Project Review Comments
- File Number
- AL266
- Project Name
- 9755 Bennison Ter ALQ for Permanent Occupancy
- Description
- ALQ for Permanent Occupancy
- Parcels
- 5222002007 5222002007
- Applicant
-
Turner Forest
Araceli Turner ( celigarciaturner@gmail.com )
(719) 688-2361 Araceli Turner ( celigarciaturner@gmail.com )
(719) 688-2361 - File Number
- AL266
- Project Manager
- Joe Letke
- Status
- Active
- Created
- 10/9/2025 7:50:51 AM
View: Project Documents | Submit/View Public Comment
| Agency | Review # | Comment | ||
|---|---|---|---|---|
|
PCD Administrative Notice
3/4/2026 10:50:26 AM |
1 | On 03/03/2026, PCD mailed "Notice of Administrative Determination" letters for AL266 to surrounding property owners within a 500-foot range (16 addresses). The potential date an administrative decision can be made is 03/17/2026. Copies of the notice, mailing labels, and selected range have been uploaded to the EDARP file. Cost of postage = $11.84 MM | 3/4/2026 10:50:26 AM | |
| View |
PCD Project Manager
3/3/2026 1:27:30 PM |
1 | -V1 Site Plan | 3/3/2026 1:27:30 PM |
| View |
PCD Project Manager
3/3/2026 1:27:18 PM |
1 | -V1 Road Impact Fee Acknowledgement comments | 3/3/2026 1:27:18 PM |
| View |
PCD Project Manager
3/3/2026 1:26:51 PM |
1 | -V1 Letter of Intent | 3/3/2026 1:26:51 PM |
| View |
PCD Project Manager
3/3/2026 1:26:35 PM |
1 | -Road Impact Fee Form (Please complete) | 3/3/2026 1:26:35 PM |
|
EPC DPW Stormwater
3/3/2026 11:26:47 AM |
1 |
EPC DPW Stormwater has no comments. Reviewed by: Zachary Jannusch Associate Engineer - Stormwater 719.500.3170 ZacharyJannusch@elpasoco.com |
3/3/2026 11:26:47 AM | |
|
EPC DPW Development Services - Engineering
3/3/2026 1:20:31 PM |
1 |
AL266: 9755 Bennison Ter - ALQ for Permanent Occupancy EPC DPW DS- Engineering Review 1. Engineering Comments have been provided on the following documents (to be uploaded by Project Manager): V1- Road Impact Fee Acknowledgement Applicant Notes: The applicant must upload the revised and missing items indicated below with his/her resubmittal: V2 - The Revised Letter of Intent per comments in Blue Beam. V2 – The completed Road Impact Fee Acknowledgement form (please use and complete the correct form, this form is available at EPC County web page). FYI: 1. No additional access/driveway permit is required. 2. No shared access easement is required. Please let me know if you have any questions. Reviewed by: Jalal Jalal Saleh, PE jalalsaleh@elpasoco.com 719-520-7550 |
3/3/2026 1:20:31 PM | |
|
PCD Project Manager
3/2/2026 11:09:29 AM |
1 |
Planning has comments on the following version 1 documents: -Letter of Intent -Site Plan Drawing Joe Letke Planner JoeLetke@elpasoco.com |
3/2/2026 11:09:29 AM | |
|
Black Forest Fire Protection District
2/26/2026 2:44:18 PM |
1 | Black Forest Fire & Rescue has reviewed the associated documents submittal and offer no comments. | 2/26/2026 2:44:18 PM | |
| View |
EPC Environmental Services
2/24/2026 11:31:02 AM |
1 | 2/24/2026 11:31:02 AM | |
| View |
Mountain View Electric Association, Inc.
2/24/2026 7:58:25 AM |
1 | See attached comment letter | 2/24/2026 7:58:25 AM |
|
EPC Parks Department
2/19/2026 2:52:50 PM |
1 |
Thank you for the opportunity to review the Special Use for an ALQ! Upon reviewing the project and site location, El Paso County Parks staff has found that there are no immediate impacts to El Paso County parks, trails, open space, or other El Paso County Parks related items. El Paso County Parks staff will not have comments regarding this project. Thank you! Ashlyn Mathy Parks Planner Park Planning Division El Paso County Parks Department Office: 719.520.6999 |
2/19/2026 2:52:50 PM |
EDARP