Project Review Comments

Back to List


File Number
SF263
Project Name
North Bay at Lake Woodmoor Final Plat (2025)
Description
Updated Final Plat for North Bay at Lake Woodmoor for 6 residential lots. Subject to PUD approval.
Parcels
7111400007 7111400007 7111404111 7111404111
Applicant
HR Green Inc.
Blaine Perkins ( blaine.perkins@hrgreen.com )
(719) 394-2430
Blaine Perkins ( blaine.perkins@hrgreen.com )
(719) 394-2430
EA Number
EA24135
File Number
SF263
Project Manager
Joe Letke
Status
Active
Created
8/22/2025 1:48:52 PM

View: Project Documents | Submit/View Public Comment



Review Comments (75)

Link Agency Review # Comment
View PCD Project Manager
8/26/2026 8:54:06 AM
2 -V2_Utility Construction Drawings Comments 8/26/2026 8:54:06 AM
View PCD Project Manager
8/26/2026 8:53:50 AM
2 -+V2_Soils & Geology Report Comments 8/26/2026 8:53:50 AM
View PCD Project Manager
8/26/2026 8:53:30 AM
2 -V2_Road Impact Fee Acknowledgment Form Comments 8/26/2026 8:53:30 AM
View PCD Project Manager
8/26/2026 8:53:04 AM
2 -V2_No-Rise Certification Comments 8/26/2026 8:53:04 AM
View PCD Project Manager
8/26/2026 8:52:40 AM
2 -V2_Letter of Intent Comments 8/26/2026 8:52:40 AM
View PCD Project Manager
8/26/2026 8:52:06 AM
2 -V2_Grading & Erosion Control (GEC) Plan Comments 8/26/2026 8:52:06 AM
View PCD Project Manager
8/26/2026 8:51:43 AM
2 -V2_Financial Assurance Estimate (FAE) Form 8/26/2026 8:51:43 AM
View PCD Project Manager
8/26/2026 8:51:27 AM
2 -V2_Final Plat Drawings Comments 8/26/2026 8:51:27 AM
View PCD Project Manager
8/26/2026 8:50:37 AM
2 -V2_Drainage Report - Final Comments 8/26/2026 8:50:37 AM
View PCD Project Manager
8/26/2026 8:49:50 AM
2 -V2_Construction Drawings (PlansProfiles) 8/26/2026 8:49:50 AM
View PCD Project Manager
8/26/2026 8:49:34 AM
2 -V2_Channel Maintenance Agreement Comments 8/26/2026 8:49:34 AM
PCD Project Manager
8/26/2026 8:48:32 AM
2 Planning has comments on the following version 2 documents:

-Letter of Intent
-Final Plat Drawings
-Soils and Geo Report

Joe Letke
Planner
JoeLetke@elpasoco.com
8/26/2026 8:48:32 AM
EPC DPW Development Services - Engineering
8/25/2026 4:13:51 PM
3 SF263: North Bay at Lake Woodmoor PUD
DPW LD _ Engineering Review 2.
PUD252
EA24-135

Engineering Comments have been provided on the following documents (to be uploaded by Project Manager):

V2_Channel Maintenance Agreement (Reminder: Easements legal description to be provided in following submittal on page 16 after verifying there are no major comments remaining that may affect placement of easements.
V2_ Construction Drawings (Plans Profiles)
V2_Drainage Report - Final
V2_Final Plat Drawings
V2_Utility Plan
V2_Financial Assurance Estimate (FAE) Form
V2_Grading & Erosion Control (GEC) Plan
V2_No-Rise Certification
V2_Road Impact Fee Acknowledgment Form

The following documents have no comments:

V2_Letter of Intent LOI
V2_Soils & Geology Report

The comments for the following documents were provided with PUD252 review dated 8/12/2026 1:43:01 PM:

V3 - PUD Development Plans
V3 - Landscape Plan
V2_Traffic Impact Study



Applicant Notes:

I am requesting in person RCR “Review Comment Resolution” meeting prior to resubmittal to make sure all comments are addressed, so we can move this project forward to approval.

