Project Review Comments

Back to List


File Number
SF2531
Project Name
Flying Horse North Filing No. 8
Parcels
5130000006 5130000006
Applicant
HR Green Inc.
Blaine Perkins ( blaine.perkins@hrgreen.com )
(719) 394-2430
Blaine Perkins ( blaine.perkins@hrgreen.com )
(719) 394-2430
File Number
SF2531
Project Manager
Ryan Howser
Status
Active
Created
10/9/2025 1:10:46 PM

View: Project Documents | Submit/View Public Comment



Review Comments (76)

Link Agency Review # Comment
View EPC DPW Development Services - Engineering
9/17/2026 11:18:09 AM
3 Drainage Report 9/17/2026 11:18:09 AM
View EPC DPW Development Services - Engineering
9/17/2026 11:03:23 AM
3 GEC Plan 9/17/2026 11:03:23 AM
View EPC DPW Development Services - Engineering
9/17/2026 11:00:55 AM
3 Construction Drawings 9/17/2026 11:00:55 AM
View EPC DPW Development Services - Engineering
9/17/2026 11:00:38 AM
3 Traffic Impact Study 9/17/2026 11:00:38 AM
EPC DPW Development Services - Engineering
9/17/2026 11:20:00 AM
3 DPW Engineering review 3 has comments on the following documents

- Traffic Impact Study
- Construction Drawings

Engineering comments have been resolved on the following documents

- Final Plat Drawings
- Deviation Request
- Financial Assurance Form

Please include signatures on engineering documents with the next submittal.

Review by
Bret Dilts, PE
bretdilts@elpasoco.com
719-520-6864
9/17/2026 11:20:00 AM
PCD Project Manager
9/16/2026 10:08:11 AM
3 Review 3: PCD Planning Division has completed its review and has no further comments at this time. 9/16/2026 10:08:11 AM
County Attorney - Development Review
9/15/2026 1:26:48 PM
3 1) Regarding the Detention Maintenance Agreement:

a) Paragraph 6 needs to include the language in the prior draft indicating the County may enter onto the property and "shall have the right to seek reimbursement from the responsible Parties for its actual costs and expenses in performing the work."

b) Regarding Exhibit B: if the easement is not granted over the entire property and is only over a portion of the property, then Exhibit B needs to clearly depict the portion of the property where the easement is granted. The map should visually depict the location of the easement in relation to the pond on the property. The easement must also abut a public road so the County has legal access.

c) The signatory for the Metro District needs to reflect that the individual signing has authority to sign on behalf of the Metro District for Filing No. 8. Please delete the language "No. 1-5" on the signature block.

2) Regarding the Subdivision Improvements Agreement, because this is being signed administratively, the Clerk and Recorder does not need to attest (and his signature line should be deleted) but it will need to be notarized. Please modify signature block as follows:

BOARD OF COUNTY COMMISSIONERS OF
EL PASO COUNTY, COLORADO


__________________________ By:________________________________________________
(Date Final Plat Approved) Meggan Herington, Executive Director
Planning and Community Development Department
Authorized signatory pursuant to LDC


The foregoing instrument was acknowledged before me this _______ day of ______________, 20__, by __________________, Executive Director of El Paso County Planning and Community Development Department.

Witness my hand and official seal.
My commission expires: __________________

_________________________________________
Notary Public


Approved as to form:

___________________________________
County Attorney’s Office
________________________________________________________________________________________________



Reviewed by: Erika Keech, Sr. County Attorney, erikakeech2@elpasoco.com.
9/15/2026 1:26:48 PM
Colorado Geological Survey
9/15/2026 11:40:30 AM
3 The available referral documents include the Final Plat (Edward-James Surveying, Inc., October 1, 2025), Construction Documents (HR Green, April 2, 2026), and other documents. The Soils and Geology Study (Entech Engineering, Inc., October 15, 2025) was provided in the previous submittals.

