Project Review Comments
- Project Name
- Haven Valley Filing No. 1A PUDSP & Final Plat Amendment
- Description
- Administrative PUD/SP Amendment to adjust lot coverage standards. Associated with Final Plat amendment for modified lot lines for Lots 1-9 and 14-27.
- Location
- Parcels
- 6512200001 6512200001
- Applicant
-
Challenger Homes Land Development
Erin Smith ( Esmith@ChallengerHomes.com )
(719) 598-5192 x1024 Erin Smith ( Esmith@ChallengerHomes.com )
(719) 598-5192 x1024 - EA Number
- EA20157
- File Number
- PUDSP257
- Project Manager
- Ryan Howser
- Status
- Active
- Created
- 8/19/2025 1:42:01 PM
View: Project Documents
| Agency | Comment | ||
|---|---|---|---|
|
PCD Project Manager
11/13/2025 8:56:35 AM |
Review 2: PCD Planning Division has no comments on this item. Please note when you come in to drop off the documents for recordation, regarding the revised PUD and plat drawings, you may remove the bubbled changes on the version to be recorded. Please coordinate with PCD Project Manager regarding potential recording dates. | 11/13/2025 8:56:35 AM | |
|
EPC DPW Development Services - Engineering
11/12/2025 7:52:33 AM |
Review 2. DS Engineering comments are resolved. Reviewed by: Joe Sandstrom, EI, Associate Engineer josephsandstrom@elpasoco.com (719) 520-6314 |
11/12/2025 7:52:33 AM | |
|
EPC DPW Stormwater
11/10/2025 5:03:11 PM |
Review 2: EPC DPW Stormwater comments have been resolved on the following document(s): -LOI EPC DPW Stormwater has no further comments. EPC Project Manager: no re-review necessary. Reviewed by: Glenn Reese, P.E. Principal Engineer - Stormwater 719.675.2654 GlennReese@elpasoco.com |
11/10/2025 5:03:11 PM | |
| View |
PCD Project Manager
10/10/2025 11:23:55 AM |
V1: PUD Development Plan comments | 10/10/2025 11:23:55 AM |
| View |
PCD Project Manager
10/10/2025 11:23:41 AM |
V1: LOI comments (Engineering and Stormwater comments only) | 10/10/2025 11:23:41 AM |
| View |
PCD Project Manager
10/10/2025 11:23:21 AM |
V1: Final Plat comments | 10/10/2025 11:23:21 AM |
|
PCD Project Manager
10/10/2025 11:23:01 AM |
Review 1: PCD Planning Division comments have been provided (in green) on the following uploaded documents: - PUD Development Plan - Final Plat (includes Engineering comments) |
10/10/2025 11:23:01 AM | |
|
PCD Administrative Notice
10/10/2025 10:46:26 AM |
On 10/10/2025, PCD mailed "Notice of Administrative Determination" letters for PUDSP257 to surrounding property owners within a 500-foot range (182 addresses). The potential date an administrative decision can be made is 10/24/2025. Copies of the notice, mailing labels, and selected range have been uploaded to the EDARP file. Cost of postage = $134.68. JM | 10/10/2025 10:46:26 AM | |
|
EPC DPW Development Services - Engineering
10/8/2025 11:42:18 AM |
Review 1. Engineering comments on the following documents (to be uploaded by the project manager): - Letter of Intent - Final Plat Documents to be included with the next submittal: - Amended Drainage Report/Drainage Letter Note to Project Manager: Please allow for a full 21-day review cycle upon resubmittal as a drainage report was previously requested but was not submitted. Reviewed by: Joe Sandstrom, EI, Associate Engineer josephsandstrom@elpasoco.com (719) 520-6314 |
10/8/2025 11:42:18 AM | |
|
EPC DPW Stormwater
10/8/2025 12:38:10 PM |
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded document(s): -LOI...(to be uploaded by PM) The proposed amendment will make Tract C larger, which will have no negative impact on stormwater quality that would require a change in drainage calcs or anything else stormwater related. However, I do have comments in the LOI related to the proposed increase in lot coverage. Also, I will review the required Drainage Report with the next submittal. Reviewed by: Glenn Reese, P.E. Principal Engineer - Stormwater 719.675.2654 GlennReese@elpasoco.com |
10/8/2025 12:38:10 PM |
EDARP