The applicant must upload to EDARP the revised items indicated below with his/her resubmittal:

V3_Channel Maintenance Agreement (Reminder: Easements legal description to be provided in following submittal on page 16 after verifying there are no major comments remaining that may affect placement of easements.
V3_ Construction Drawings (Plans Profiles)
V3_Drainage Report – Final
V3_Final Plat Drawings
V2_Utility Plan
V3_Financial Assurance Estimate (FAE) Form
V3_Grading & Erosion Control (GEC) Plan
V3_No-Rise Certification
V3_Road Impact Fee Acknowledgment Form

FYI:
1. Two driveway Access Permits shall be issued for this project.
2. ROW permit must be issued for the construction work for the relocated Stormwater pipeline for the portion in the ROW.
3. Basin fee & Bridge Fee are applicable. 2026 Basin fee is $27,282 per impervious acre and Bridge Fee is $1,492 per impervious acre.
4. The ECM Administrator will sign and date the plans, reports, and documents after you make your final submittal (make sure ALL comments are addressed before you make your final submittal and the plans, reports, and documents have no additional comments).


Reviewed by:

Jalal
Jalal Saleh, PE
jalalsaleh@elpasoco.com
361-687-3384

Jeff Rice, PE,
Drainage Planning Manager • Department of Transportation
JeffRice@elpasoco.com
8/25/2026 4:13:51 PM
View EPC DPW Stormwater
8/24/2026 4:03:47 PM
3 PCM Applicability Form comments 8/24/2026 4:03:47 PM
View EPC DPW Stormwater
8/24/2026 4:03:22 PM
3 PCM O&M Manual comments 8/24/2026 4:03:22 PM
County Attorney - Development Review
8/21/2026 10:02:56 AM
3 1) Regarding the SIA, please fill in the blanks. SIA will be reviewed in a future submittal once it is completed.

2) Regarding the Stormwater Maintenance Agreement, thank you for making previous changes. Please submit Exhibit B in future submittal. It should include a map clearly depicting the location of the easement in relation to the pond.

Erika Keech
Sr. County Attorney
8/21/2026 10:02:56 AM
Colorado Geological Survey
8/20/2026 9:10:11 AM
3 Colorado Geological Survey (CGS) Review Comments
Project: North Bay at Lake Woodmoor – Final Plat SF263; CGS Project EP-17-0024_8
As requested in El Paso County email dated August 3, 2026, CGS reviewed the North Bay at Lake Woodmoor Final Plat submittal, located at 39.1048, -104.8561, including the March 11, 2026 CTL|Thompson Geologic Hazards Evaluation and Preliminary Geotechnical Investigation Update, Final Plat, construction drawings, grading and erosion control plans, and Final Drainage Report.
CGS's August 11, 2026 review of PUD252 addressed the geologic compatibility of the six-lot development configuration; this Final Plat review considers the additional access, drainage, and channel-stabilization information submitted under SF263.
CGS understands that the proposed development consists of six single-family residential lots with two private access drives and associated grading, utilities, and drainage improvements. The primary unresolved geologic hazard for the Final Plat is fluvial erosion and scour associated with the Lake Fork of Dirty Woman Creek drainage corridor.
Fluvial Hazard Evaluation
CGS generally agrees with the geologic interpretation and identification of geologic hazards presented in the submitted reports. The Final Drainage Report evaluates hydraulic conditions within the Lake Fork corridor, identifies areas of elevated erosive potential, and proposes channel stabilization. The residential lots are located outside the mapped and modeled 100-year floodplain; however, the Redbridge Point access crosses the floodplain and associated channel improvements are located within the active drainage corridor.
The submitted information does not clearly demonstrate whether scour, stream-bank erosion, or lateral channel migration could undermine the Redbridge Point access or associated improvements. For the County to determine that the proposed subdivision is compatible with the identified hazard, these fluvial processes should be addressed in relation to the proposed access and channel stabilization.
CGS recommends that the applicant's engineer supplement the submitted evaluation to address scour, stream-bank erosion, and lateral channel migration at the Redbridge Point access and associated channel improvements, and demonstrate that the proposed stabilization approach is appropriate for the anticipated conditions without materially increasing fluvial-hazard exposure upstream or downstream.
CGS has no objection to conditional approval of SF263, provided the fluvial-hazard issue identified above is resolved to the satisfaction of El Paso County.
Submitted August 20, 2026 by Jonathan R. Lovekin, Senior Engineering Geologist, Colorado Geological Survey, jlovekin@mines.edu
8/20/2026 9:10:11 AM
EPC DPW Stormwater
8/24/2026 3:30:49 PM
3 Review 2: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded document(s):
- Drainage Report ...................(to be uploaded by DS engineer)
- GEC Plan ..............................(to be uploaded by DS engineer)
- PCM Applicability Form
- PCM O&M Manual