We offer the following additional comments:

1. Note 29 of the plat states, “Groundwater monitoring is to be conducted for one year for lots within shallow groundwater areas which are in areas in which proposed floor levels are at least three feet above maximum anticipated groundwater levels.” CGS continues to recommend that the county require groundwater monitoring/observation holes at the Flying Horse North to be checked seasonally.

2. According to the updated plat, the lots that are affected by drainages and potentially shallow groundwater include: 1, 2, 7, 8, 20, 21, 30, 33, 45, 49, and 50. CGS notes that setbacks appear to be established and noted on the plans. Building footprints should be outside the setback areas.

Provided Entech’s recommendations are strictly adhered to, CGS has no further comments.

Submitted 9/15/2026 by Amy Crandall, Engineering Geologist, Colorado Geological Survey (303-384-2632 or acrandall@mines.edu)
9/15/2026 11:40:30 AM
Black Forest Fire Protection District
9/14/2026 5:24:20 PM
3 Black Forest Fire Rescue has reviewed the submittal for Flying Horse North Filing No. 8. This review acknowledges the agreement reached during the previous meeting between Joe and the BFFR chiefs.

The fire-protection water-supply method remains under discussion and is not approved by BFFR. The proposal to use the pressurized Sundance system, including Hydrants 17 and 21 and the existing pump-house source, requires BFFR review before it may replace the proposed cisterns.

Provide documentation confirming the legal authority for BFFR and mutual-aid departments to access and use these water sources during an emergency. Identify responsibility for testing, maintenance, repairs, snow removal, vegetation control, and continuous access.

Provide flow-test documentation for Hydrants 17 and 21 demonstrating a minimum uninterrupted flow of 250 gpm for two hours. The final fire-protection plan shall show approved travel routes and confirm that every parcel entrance is within two miles of an approved water source. All designated water-supply locations shall have approved all-weather apparatus access and operating areas. Hydrants shall remain visible, unobstructed, protected from vehicle damage, marked, and accessible year-round. Final connections, color coding, signs, and clearances shall meet BFFR requirements. If the system cannot meet the legal, flow, duration, distance, and access requirements, additional hydrants, cisterns, or another approved water supply may be required. Plat approval does not constitute final BFFR acceptance of the water-supply arrangement.

Fire apparatus access roads shall maintain a minimum unobstructed width of 20 feet, vertical clearance of 13 feet 6 inches, an approved all-weather surface, grades not exceeding 10 percent unless specifically approved, and turning radii suitable for BFFR apparatus. A minimum unobstructed width of 26 feet shall be maintained near hydrants. Required access shall be completed before combustible construction begins.

The proposed deviation for the length of Sandbagger Drive does not waive fire-code access requirements. The final road system shall provide approved emergency access, apparatus turnaround, and evacuation capability. Any gates shall have an approved Knox emergency-access system and shall not reduce the required width. BFFR may require additional access, road interconnection, or turnaround improvements.

Flying Horse North Filing No. 8 is subject to the Colorado Wildfire Resiliency Code. The existing wildfire report does not replace CWRC review. Ground-truthing shall be completed and submitted to BFFR to establish the applicable hazard class. Each lot and structure shall comply with the assigned hazard-class requirements in effect when its permit is issued.

All homes and accessory structures shall have an approved Class A roof covering or Class A roof assembly. Exterior walls, siding, eaves, soffits, decks, projections, doors, windows, vents, and other components shall use approved noncombustible, ignition-resistant, ember-resistant, or other CWRC-compliant materials. Vinyl siding and other combustible exterior materials are prohibited where disallowed by the assigned hazard class.

Roof edges, eaves, soffits, attic vents, foundation vents, and other openings shall resist ember intrusion. Vent openings shall have approved ember-resistant protection or corrosion-resistant metal mesh with openings not exceeding 1/8 inch. Decks and similar projections shall use approved CWRC-compliant materials. Combustible storage beneath decks is prohibited, and required under-deck protection shall be provided. Combustible fencing shall not connect directly to a structure without an approved noncombustible transition.

