Project Review Comments

Back to List


File Number
COM2611
Project Name
Venetucci Farm Barn Remodel and Restroom Addition
Description
Renovate the existing barn used as an event facility, addition of a new standalone restroom facility, and a paved area for ADA parking. The project limits are confined to those small areas needing improvement, approximately 5,000 SF in total. The proposed event center within the barn is an approved use permitted by Special Use Permit completed in 2021 (AL2215). The existing barn and new restroom facility will be connected to a municipal water and wastewater system provided by the Security Water and Sanitation District. Inclusion into this district for municipal services was completed in 2020, Reception No. 220176019. As part of this project there are no major revisions anticipated to existing landscape, farm operations, parking, or traffic.
Parcels
6511300008 6511300008
Applicant
N.E.S. Inc.
Andrea Barlow ( abarlow@nescolorado.com )
(719) 471-0073
Andrea Barlow ( abarlow@nescolorado.com )
(719) 471-0073
File Number
COM2611
Project Manager
Lacey Dean
Status
Active
Created
2/24/2026 2:27:54 PM

View: Project Documents



Review Comments (4)

Link Agency Review # Comment
PCD Project Manager
5/21/2026 1:57:46 PM
1 Review 1: EPC Planning Division has no comments.

Reviewed by:
Lacey Dean, Associate Planner
laceydean2@elpasoco.com
5/21/2026 1:57:46 PM
View EPC DPW Development Services - Engineering
5/20/2026 4:34:22 PM
1 Road Impact Fee Acknowledgement Form 5/20/2026 4:34:22 PM
EPC DPW Development Services - Engineering
5/20/2026 4:35:03 PM
1 Review 1.

Engineering comments on the following documents (to be uploaded by the project manager):
- Road Impact Fee Acknowledgement Form (Traffic Study was submitted in this slot)

Please resubmit the signed pre-filled Road Impact Fee Acknowledgement Form (uploaded as a separate file) instead of the traffic study. There is no record that the Road Impact Fees were paid for the previously approved site development plan PPR2153. The Road Impact Fees shall be due prior to the approval of this application.

Reviewed by:
Joe Sandstrom, EIT, CFM
Associate Engineer
Department of Public Works
O: 719-520-6314
M: 719-505-0516
5/20/2026 4:35:03 PM
EPC DPW Stormwater
5/20/2026 2:25:02 PM
1 EPC DPW Stormwater has no comments.

Reviewed by:
Zachary Jannusch
Associate Engineer - Stormwater
719.500.3170
ZacharyJannusch@elpasoco.com
5/20/2026 2:25:02 PM