Project Review Comments
- Project Name
- Haven Valley Filing No. 1A PUDSP & Final Plat Amendment
- Description
- Administrative PUD/SP Amendment to adjust lot coverage standards. Associated with Final Plat amendment for modified lot lines for Lots 1-9 and 14-27.
- Location
- Parcels
- 6512200001 6512200001
- Applicant
- 
            Challenger Homes Land Development
                
 Erin Smith ( Esmith@ChallengerHomes.com )
 (719) 598-5192 x1024 Erin Smith ( Esmith@ChallengerHomes.com )
 (719) 598-5192 x1024
- EA Number
- EA20157
- File Number
- PUDSP257
- Project Manager
- Ryan Howser
- Status
- Active
- Created
- 8/19/2025 1:42:01 PM
View: Project Documents
| Agency | Comment | ||
|---|---|---|---|
| View | PCD Project Manager 10/10/2025 11:23:55 AM | V1: PUD Development Plan comments | 10/10/2025 11:23:55 AM | 
| View | PCD Project Manager 10/10/2025 11:23:41 AM | V1: LOI comments (Engineering and Stormwater comments only) | 10/10/2025 11:23:41 AM | 
| View | PCD Project Manager 10/10/2025 11:23:21 AM | V1: Final Plat comments | 10/10/2025 11:23:21 AM | 
| PCD Project Manager 10/10/2025 11:23:01 AM | Review 1: PCD Planning Division comments have been provided (in green) on the following uploaded documents: - PUD Development Plan - Final Plat (includes Engineering comments) | 10/10/2025 11:23:01 AM | |
| PCD Administrative Notice 10/10/2025 10:46:26 AM | On 10/10/2025, PCD mailed "Notice of Administrative Determination" letters for PUDSP257 to surrounding property owners within a 500-foot range (182 addresses). The potential date an administrative decision can be made is 10/24/2025. Copies of the notice, mailing labels, and selected range have been uploaded to the EDARP file. Cost of postage = $134.68. JM | 10/10/2025 10:46:26 AM | |
| EPC DPW Development Services - Engineering 10/8/2025 11:42:18 AM | Review 1. Engineering comments on the following documents (to be uploaded by the project manager): - Letter of Intent - Final Plat Documents to be included with the next submittal: - Amended Drainage Report/Drainage Letter Note to Project Manager: Please allow for a full 21-day review cycle upon resubmittal as a drainage report was previously requested but was not submitted. Reviewed by: Joe Sandstrom, EI, Associate Engineer josephsandstrom@elpasoco.com (719) 520-6314 | 10/8/2025 11:42:18 AM | |
| EPC DPW Stormwater 10/8/2025 12:38:10 PM | Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded document(s): -LOI...(to be uploaded by PM) The proposed amendment will make Tract C larger, which will have no negative impact on stormwater quality that would require a change in drainage calcs or anything else stormwater related. However, I do have comments in the LOI related to the proposed increase in lot coverage. Also, I will review the required Drainage Report with the next submittal. Reviewed by: Glenn Reese, P.E. Principal Engineer - Stormwater 719.675.2654 GlennReese@elpasoco.com | 10/8/2025 12:38:10 PM | 
 EDARP
                    EDARP