Maintain a noncombustible zone within five feet of each structure, including beneath decks and projections. Combustible mulch, firewood, stored materials, dead vegetation, and similar ignition sources are prohibited in this zone. Vegetation from 5 to 30 feet shall be spaced and maintained so it does not create a continuous fuel path to structures. Extended defensible space and natural grasses shall be maintained under the CWRC and approved wildfire mitigation plan. Vegetation along evacuation routes, apparatus roads, hydrants, pull-offs, and roadway shoulders shall be managed to reduce fire exposure and preserve access.

The HOA or responsible entity shall maintain common-area defensible space, roadsides, emergency routes, hydrant areas, and other wildfire mitigation features. CWRC requirements shall be included in subdivision or recorded documents.

Each building requires separate review under the CWRC, the adopted 2021 International Fire Code, and its adopted appendices. Required documentation and inspections shall be completed before final approval or occupancy. Changes to the lot layout, water supply, access, roads, wildfire mitigation plan, or proposed construction shall be resubmitted to BFFR.
9/14/2026 5:24:20 PM
EPC DPW Stormwater
9/8/2026 12:32:56 PM
3 Review 3: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following document(s) to be uploaded by others:
- CDs
- Drainage Report
- GEC Plan

EPC DPW Stormwater comments have been resolved on the following document(s):
- PCM Applicability Form

Reviewed by:
Glenn Reese, P.E.
Principal Engineer - Stormwater
719.675.2654
GlennReese@elpasoco.com
9/8/2026 12:32:56 PM
Pikes Peak Regional Building Department
9/3/2026 10:28:21 AM
3 1. The following areas needs addressing corrected: Lot 42-14579 not 14529 Holmes Road, Lot 43-14629 not 14579 Homles Rd, Lot 44-14679 not 14629.
Add Tract A -14696 Wedge Trail-place north of lot 34, add 14581 to lot 42 to the south end for a well site is still needed. Move 14511 Homes Road from lots 41 and move to Tract D-this is where it was assigned.
2. 50 Lot and 3 tract with addresses, total fees are $530.00.
3. Standard final plat comments apply. See prior comments for details.


Amy Vanderbeek
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2930 E: Amy@pprbd.org
9/3/2026 10:28:21 AM
View EPC Parks Department
2/5/2026 1:29:58 PM
2 El Paso County Parks Department Final Comments, 2nd Submittal - Please See Attached Documentation (Originally endorsed by the El Paso County Park Advisory Board on November 12, 2025) 2/5/2026 1:29:58 PM
View Cherokee Metro Dist
2/4/2026 8:31:14 AM
2 Cherokee Metropolitan District does have a 24" Water line from Sundance Ranch that is in the general vicinity of the Flying Horse North development. Please see the attached image for reference.

The development's water is being provided by drilling their own wells and no sanitary sewer treatment is needed from Cherokee M. District.

No conflicts with Cherokee Metro District water infrastructure for this plan. No further review needed
2/4/2026 8:31:14 AM
Black Forest Fire Protection District
1/28/2026 11:10:13 PM
2 I agree with El Paso county roland Peterson The Fire Protection Report notes that cisterns will be provided but cisterns are not shown on the Final Plat or the Construction Drawings. Where will the cisterns be located and how will they be constructed? The cisterns' compliance with NFPA 1142 and NFPA 22 can not be determined with the information provided. How will the cisterns be filled?

Has the storage of water for fire protection been added to the State Water Finding?
1/28/2026 11:10:13 PM
View EPC DPW Development Services - Engineering
1/23/2026 10:51:24 AM
2 Drainage Report 1/23/2026 10:51:24 AM
View EPC DPW Development Services - Engineering
1/23/2026 10:50:56 AM
2 Financial Assurance Form 1/23/2026 10:50:56 AM
View EPC DPW Development Services - Engineering
1/23/2026 10:49:09 AM
2 Construction Drawings 1/23/2026 10:49:09 AM
View EPC DPW Development Services - Engineering
1/23/2026 10:48:42 AM
2 Deviation Request 1/23/2026 10:48:42 AM
View EPC DPW Development Services - Engineering
1/23/2026 10:47:59 AM
2 Traffic Impact Study 1/23/2026 10:47:59 AM
View EPC DPW Development Services - Engineering
1/23/2026 10:47:44 AM
2 Final Plat Drawings 1/23/2026 10:47:44 AM
EPC DPW Development Services - Engineering
1/23/2026 10:51:51 AM
2 DPW Engineering review 2 has comments on the following documents

