County Parks Department Office: 719.520.6978 |
11/5/2026 2:33:24 PM | |
| View |
EPC Environmental Services
11/3/2026 2:48:13 PM |
1 | 11/3/2026 2:48:13 PM |
EDARP