Project Review Comments

Back to List


File Number
COM2522
Project Name
Crossroads Chapel Minor Parking Lot Expansion
Description
Expansion of parking lot to serve the existing church use.
Parcels
6205000019 6205000019
Applicant
Crossroads Chapel SBC
Crossroads Elder/Trustee Terry Etnyre ( etnyres1@comcast.net )
(719) 377-1573
Crossroads Elder/Trustee Terry Etnyre ( etnyres1@comcast.net )
(719) 377-1573
File Number
COM2522
Project Manager
Miranda Benson
Status
Closed
Created
7/21/2025 11:55:51 AM

View: Project Documents



Review Comments (10)

Link Agency Review # Comment
PCD Project Manager
9/22/2025 3:51:38 PM
2 V2_Planning review complete. All planning comments (green boxes) have been resolved.

The COM- Site Plan Drawing will be sent to the Planning Manager for stamp of approval. Once this is received, it will be uploaded under "Approved Documents". I will also be waiting for the Drainage Letter to be signed by Engineering. Once both are uploaded to the EDARP file, the project will be closed/complete.

Thank you,

Miranda Benson
mirandabenson2@elpasoco.com
9/22/2025 3:51:38 PM
EPC DPW Development Services - Engineering
9/22/2025 12:05:57 PM
2 Review 2.

Engineering comments have been resolved. Engineering documents are routed for signature. Approved documents will be uploaded by the project manager.

Reviewed by:
Joe Sandstrom, EI, Associate Engineer
josephsandstrom@elpasoco.com
(719) 520-6314
9/22/2025 12:05:57 PM
EPC DPW Stormwater
9/16/2025 10:51:56 AM
2 Review 2: EPC DPW Stormwater comments have been resolved on the following document(s):
- Drainage Letter

EPC DPW Stormwater has no further comments. EPC Project Manager: no re-review necessary.

Reviewed by:
Glenn Reese, P.E.
Principal Engineer - Stormwater
719.675.2654
GlennReese@elpasoco.com
9/16/2025 10:51:56 AM
View PCD Project Manager
9/2/2025 8:56:52 AM
1 V1_Drainage Letter_COMMENTS 9/2/2025 8:56:52 AM
View PCD Project Manager
9/2/2025 8:56:44 AM
1 V1_Landscape Plan_COMMENTS 9/2/2025 8:56:44 AM
View PCD Project Manager
9/2/2025 8:56:33 AM
1 V1_Lighting Plan_COMMENTS 9/2/2025 8:56:33 AM
View PCD Project Manager
9/2/2025 8:56:20 AM
1 V1_Site Plan Drawing_COMMENTS 9/2/2025 8:56:20 AM
PCD Project Manager
9/2/2025 8:55:55 AM
1 V1_Planning review complete. Planning comments are in green boxes. Very minor comments were added to the following documents:

- Site Plan Drawing
- Lighting Plan
- Landscaping Plan

Thank you,
Miranda Benson
mirandabenson2@elpasoco.com
9/2/2025 8:55:55 AM
EPC DPW Development Services - Engineering
8/28/2025 4:38:16 PM
1 Review 1.

Engineering comments provided on the following documents in blue:
- Drainage Letter
- Site Plan

Feel free to contact me if you have any questions regarding engineering comments.

Reviewed by:
Joe Sandstrom, EI, Associate Engineer
josephsandstrom@elpasoco.com
(719) 520-6314
8/28/2025 4:38:16 PM
EPC DPW Stormwater
8/28/2025 2:28:56 PM
1 Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following document that will be uploaded by the PM:
- Drainage Letter

Reviewed by:
Glenn Reese, P.E.
Principal Engineer - Stormwater
719.675.2654
GlennReese@elpasoco.com