EPC DPW Stormwater comments have been resolved on the following document(s):
- Channel Maintenance Agreement
- ESQCP
- FAE
- GEC Checklist
- PCM Maintenance Agreement
- SWMP
- SWMP Checklist

Reviewed by:
Zachary Jannusch
Associate Engineer - Stormwater
719.500.3170
ZacharyJannusch@elpasoco.com
8/24/2026 3:30:49 PM
County Attorney - Water
8/17/2026 11:04:25 AM
3 Please address comments from 3/3/26. 8/17/2026 11:04:25 AM
EPC Sheriff's Department
8/9/2026 6:02:34 PM
3 This application states it is covered by Monument Fire for fire protection. The Fire Commitment Letter and application review should be completed by Monument Fire, not EPSO Wildland. Thank you. 8/9/2026 6:02:34 PM
911 Authority - El Paso/Teller County
8/3/2026 2:38:49 PM
3 Comments for E911 as follows:

Redbridge Pt – Previously approved and reserved
Shoreditch Hts – Previously approved and reserved

No action for E911 on this submittal.

Thank you.
Justin
8/3/2026 2:38:49 PM
US Army Corps of Engineers-Pueblo
8/3/2026 2:20:36 PM
3 If the applicant has determined the activity would involve the discharge of dredged or fill material into an aquatic resource (e.g. stream, creek, wetland, pond, etc.), please have them contact our office at SPA-RD-CO@usace.army.mil for a determination of permitting requirements. 8/3/2026 2:20:36 PM
RBD Floodplain
8/3/2026 2:04:19 PM
3 when ready please submit directly to the Regional Floodplain office your application for work in the floodplain.
No further comment .
8/3/2026 2:04:19 PM
Central CO Conservation District
4/2/2026 9:20:09 PM
1 FYI, this should have been sent to the El Paso County Conservation District as this is their area, as Central Colorado Conservation District does not cover this property. Thank you! 4/2/2026 9:20:09 PM
County Attorney - Development Review
3/12/2026 9:57:39 AM
2 It is not clear why two Stormwater Facility Maintenance Agreements were submitted.

I previously submitted comments to the Word version of the document titled: "PCM Maintenance Agreement."

A PDF "Channel Maintenance Agreement" was also uploaded. Word versions of such documents are required.

If the applicant would like to submit the Maintenance Agreement PDF exhibits for review, please submit them separately and label them accordingly.

The submitted "Channel Maintenance Agreement" PDF appears to have the same issues as the Word version with respect to the name of the HOA.

Please address the previous comments in the PCM Maintenance Agreement and, unless engineering requires two agreements, submit one version in WORD (editable format) for subsequent review.

