Project Review Comments
- Project Name
- 7955 W Hwy 24 Side Yard Setback Relief
- Description
- Administrative Relief to allow a 4' side yard setback where 5' is required in R-T (Residential Topographic) zoning district. Table 5-4, Footnote 12: "The side yard setback is 25 feet when the lot is 5 acres or larger, or 5 feet if the lot is less than 5 acres." Land Development Code 1971 R-T lot size minimum was 10,000 sq. ft. Lot creation date: 2-16-1968.
- Location
- Parcels
- 8326200049 8326200049
- Applicant
-
McCracken Professional Group LLC
Matt McCracken ( office@mccrackenpros.com )
(719) 491-6198 Matt McCracken ( office@mccrackenpros.com )
(719) 491-6198 - File Number
- ADR258
- Project Manager
- Miranda Benson
- Status
- Active
- Created
- 8/15/2025 11:20:16 AM
View: Project Documents
| Agency | Comment | ||
|---|---|---|---|
|
EPC DPW Development Services - Engineering
9/16/2025 4:45:09 PM |
No additional engineering comments. reviewed by: Daniel Torres danieltorres@elpasoco.com |
9/16/2025 4:45:09 PM | |
|
PCD Project Manager
9/16/2025 2:47:10 PM |
V2_Planning review complete. All planning comments (green boxes) were addressed and resolved. No further comments. In preparation for approval (all review comments must be resolved), an Administrative Approval Letter/Packet will be drafted for the Planning Manager's signature. Once this is completed, the final copy will be uploaded to the EDARP project under "Approved Documents". Include this letter with future building permit submittals through PPRBD. Thank you, Miranda Benson mirandabenson2@elpasoco.com |
9/16/2025 2:47:10 PM | |
| View |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
9/12/2025 1:18:10 PM |
Colorado Springs Utilities has no further comment for this Administrative Relief application. | 9/12/2025 1:18:10 PM |
| View |
PCD Project Manager
9/8/2025 11:44:59 AM |
ADR258 V1_Planning Review Comments | 9/8/2025 11:44:59 AM |
| View |
PCD Project Manager
9/8/2025 11:44:49 AM |
V1_Site Plan Drawing_COMMENTS | 9/8/2025 11:44:49 AM |
| View |
PCD Project Manager
9/8/2025 11:44:38 AM |
V1_Letter of Intent_COMMENTS | 9/8/2025 11:44:38 AM |
|
PCD Project Manager
9/8/2025 11:44:27 AM |
V1_Planning review complete. Comments need to be addressed on the following documents: - Letter of Intent - Site Plan Drawing The Planning Review checklist was added for reference. This does not need to be returned! Thank you, Miranda Benson mirandabenson2@elpasoco.com |
9/8/2025 11:44:27 AM | |
| View |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
9/4/2025 12:22:07 PM |
Please address the following comments: Label height of new retaining wall. Show and label existing underground electric service line "Secondary UG Conductor:12HY-2" to ensure no conflict. Call 811 locates to confirm exact location. |
9/4/2025 12:22:07 PM |
|
EPC DPW Stormwater
9/2/2025 4:05:03 PM |
Review 1: EPC DPW Stormwater has no comments. The proposed project will not disturb greater than 1 ac of soil. EPC Project Manager: no re-review necessary. Reviewed by: Mikayla Hartford, P.E. Engineer - Stormwater 719.339.5053 MikaylaHartford@elpasoco.com |
9/2/2025 4:05:03 PM | |
|
EPC DPW Development Services - Engineering
9/2/2025 2:49:54 PM |
Review 1. Engineering comments in blue on the following document (to be uploaded by the project manager at a later date): - Letter of Intent - Site Plan Drawing Reviewed by: Joe Sandstrom, EI, Associate Engineer josephsandstrom@elpasoco.com (719) 520-6314 |
9/2/2025 2:49:54 PM | |
|
PCD Administrative Notice
8/27/2025 11:26:25 AM |
On 08/27/2025, PCD mailed "Notice of Administrative Determination" letters for ADR258 to surrounding property owners within a 500-foot range (19 addresses). The potential date an administrative decision can be made is 09/10/2025. Copies of the notice, mailing labels, and selected range have been uploaded to the EDARP file. Cost of postage = $14.06 JM | 8/27/2025 11:26:25 AM |
EDARP