- Final Plat Drawings
- Traffic Impact Study
- Deviation Request
- Construction Drawings
- Financial Assurance Form

Engineering comments have been resolved on the following documents

- Drainage Report - Final

Review by
Bret Dilts, PE
bretdilts@elpasoco.com
719-520-6864
1/23/2026 10:51:51 AM
View EPC DPW Stormwater
1/22/2026 2:47:14 PM
2 PCM Applicability Form 1/22/2026 2:47:14 PM
View EPC DPW Stormwater
1/22/2026 2:46:49 PM
2 GEC Plan 1/22/2026 2:46:49 PM
PCD Project Manager
1/22/2026 1:42:04 PM
2 Review 2: PCD Planning Division has completed its review and has provided comments in green on the following documents:
- Final Plat (to be uploaded by engineering)
1/22/2026 1:42:04 PM
View Colorado Geological Survey
1/21/2026 10:41:02 AM
2 1/21/2026 10:41:02 AM
County Attorney - Development Review
1/15/2026 11:33:48 AM
2 Please prepare SIA, DMA and License Agreement for signatures. No additional comments from County Attorney – Development Review at this time.

Reviewed by: Erika Keech, Sr. County Attorney, erikakeech2@elpasoco.com
1/15/2026 11:33:48 AM
EPC DPW Stormwater
1/22/2026 2:46:04 PM
2 Review 2: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded document(s):
- CDs.......................(to be uploaded by Development Services engineer)
- Drainage Report....(to be uploaded by Development Services engineer)
- GEC Plan
- PCM Applicability Form

EPC DPW Stormwater comments have been resolved on the following document(s):
- ESQCP
- FAE
- GEC Checklist
- PCM O&M Manual
- PCM Maintenance Agreement
- SWMP
- SWMP Checklist

Reviewed by:
Glenn Reese, P.E.
Principal Engineer - Stormwater
719.675.2654
GlennReese@elpasoco.com
1/22/2026 2:46:04 PM
Pikes Peak Regional Building Department
1/13/2026 10:42:54 AM
2 1. Addresses have already been assigned. Please add the addresses to the plat.
2. Standard Final Plat comments:
a. Enumerations will review the pre-plat (mylar) prior to plat for address placement, street names, and title block.

b. A $10.00 per lot and tract platting fee will be due at the time of the review of the pre-plat, (two addresses per lot and tract). If an address is not needed on a tract then no fee applies. Check should be made out to PIKES PEAK REGIONAL BUILDING DEPARTMENT or PPRBD. As of December 5th 2023, the fee for all credit/debit cards has changed from the flat 2.95% fee to the following: Over the phone Credit/Debit Card payments will be 2.3% and In-Person Debit Card payments will be 1.5% (in-person only). Paid directly to the Enumerations Department.

c. Pre-plat reviews can be reviewed via “pdf” or in-person. The pre-plat will be stamped by Enumerations for accuracy and returned to the applicant and the planner. All payments to be mailed to RBD via a check or credit card payment over the phone. Plats should not be recorded prior to Enumerations stamping the pre-plat and receiving payment of plat fees. If any pre-plat changes occur, even if changes do not apply to Enumerations, we still need to re-stamp the pre-plat. The Enumerations stamped pre-plat copy should match the recorded document minus a few signatures. If you would like an in-person review, please make an appointment on our website, https://www.pprbd.org/Home/BookAppt

d. A copy of the final recorded plat is required prior to plan submittal for RESIDENTIAL. A copy of the final recorded plat is required prior to approval in the Enumerations department on any COMMERCIAL plan submittal. Please email the Enumerations staff member that reviewed your project. Amy@pprbd.org; Brent@pprbd.org; or BeckyA@pprbd.org