Erika Keech
Sr. County Attorney
3/12/2026 9:57:39 AM
PCD Administrative Notice
3/11/2026 2:42:11 PM
1 On 03/11/2026, PCD mailed "Notice of Application" letters to surrounding property owners within a 500-foot range (68 addresses). Copies of the notice, mailing labels, and selected range have been uploaded to the EDARP file. Cost of postage to be billed to the applicant = $50.32. JM 3/11/2026 2:42:11 PM
View PCD Project Manager
3/11/2026 11:45:05 AM
1 V1_Water Resources Report 3/11/2026 11:45:05 AM
View PCD Project Manager
3/11/2026 11:44:50 AM
1 V1_Wastewater Treatment Report 3/11/2026 11:44:50 AM
View PCD Project Manager
3/11/2026 11:44:32 AM
1 V1_Soils & Geology Report 3/11/2026 11:44:32 AM
View PCD Project Manager
3/11/2026 11:44:16 AM
1 V1_Natural Landforms, Vegetation, Riparian Analysis 3/11/2026 11:44:16 AM
View PCD Project Manager
3/11/2026 11:43:58 AM
1 V1_Letter of Intent 3/11/2026 11:43:58 AM
View PCD Project Manager
3/11/2026 11:43:36 AM
1 V1_Final Plat Drawings 3/11/2026 11:43:36 AM
View PCD Project Manager
3/11/2026 11:42:53 AM
1 V1_Commitment letter from water service provider 3/11/2026 11:42:53 AM
View PCD Project Manager
3/11/2026 11:42:34 AM
1 V1_Commitment letter from waste water service provider 3/11/2026 11:42:34 AM
PCD Project Manager
3/11/2026 11:37:09 AM
1 EPC Planning Review 1 Comments: Please see comments on the following documents:
- V1_Final Plat Drawings
- V1_Letter of Intent
- V1_Commitment letter from water service provider
- V1_Commitment letter from waste water service provider
- V1_Natural Landforms, Vegetation, Riparian Analysis
- V1_Soils & Geology Report
- V1_Water Resources Report
- V1_Wastewater Treatment Report

Reviewed by:
Maria Lancto, AICP, Senior Planner
marialancto@elpasoco.com
719-520-6447
3/11/2026 11:37:09 AM
View EPC DPW Stormwater
3/10/2026 4:43:11 PM
1 PCM Maintenance Agreement Redlines 3/10/2026 4:43:11 PM
View EPC DPW Stormwater
3/10/2026 4:42:02 PM
1 SWMP Redlines 3/10/2026 4:42:02 PM
View EPC DPW Stormwater
3/10/2026 4:41:40 PM
1 SWMP Checklist Redlines 3/10/2026 4:41:40 PM
View EPC DPW Stormwater
3/10/2026 4:41:18 PM
1 PCM Applicability Form Redlines 3/10/2026 4:41:18 PM
View EPC DPW Stormwater
3/10/2026 4:40:51 PM
1 GEC Checklist Redlines 3/10/2026 4:40:51 PM
View EPC DPW Stormwater
3/10/2026 4:40:27 PM
1 ESQCP Redlines 3/10/2026 4:40:27 PM
View EPC DPW Stormwater
3/10/2026 4:39:55 PM
1 Utilities Drawings Redlines 3/10/2026 4:39:55 PM
View EPC DPW Stormwater
3/10/2026 4:39:26 PM
1 SIA Redlines 3/10/2026 4:39:26 PM
View EPC DPW Stormwater
3/10/2026 4:39:10 PM
1 RIF Acknowledgement Form Redlines 3/10/2026 4:39:10 PM
View EPC DPW Stormwater
3/10/2026 4:38:29 PM
1 GEC Plan Redlines 3/10/2026 4:38:29 PM
View EPC DPW Stormwater
3/10/2026 4:38:07 PM
1 FAE Form Redlines 3/10/2026 4:38:07 PM
View EPC DPW Stormwater
3/10/2026 4:37:44 PM
1 Drainage Report Redlines 3/10/2026 4:37:44 PM
View EPC DPW Stormwater
3/10/2026 4:37:21 PM
1 CD Redlines 3/10/2026 4:37:21 PM
View EPC DPW Stormwater
3/10/2026 4:37:02 PM
1 Channel Maintenance Agreement Redlines 3/10/2026 4:37:02 PM
EPC DPW Development Services - Engineering
3/9/2026 3:45:25 PM
1 SF263: North Bay at Lake Woodmoor PUD; PUD252 and EA24135
DPW Review 1.
Engineering Comments have been provided on the following documents (to be uploaded by Project Manager):

V1 - LOI
V1 – Final plat Drawings
V1 - Drainage Report
V1 - Grading & Erosion Control (GEC) Plan
V1 - FAE
V1 – The completed Road Impact Fee Acknowledgement form
V1 - Utility Construction Drawings
V1 – Construction Drawings (Plans. Profiles)

Applicant Notes:

I am requesting a response letter with your next submittal explaining how each comment was addressed (please copy and paste all comments to your response letter and respond below each comment). Please do not use the words done, fixed, etc. instead explain how you addressed each comment and indicate the sheet number.

