Project Review Comments
- File Number
- COM266
- Project Name
- Starlight Auto Sales Site
- Description
- *UPDATE 7/13/2026: Applicant's team requested the project be reopened so that a revised site plan could be provided. *ORIGINAL: Request to approve the site and landscape plans as submitted for Special Use file #AL2523.
- Location
- 205 Main Street Colorado Springs, 80911
- Parcels
- 6514103020 6514103020
- Applicant
-
Starlight Auto Sales
Owner Mohammed Kareem ( starlightautosales205@gmail.com )
(719) 744-4144 Owner Mohammed Kareem ( starlightautosales205@gmail.com )
(719) 744-4144 - File Number
- COM266
- Project Manager
- Miranda Benson
- Status
- Active
- Created
- 3/12/2026 9:53:32 AM
View: Project Documents
| Agency | Review # | Comment | ||
|---|---|---|---|---|
|
PCD Project Manager
4/24/2026 8:13:20 AM |
1 |
Planning review complete. The submitted site plan correctly implements the approved Special Use request. No changes or corrections are needed. This will be forwarded to the Planning Manager for stamp of approval on the site plan. Once this is complete, the stamped version will be uploaded to EDARP. Please download this verision and include it with your future building permit submission to PPRBD. The Road Impact Fee will be due at the time of building permit. Please continue working with your Code Enforcement Officer to implement the required changes to the property! Thank you, Miranda Benson MirandaBenson2@elpasoco.com |
4/24/2026 8:13:20 AM | |
|
EPC DPW Development Services - Engineering
4/23/2026 7:24:50 AM |
1 |
Review 1. No engineering comments on the application. Road Impact Fee will be due at time of building permit and the rate is (Square Footage of addition building ) X ($447/1,000 square feet) . If the addition size remains 648 SF at building permit, the fee will be $289.65. Reviewed by: Joe Sandstrom, EI, Associate Engineer josephsandstrom@elpasoco.com (719) 520-6314 |
4/23/2026 7:24:50 AM | |
|
EPC DPW Stormwater
4/22/2026 12:21:13 PM |
1 |
Review 1: EPC DPW Stormwater has no comments. EPC Project Manager: no re-review necessary. Note: The proposed area of soil disturbance is less than 1 acre, therefore an ESQCP is not required. If the area of disturbance exceeds 1 acre at any time, all work must be stopped and an ESQCP must be obtained in order to resume construction. Reviewed by: Mikayla Hartford, P.E. Senior Engineer - Stormwater 719.339.5053 MikaylaHartford@elpasoco.com |
4/22/2026 12:21:13 PM |
EDARP