Amy Vanderbeek
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2930 E: Amy@pprbd.org
1/13/2026 10:42:54 AM
911 Authority - El Paso/Teller County
1/12/2026 8:22:12 AM
2 No action for E911 on this submittal.
Thank you.
Justin
1/12/2026 8:22:12 AM
View Mountain View Electric Association, Inc.
11/18/2025 11:48:57 AM
1 11/18/2025 11:48:57 AM
View EPC Health Department
11/17/2025 12:48:02 PM
1 11/17/2025 12:48:02 PM
EPC Fire and Wildfire Program Manager
11/14/2025 8:35:41 AM
1 The Fire Protection Report notes that cisterns will be provided but cisterns are not shown on the Final Plat or the Construction Drawings. Where will the cisterns be located and how will they be constructed? The cisterns' compliance with NFPA 1142 and NFPA 22 can not be determined with the information provided. How will the cisterns be filled?

Has the storage of water for fire protection been added to the State Water Finding?

Roland Peterson
Fire Safety and Wildfire Mitigation Program Manager
Planning & Community Development
719.520.6075
rolandpeterson@elpasoco.com
11/14/2025 8:35:41 AM
View EPC DPW Development Services - Engineering
11/13/2025 11:47:07 PM
1 Final Drainage Report comments 11/13/2025 11:47:07 PM
View EPC DPW Development Services - Engineering
11/13/2025 11:45:45 PM
1 Construction Drawings comments 11/13/2025 11:45:45 PM
View EPC DPW Development Services - Engineering
11/13/2025 11:44:58 PM
1 Financial assurance estimate comments 11/13/2025 11:44:58 PM
View EPC DPW Development Services - Engineering
11/13/2025 11:44:13 PM
1 Traffic Study Comments 11/13/2025 11:44:13 PM
View EPC DPW Development Services - Engineering
11/13/2025 11:43:34 PM
1 Deviation Request comments 11/13/2025 11:43:34 PM
View EPC DPW Development Services - Engineering
11/13/2025 11:42:42 PM
1 GEC Plan comments 11/13/2025 11:42:42 PM
View EPC DPW Development Services - Engineering
11/13/2025 11:42:00 PM
1 Letter of Intent comments 11/13/2025 11:42:00 PM
View EPC DPW Development Services - Engineering
11/13/2025 11:41:25 PM
1 Final Plat comments 11/13/2025 11:41:25 PM
View PCD Project Manager
11/13/2025 2:51:14 PM
1 V1: DMA 11/13/2025 2:51:14 PM
View PCD Project Manager
11/13/2025 2:50:50 PM
1 V1: SWMP Checklist 11/13/2025 2:50:50 PM
View PCD Project Manager
11/13/2025 2:50:27 PM
1 V1: SWMP 11/13/2025 2:50:27 PM
View PCD Project Manager
11/13/2025 2:49:58 PM
1 V1: O&M 11/13/2025 2:49:58 PM
View PCD Project Manager
11/13/2025 2:49:39 PM
1 V1: PCM form 11/13/2025 2:49:39 PM
View PCD Project Manager
11/13/2025 2:49:13 PM
1 V1: GEC Checklist 11/13/2025 2:49:13 PM
View PCD Project Manager
11/13/2025 2:48:51 PM
1 V1: ESQCP 11/13/2025 2:48:51 PM
View PCD Project Manager
11/13/2025 2:44:39 PM
1 V1: WSIS 11/13/2025 2:44:39 PM
View PCD Project Manager
11/13/2025 2:44:21 PM
1 V1: SEO letter 11/13/2025 2:44:21 PM
View PCD Project Manager
11/13/2025 2:44:01 PM
1 V1: Soils & Geology report 11/13/2025 2:44:01 PM
View PCD Project Manager
11/13/2025 2:42:41 PM
1 V1: Noxious weed management plan 11/13/2025 2:42:41 PM
View PCD Project Manager
11/13/2025 2:42:03 PM
1 V1: Natural gas commitment letter 11/13/2025 2:42:03 PM
View PCD Project Manager
11/13/2025 2:41:38 PM
1 V1: CAO water finding 11/13/2025 2:41:38 PM
PCD Project Manager
11/13/2025 2:40:50 PM
1 Review 1: PCD Planning Division has completed its review and has provided comments in green on the following documents:
- CAO Water finding
- Natural Gas commitment letter
- Noxious Weed Management Plan
- Soils & Geology Report
- SEO Water Finding
- WSIS
- LOI (to be uploaded by engineering)
- Final Plat (to be uploaded by engineering)
11/13/2025 2:40:50 PM
View Colorado Geological Survey
11/13/2025 12:49:36 PM
1 See attached comments. 11/13/2025 12:49:36 PM
Colorado Springs Public Works
11/13/2025 8:20:08 AM
1 Traffic Engineering has no comments on this item.