Please email me at the email address indicated below a request for a TEAM’S RCR “Review Comment Resolution” meeting prior to resubmittal to make sure all comments are addressed, so we can move this project forward to approval.
The applicant must upload to EDARP the revised items indicated below with his/her resubmittal:

V2 - LOI
V2 – Final plat Drawings
V2 - Drainage Report
V2 - Grading & Erosion Control (GEC) Plan
V2 - FAE
V2 – The completed Road Impact Fee Acknowledgement form
V2 - Utility Construction Drawings
V2 – Construction Drawings (Plans. Profiles)
Missing: Submit V3 – PUD Development Plans (See V2 – PUD Development Plans comments dated 2/11/2026 under EDARP number PUD252)
Missing: Submit Two Joint access easement are required for driveways accessing lots 1-3 and 4-6.

FYI:
1. The ECM Administrator will sign and date the plans, reports, and documents after you make your final submittal (make sure ALL comments are addressed before you make your final submittal and the plans, reports, and documents have no additional comments).
2. Two access permits will be issued.


Reviewed by:


Jalal
Jalal Saleh, PE
jalalsaleh@elpasoco.com
3/9/2026 3:45:25 PM
EPC DPW Development Services - Engineering
3/10/2026 3:33:52 PM
1 SF263: North Bay at Lake Woodmoor PUD; PUD252 and EA24135
DPW Review 1.
Engineering Comments have been provided on the following documents (to be uploaded by Project Manager):

V1 - LOI
V1 – Final plat Drawings
V1 - Drainage Report
V1 - Grading & Erosion Control (GEC) Plan
V1 - FAE
V1 – The completed Road Impact Fee Acknowledgement form
V1 - Utility Construction Drawings
V1 – Construction Drawings (Plans. Profiles)
V1- Channel Maintenance Agreement
V1- Subdivision Improvement Agreement; this Agreement is required for Common Improvements (NOT for Public Improvements, no Public Improvements are called for on the plans).

Applicant Notes:

I am requesting a response letter with your next submittal explaining how each comment was addressed (please copy and paste all comments to your response letter and respond below each comment). Please do not use the words done, fixed, etc. instead explain how you addressed each comment and indicate the sheet number.

Please email me at the email address indicated below a request for a TEAM’S RCR “Review Comment Resolution” meeting prior to resubmittal to make sure all comments are addressed, so we can move this project forward to approval.
The applicant must upload to EDARP the revised items indicated below with his/her resubmittal:

V2 - LOI
V2 – Final plat Drawings
V2 - Drainage Report
V2 - Grading & Erosion Control (GEC) Plan
V2 - FAE
V2 – The completed Road Impact Fee Acknowledgement form
V2 - Utility Construction Drawings
V2 – Construction Drawings (Plans. Profiles)
V2-Channel Maintenance Agreement
V2- Subdivision Improvement Agreement
Missing: Submit V3 – PUD Development Plans (See V2 – PUD Development Plans comments dated 2/11/2026 under EDARP number PUD252)
Missing: Submit Two Joint access easement are required for driveways accessing lots 1-3 and 4-6.

FYI:
1. The ECM Administrator will sign and date the plans, reports, and documents after you make your final submittal (make sure ALL comments are addressed before you make your final submittal and the plans, reports, and documents have no additional comments).
2. Two access permits will be issued.


