Project Review Comments
- File Number
- COM2522
- Project Name
- Crossroads Chapel Minor Parking Lot Expansion
- Description
- Expansion of parking lot to serve the existing church use.
- Parcels
- 6205000019 6205000019
- Applicant
-
Crossroads Chapel SBC
Crossroads Elder/Trustee Terry Etnyre ( etnyres1@comcast.net )
(719) 377-1573 Crossroads Elder/Trustee Terry Etnyre ( etnyres1@comcast.net )
(719) 377-1573 - File Number
- COM2522
- Project Manager
- Miranda Benson
- Status
- Closed
- Created
- 7/21/2025 11:55:51 AM
View: Project Documents
| Agency | Review # | Comment | ||
|---|---|---|---|---|
|
PCD Project Manager
9/22/2025 3:51:38 PM |
2 |
V2_Planning review complete. All planning comments (green boxes) have been resolved. The COM- Site Plan Drawing will be sent to the Planning Manager for stamp of approval. Once this is received, it will be uploaded under "Approved Documents". I will also be waiting for the Drainage Letter to be signed by Engineering. Once both are uploaded to the EDARP file, the project will be closed/complete. Thank you, Miranda Benson mirandabenson2@elpasoco.com |
9/22/2025 3:51:38 PM | |
|
EPC DPW Development Services - Engineering
9/22/2025 12:05:57 PM |
2 |
Review 2. Engineering comments have been resolved. Engineering documents are routed for signature. Approved documents will be uploaded by the project manager. Reviewed by: Joe Sandstrom, EI, Associate Engineer josephsandstrom@elpasoco.com (719) 520-6314 |
9/22/2025 12:05:57 PM | |
|
EPC DPW Stormwater
9/16/2025 10:51:56 AM |
2 |
Review 2: EPC DPW Stormwater comments have been resolved on the following document(s): - Drainage Letter EPC DPW Stormwater has no further comments. EPC Project Manager: no re-review necessary. Reviewed by: Glenn Reese, P.E. Principal Engineer - Stormwater 719.675.2654 GlennReese@elpasoco.com |
9/16/2025 10:51:56 AM | |
| View |
PCD Project Manager
9/2/2025 8:56:52 AM |
1 | V1_Drainage Letter_COMMENTS | 9/2/2025 8:56:52 AM |
| View |
PCD Project Manager
9/2/2025 8:56:44 AM |
1 | V1_Landscape Plan_COMMENTS | 9/2/2025 8:56:44 AM |
| View |
PCD Project Manager
9/2/2025 8:56:33 AM |
1 | V1_Lighting Plan_COMMENTS | 9/2/2025 8:56:33 AM |
| View |
PCD Project Manager
9/2/2025 8:56:20 AM |
1 | V1_Site Plan Drawing_COMMENTS | 9/2/2025 8:56:20 AM |
|
PCD Project Manager
9/2/2025 8:55:55 AM |
1 |
V1_Planning review complete. Planning comments are in green boxes. Very minor comments were added to the following documents: - Site Plan Drawing - Lighting Plan - Landscaping Plan Thank you, Miranda Benson mirandabenson2@elpasoco.com |
9/2/2025 8:55:55 AM | |
|
EPC DPW Development Services - Engineering
8/28/2025 4:38:16 PM |
1 |
Review 1. Engineering comments provided on the following documents in blue: - Drainage Letter - Site Plan Feel free to contact me if you have any questions regarding engineering comments. Reviewed by: Joe Sandstrom, EI, Associate Engineer josephsandstrom@elpasoco.com (719) 520-6314 |
8/28/2025 4:38:16 PM | |
|
EPC DPW Stormwater
8/28/2025 2:28:56 PM |
1 |
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following document that will be uploaded by the PM: - Drainage Letter Reviewed by: Glenn Reese, P.E. Principal Engineer - Stormwater 719.675.2654 GlennReese@elpasoco.com |
8/28/2025 2:28:56 PM |
EDARP