Zaker Alazzeh, P.E.
Traffic Engineering Manager/Deputy City Traffic Engineer
City of Colorado Springs
(719) 385-5468
Zaker.Alazzeh@coloradosprings.gov
11/13/2025 8:20:08 AM
View Parks Advisory Board
11/13/2025 8:18:42 AM
1 El Paso County Parks Department, Final Comments - Please See Attached Documentation (Endorsed by the El Paso County Park Advisory Board on November 12, 2025) 11/13/2025 8:18:42 AM
EPC DPW Stormwater
11/13/2025 12:00:00 PM
1 Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following document(s) to be uploaded by the PM:
- CDs.......................(to be uploaded by Development Services engineer)
- Drainage Report....(to be uploaded by Development Services engineer)
- ESQCP
- FAE........................(to be uploaded by Development Services engineer)
- GEC Plan...............(to be uploaded by Development Services engineer)
- GEC Checklist
- PCM Applicability Form
- PCM Maintenance Agreement
- PCM O&M Manual
- SWMP
- SWMP Checklist

Please provide the following document(s) upon resubmittal (the planner will need to send an upload request):
- PCM - MHFD Detention Calcs or SDI Form

Reviewed by:
Glenn Reese, P.E.
Principal Engineer - Stormwater
719.675.2654
GlennReese@elpasoco.com
11/13/2025 12:00:00 PM
Colorado Springs Public Works
11/10/2025 1:49:04 PM
1 EDRD has no comments on this item.

Reviewed by Hao Vo, P.E.
hao.vo@coloradosprings.gov
11/10/2025 1:49:04 PM
EPC DPW Development Services - Engineering
11/10/2025 1:22:42 PM
1 DPW Engineering review 1 has comments on the following documents

- Final Plat Drawings
- Deviation Request
- Traffic Impact Study
- Drainage Report - Final
- Construction Drawings
- Financial Assurance Form

Review by
Bret Dilts, PE
bretdilts@elpasoco.com
719-520-6864
11/10/2025 1:22:42 PM
View County Attorney - Development Review
11/10/2025 11:24:36 AM
1 See edits to DMA. No comments with respect to SIA, License Agreement, Articles of Incorporation or HOA Bylaws.