Reviewed by:


Jalal
Jalal Saleh, PE
jalalsaleh@elpasoco.com
3/10/2026 3:33:52 PM
View Mountain View Electric Association, Inc.
3/9/2026 2:35:28 PM
1 See attached comment letter 3/9/2026 2:35:28 PM
EPC DPW Stormwater
3/10/2026 3:19:56 PM
1 Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded document(s):
- Channel Maintenance Agreement
- Drainage Report
- ESQCP
- FAE
- GEC Checklist
- GEC Plan
- PCM Applicability Form
- PCM Maintenance Agreement
- SWMP
- SWMP Checklist

Please provide the following document(s) upon resubmittal (the planner will need to send an upload request):
- PCM O&M Manual

Reviewed by:
Zachary Jannusch
Associate Engineer - Stormwater
719.500.3170
ZacharyJannusch@elpasoco.com
3/10/2026 3:19:56 PM
Pikes Peak Regional Building Department
3/6/2026 8:59:50 AM
1 Enumerations has the following comments:

1. Enumerations is in agreement with the 911 authority that the drive accesses need to be named private street. Once the names of the private streets are agreed upon, they need to be shown on the plat.
2. Once the street names are agreed upon, submit a copy of the plat to Enumerations for address assignment. When the addressing is returned, the addresses must be added to the plat in the appropriate location.
3. Enumerations will review the mylar prior to recording for addressing, street names, and title block. An Enumerations fee of $10 per lot/tract to which an address has been assigned.
4. No plans for any of these lots can be submitted prior to Enumerations having a copy of the final recorded plat in our records.

Brent Johnson
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2888 E: brent@pprbd.org W: pprbd.org
3/6/2026 8:59:50 AM
View Woodmoor Water and Sanitation District
3/5/2026 4:41:53 PM
1 Please see the attached documents for all WWSD Comments. 3/5/2026 4:41:53 PM
View Woodmoor Water and Sanitation District
3/5/2026 4:40:54 PM
1 Please see the attached documents for all WWSD Comments. 3/5/2026 4:40:54 PM
View County Attorney - Development Review
3/5/2026 1:04:56 PM
1 See edits to attached Maintenance Agreement.

Erika Keech
Sr. County Attorney
erikakeech2@elpasoco.com
3/5/2026 1:04:56 PM
View County Attorney - Development Review
3/5/2026 1:03:45 PM
1 See edits to attached SIA.

Erika Keech
Sr. County Attorney
erikakeech2@elpasoco.com
3/5/2026 1:03:45 PM
County Attorney - Water
3/3/2026 1:50:54 PM
1 1) On the Water Supply Information Summary and Water Resource Report, please list the water demand in acre-feet, listing out any irrigation uses or stock watering separately.
2) The commitment letter needs to identify the amount of water being committed in acre-feet. See also the letter from the Colorado Division of Water dated February 26, 2026 with the same request.
3) Additionally, pursuant to Sections 8.4.7 (B)(3)(c)(v) and (e) of the Land Development Code the Water Resource Report needs to address more recent information regarding available water supply of Woodmoor Water & Sanitation (provides information from 14 years ago).
3/3/2026 1:50:54 PM
View EPC Parks Department
3/3/2026 8:25:14 AM
1 See attached documentation for the associated review by Parks staff.

Thank you!

Ashlyn Mathy
Parks Planner
Park Planning Division
El Paso County Parks Department
Office 719.520.6999
3/3/2026 8:25:14 AM
View Tri-Lakes-Monument Fire Protection District
2/27/2026 10:37:37 AM
1 Colorado Wildfire Resiliency Code 2/27/2026 10:37:37 AM
View Tri-Lakes-Monument Fire Protection District
2/27/2026 10:36:33 AM
1 1. Plan is acceptable for firefighting water supply.
2. Plan is acceptable for emergency access.
3. Development will be subject to the Colorado Wildfire Resiliency Code Class 2 requirements if permitted after 6/30/26 (see attached).
4. See Monument Fire Development Guide for addition information.
2/27/2026 10:36:33 AM
Black Hills Energy-Aquila
2/26/2026 4:41:03 PM
1 BHE has facilities in area. BHE will Serve. Please call in locates before excavation. 2/26/2026 4:41:03 PM
View Colorado Division of Water Resources
2/26/2026 2:59:59 PM
1 2/26/2026 2:59:59 PM
Upper Black Squirrel Creek GWMD
2/26/2026 12:30:57 PM
1 This is not in the Upper Black Squirrel Creek GWMD 2/26/2026 12:30:57 PM
Colorado Springs Planning & Community Development
2/26/2026 11:28:46 AM
1 City Planning has no comment. 2/26/2026 11:28:46 AM
Monument
2/26/2026 10:31:28 AM
1 No comments of concern from Town of Monument 2/26/2026 10:31:28 AM
911 Authority - El Paso/Teller County
2/24/2026 8:20:09 AM
1 Comments for E911 as follows:

For the purpose of efficient emergency response, the two private access drives for both lots 1-3 and lots 4-6 will require streetnames.

Two streetnames were previously approved for this development (Shoreditch Heights and Redbridge Point). You are welcome to use these, or submit other desired names.

Streetnaming information (criteria, existing/reserved names) can be found on our website at:
https://www.elpasoteller911.org/street-emergency-number-databases

Please ensure that the streetnames are depicted on the plan drawings.

Thank you
Justin
2/24/2026 8:20:09 AM
Colorado Parks and Wildlife
2/25/2026 2:11:52 PM
1 No Comments 2/25/2026 2:11:52 PM
Colorado Geological Survey
2/18/2026 1:31:04 PM
1 Colorado Geological Survey (CGS) Review Comment – Resubmittal (Response #6)
File Number: SF263
Project: North Bay at Lake Woodmoor Final Plat
The January 27, 2026 Letter of Intent states under “Geologic Hazards” that no geologic hazards preclude development of the site and that the 2016 CTL|Thompson Soils and Geologic Hazard Report is being resubmitted with the application.
As stated in CGS resubmittal review comments dated December 16, 2025, and reiterated in CGS Response #5 dated February 2, 2026, the 2016 report was prepared for a materially different development configuration (28-unit layout with different grading, building envelopes, and floodplain interface). The current proposal consists of a revised 6-lot configuration with different building footprints, grading, access drives, and open space layout.
Because the development configuration has materially changed, the 2016 geologic hazards report is not technically applicable to the current PUD Development Plan and Final Plat. Density reduction alone does not establish geologic hazard adequacy under a revised layout.
No updated geologic hazards evaluation addressing the current development configuration has been submitted.
An updated geologic hazards evaluation prepared for the current configuration is required to complete CGS review. The updated report must evaluate site-specific geologic hazards under the current design, including groundwater conditions, slope stability, erosion potential, and any retaining structures.
Because the required updated geologic hazards evaluation has not been submitted, CGS cannot complete its review and cannot support approval of the current application. CGS review may proceed upon submittal and review of an updated geologic hazards evaluation prepared for the current development configuration.
Submitted 2/18/2026 by Jonathan R. Lovekin, Senior Engineering Geologist, Colorado Geological Survey, jlovekin@mines.edu
2/18/2026 1:31:04 PM
View EPC Environmental Services
2/18/2026 10:37:09 AM
1 2/18/2026 10:37:09 AM
Colorado Department of Transportation - Pueblo Office
2/18/2026 9:01:07 AM
1 CDOT has no comments regarding this development. 2/18/2026 9:01:07 AM
Road Impact Fee Administrator
2/18/2026 8:57:35 AM
1 victoriachavez@elpasoco.com
Please change the name of the document listed as "Road Impact Fee Credit Agreement." This is actually a "Road Impact Fee Acknowledgement Form." The credit agreement is a different document.

Thank you for updating the form name. No further comments at this time.
2/18/2026 8:57:35 AM
Colorado Springs Utilities, Dev, Svc.(includes water resources)
2/17/2026 11:45:49 AM
1 This project is well outside of Colorado Springs Utilities territory. We have no comments.
Blanche Ludiker 719-668-8111
2/17/2026 11:45:49 AM
RBD Floodplain
2/17/2026 11:04:03 AM
1 show floodplain extents and BFE lines on plat.
seal and sign No rise certification form