Reviewed by: Erika Keech, Senior County Attorney, erikakeech2@elpasoco.com.
11/10/2025 11:24:36 AM
View Colorado Division of Water Resources
11/5/2025 6:39:10 PM
1 11/5/2025 6:39:10 PM
View EPC Parks Department
11/5/2025 3:29:03 PM
1 El Paso County Parks Department, Preliminary Comments - Please See Attached Documentation (To be presented to the El Paso County Park Advisory Board for their consideration and endorsement on Wednesday, November 12th, 2025) 11/5/2025 3:29:03 PM
PCD Administrative Notice
11/3/2025 11:54:10 AM
1 On 11/03/2025, PCD mailed "Notice of Application" letters to surrounding property owners within a 500-foot range (16 addresses). Copies of the notice, mailing labels, and selected range have been uploaded to the EDARP file. Cost of postage to be billed to the applicant = $11.84. JM 11/3/2025 11:54:10 AM
Colorado Springs Utilities, Dev, Svc.(includes water resources)
11/3/2025 9:59:14 AM
1 Based on Note # 22, Colorado Springs Utilities has no comment on this application. 11/3/2025 9:59:14 AM
Black Forest Fire Protection District
10/30/2025 2:17:19 PM
1 Black Forest Fire is currently working with our Fire Protection Engineer and Peregrine Fire on cistern sizes, location and type to sign off on what will work best for water supply in this area.
Herdt
10/30/2025 2:17:19 PM
View EPC Environmental Services
10/30/2025 12:55:19 PM
1 10/30/2025 12:55:19 PM
Colorado Springs Planning & Community Development
10/29/2025 11:00:49 AM
1 City Planning has no comment. 10/29/2025 11:00:49 AM
Pikes Peak Regional Building Department
10/28/2025 10:43:53 AM
1 1. Moving forward with addressing for this project, please clarify if Dogleg Court is being reconfigured, that was previously shown.
2. For lots 31-37 add the street name on sheets 4-5. Do you need addresses for tracts B & C, that were not seen prior.
3. After clarifying the question regarding Dogleg Court, the addresses should be add to the plat.


Amy Vanderbeek
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2930 E: Amy@pprbd.org
10/28/2025 10:43:53 AM
911 Authority - El Paso/Teller County
10/28/2025 9:12:10 AM
1 Comments for E911 as follows:

Streetnames previously approved.

Wedge Trl is not depicted on plan drawings, please notate the streetname on applicable pages.

Thank you
Justin
10/28/2025 9:12:10 AM
View Colorado Department of Transportation - Pueblo Office
10/27/2025 11:17:26 AM
1 Please see the attached letter for CDOT's comments regarding this development. 10/27/2025 11:17:26 AM
Academy SD 20 Building Fund
10/27/2025 7:35:49 AM
1 Academy District 20 is in receipt of File # SF2531 for approval of the Flying Horse North Filing No. 8 Final Plat.

The District is requesting fees in lieu of land dedication per the existing County Code for all residential units within this development.

The District is experiencing ongoing residential development. The District gained approximately 13,650 new residential units between 2018 and 2025 which included 5,650 Single Family, 1,225 Single Family Attached, and 6,800 Apartments as reported to the District by local developers. During that same timeframe, the District only experienced a total membership increase of 23 students. This information is updated annually in October.

A drop in the birth rate plus the significant increase in the cost of housing has slowed student growth in the District.

The District is able to serve each student who is a resident of District 20.

If you need additional information, please contact me.

Don Smith
Planning Consultant
10/27/2025 7:35:49 AM
Black Forest Land Use Committee
10/27/2025 3:45:22 AM
1 The Black Forest Land Use Committee has reviewed this proposal and recommends approval. 10/27/2025 3:45:22 AM
Colorado Parks and Wildlife
10/24/2025 12:26:28 PM
1 Colorado Parks and Wildlife (CPW) has reviewed the plans for Flying Horse North Filing No. 8 in El Paso County. Colorado Parks and Wildlife (CPW) is familiar with the site and has commented on the overall Flying Horse project area in the past. CPW recommends referring to those previous comments. Based on the location and proposed actions, CPW anticipates that this project's impacts on the wildlife resource would be negligible if our previous comments are taken into consideration.

We appreciate being allowed to comment. Please feel free to contact District Wildlife Manager, Aaron Berscheid, should you have any questions or require additional information at 719-439-9601 or via email at aaron.berscheid@state.co.us
10/24/2025 12:26:28 PM
RBD Floodplain
10/23/2025 2:50:54 PM
1 site is not in the floodplain , no comment 10/23/2025 2:50:54 PM
County Attorney - Water
10/23/2025 2:50:00 PM
1 Water sufficiency is being reviewed with the PUDSP amendment. 10/23/2025 2:50:00 PM